[Adams County](https://plannednearby.com/c/adams-pa/) · [Straban Township](https://plannednearby.com/c/adams-pa/straban-township) · #2024-05-utility-scale-solar-project-adams-miller · [Solar farms tracker](https://plannednearby.com/topics/solar-farms/)

# Utility-scale solar project, Adams Miller Solar

Straban Township, PA · government & utilities

In short: **Utility-scale solar project, Adams Miller Solar** is a government or utility project in Straban Township, Adams County, PA. As of November 24, 2026, the public records we track show nothing newer since May 15, 2024. The town may have acted since.

Stage: No recent records · Latest record we have · May 15, 2024

The public records we track show nothing newer in over two years. The town may have acted since: local decisions don't always reach these records.

## About this project

A utility-scale solar project in Straban Township. The agenda does not give its size or the current use of the land.

- **Plan type:** SLD submission (stage not stated)
- **Land use:** other

## Project history

- **2024-05-15** · #2024-05-utility-scale-solar-project-adams-miller · SLD submission (stage not stated)

[County plan review office →](https://www.adamscountypa.gov/departments/officeofplanninganddevelopment/panningcommission)

Map pin is approximate.

## The full picture AI research · Nov 17, 2026

Adams Miller Solar is a proposed 3-megawatt solar farm at 30 Miller Road in Straban Township. The developer is SolAmerica Energy. It would sit on a 123-acre site. About 7.43 of those acres are in neighboring Cumberland Township, along Boyds School Road, with an entrance off Old Harrisburg Road.

The county agenda didn't say how big the project is or what the land is used for now. Local news coverage gives the size and location, but no source found says what the land is used for today. Roughly 26 acres, about a fifth of the site, would be disturbed during construction.

Two neighboring landowners opposed the plan at a January 2025 township meeting. They argued that the developer rushed the plan to beat stricter 2024 solar rules. They also raised concerns about stormwater runoff into Rock Creek, glare and inverter noise. The developer disputed the claims about deficiencies in its stormwater study.

### What it could mean nearby

- Stormwater: opponents worry that runoff from the roughly 26 disturbed acres could reach Rock Creek. Cumberland Township asked its engineer to review the plan.
- Glare and noise: opponents say the panel layout could cause glare on Boyds School Road and that inverter noise could be a problem. The developer says the inverters will be placed in the middle of the site, away from neighbors.
- Access: the site entrance would be off Old Harrisburg Road.

### Where it stands

The latest news coverage found (January 2025) shows Straban's supervisors tabling the preliminary land development plan for further discussion, and Cumberland Township also tabled its review. No source found shows a later approval or construction. A final land development plan and state agency approvals would normally come next.

- **Feb 3, 2025** Straban supervisors were scheduled to take up the plan again. No outcome was found.
- **Jan 28, 2025** Cumberland Township supervisors tabled their review and asked their engineer to look at the plan
- **Jan 6, 2025** Straban supervisors tabled the preliminary land development plan after neighbors objected
- **May 15, 2024** Solar land development plan submission was reviewed at a county planning commission meeting

### Who's behind it

SolAmerica Energy · A solar developer that is also proposing the separate Adams Buohl solar project on Old Harrisburg Road in Straban Township.

### Around the web

- [Straban hears opposition and support on proposed solar projects](https://gettysburgconnection.org/?p=85068) — Gettysburg Connection · Jan 6, 2025The Adams Miller plan at 30 Miller Road was tabled. SolAmerica Energy is the developer, and two neighbors raised objections