[Adams County](https://plannednearby.com/c/adams-pa/) · [Straban Township](https://plannednearby.com/c/adams-pa/straban-township) · #2024-05-granite-lake-residential-development-str · [Large housing developments (100+ homes) tracker](https://plannednearby.com/topics/large-housing/)

# Granite Lake residential development, Straban

Straban Township, PA · 265 homes, single-family homes

In short: **Granite Lake residential development, Straban** is a single-family home development in Straban Township, Adams County, PA. It would add 265 homes. Its estimated construction value is about $148.4M, a rough estimate from its size. As of November 24, 2026, it is approved according to web research. Latest record: Gettysburg Connection reported that the Straban supervisors gave the preliminary plan conditional approval, with a 60-unit first phase, and the township… What usually happens next: building and stormwater permits; site work often starts within 3 to 12 months.

Stage: Approved · Gettysburg Connection reported that the Straban supervisors gave the preliminary plan conditional approval, with a 60-unit first phase, and the township agendas list the Phase 1 final plan as still pending. · web research checked Nov 10, 2026 · [source](https://gettysburgconnection.org/?p=77607) AI research

Usually next: building and stormwater permits; site work often starts within 3 to 12 months.

## About this project

A residential development in Straban Township with 189 single-family homes and 76 townhomes, for 265 units total.

- **Plan type:** SLD submission (stage not stated)
- **Land use:** single-family

## Project history

- **2024-05-15** · #2024-05-granite-lake-residential-development-str · SLD submission (stage not stated) · 265 lots/units

[County plan review office →](https://www.adamscountypa.gov/departments/officeofplanninganddevelopment/panningcommission)

Map pin is approximate.

## The full picture AI research · Nov 10, 2026

Granite Lake is a planned neighborhood at 250 Natural Springs Road in Straban Township, behind the Giant grocery store and Gettysburg Marketplace near Gettysburg. County records describe 265 homes: 189 single-family houses and 76 townhomes. The streets would be built around an existing lake, and one existing lakeside home would be folded into the plan. A county table lists the site at about 143 acres. That figure is unconfirmed.

The township supervisors gave the preliminary plan conditional approval on June 3, 2024. The first phase is 60 homes. Conditions include following the township engineer's review letter and waiting until October to remove trees, because of a bat-habitat restriction.

The Phase 1 final plan has been on township agendas since 2025. It was on the agenda for Nov. 2, 2026, with a deadline of Nov. 5, 2026, and no outcome had been posted. No listings, model homes, builder site or construction reports turned up.

### What it could mean nearby

- Main access would be Natural Springs Road, which the plan would widen, so traffic on that road and at the shopping center is likely to increase.
- Up to 265 new households, built in phases with 60 homes first, would add demand for schools and local services.
- The homes would connect to public water and sewer. The developer still needs approval from the sewer and water authority.
- PennDOT must approve highway access before building permits can be issued.

### Where it stands

The preliminary plan was conditionally approved June 3, 2024, and the Phase 1 final land development plan has been pending before the supervisors since 2025, with a Nov. 5, 2026 deadline to act. After final approval, the developer still needs state and local permits, such as highway access and stormwater permits, before building. Note: The Gettysburg Connection article gives 256 total homes, while county records give 265 (189 single-family and 76 townhomes); the page's headline 'single-family' type also leaves out the townhomes.

- **Nov 2, 2026** Phase 1 final land development plan on the supervisors' agenda, must act by Nov. 5; outcome not posted
- **Aug 3, 2026** Phase 1 final plan on the supervisors' agenda again, with an Aug. 5 deadline
- **May 4, 2026** Phase 1 final plan on the supervisors' agenda, with a May 6 deadline
- **Feb 2, 2026** Phase 1 final plan on the supervisors' agenda, with a Feb. 4 deadline
- **Jun 3, 2024** Supervisors gave the preliminary plan conditional approval
- **May 15, 2024** County planning commission meeting reviewed the plan

### Around the web

- [Two large residential-commercial projects move forward on York Rd. in Gettysburg](https://gettysburgconnection.org/?p=77607) — Gettysburg Connection · Jun 7, 2024Reports the conditional preliminary approval, 60-unit first phase, conditions, Natural Springs Road access and the engineering firms involved.
- [Board of Supervisors Meetings](https://www.strabantownship.com/category/board-of-supervisors-meetings/) — Straban Township · Nov 2, 2026Agendas for Feb., May, Aug. and Nov. 2026 list the Phase 1 final land development plan at 250 Natural Springs Road with act-by deadlines and no posted outcomes.
- [Board of Supervisors, June 3, 2024](https://www.strabantownship.com/2024/05/28/board-of-supervisors-june-3-2024/) — Straban Township · May 28, 2024Lists the Preliminary Subdivision Plan at 250 Natural Springs Road for action by June 6, 2024.

Planning terms explained

- **Preliminary plan:** The first formal layout of lots, streets and utilities that a municipality reviews before the detailed final plan.
- **Final land development plan:** The detailed, engineered plan that must be approved before construction can begin.
- **Conditional approval:** Approval that depends on the developer meeting listed requirements.
- **Must act by:** The legal deadline by which the supervisors must decide on a plan, unless the developer agrees to extend it.
- **Phase 1:** The first stage of a multi-stage project, here 60 of the planned homes.

Researched by AI from public sources on Nov 10, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

## How to comment officially

**For this project:** The Straban Township Board of Supervisors decides the final plan at its public meetings, and residents can comment there or through the township office.

In Pennsylvania, Straban Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

- Speak at the Straban Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Straban Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.

[Find Straban Township's meeting agendas →](https://www.google.com/search?q=Straban+Township+PA+planning+commission+meeting+agenda)

Comments on this page are not sent to officials and are not part of the public record.

## Scope estimate for contractors

Estimated construction value: **$148.4M**

- ~8,480 roofing squares
- ~265 HVAC systems
- ~265 kitchens / 530+ bathrooms
- ~742,000 sq ft of finished living space

**Contractor or supplier?** Get projects like this in the counties you work, by email. [Get free contractor alerts →](https://plannednearby.com/contractors)

## More projects nearby

- [Subdivision into two residential lots, Cavalry Field Rd](https://plannednearby.com/x/adams-sld-24-002) — same area · 2 homes, single-family homes · Straban Township · filed 2024-07-17
- [9,000 sq ft pole building on New Chester Rd](https://plannednearby.com/x/adams-sld-25-092) — same area · 9,000 sq ft non-residential, retail & commercial · Straban Township · filed 2026-01-21
- [Adams Miller solar project, Straban Twp](https://plannednearby.com/x/adams-adams-miller-solar-project-straban-twp-391819) — same area · government & utilities · Straban Township · filed 2024-07-17
- [300-unit apartment complex, Hunterstown Rd](https://plannednearby.com/x/adams-sld-22-023) — same area · 300 homes, apartments · Straban Township · filed 2024-07-17
- [Agricultural lot split into two lots](https://plannednearby.com/x/adams-agricultural-lot-split-into-two-lots-237dd0) — same area · lot line change · Straban Township · filed 2025-08-20
- [Gettysburg Plant Building Expansion](https://plannednearby.com/x/adams-sld-24-008) — same area · 64,995 sq ft non-residential, industrial · Straban Township · filed 2024-02-21

[See everything nearby on a map →](https://plannednearby.com/near#39.88215,-77.16614,Straban%20Township)

---

Source page: https://plannednearby.com/x/adams-2024-05-granite-lake-residential-development-str

Data from public planning, zoning and permit records in Pennsylvania, New Jersey and Delaware: county planning commissions, Philadelphia permits and zoning appeals, New Jersey construction permits, Delaware's Preliminary Land Use Service (PLUS) and Pennsylvania DEP stormwater permits, processed automatically. Summaries are written by AI from those records. Estimates are rough order-of-magnitude and not engineering figures. Always verify with the municipality. Not affiliated with any county or state agency. Map data © OpenStreetMap contributors.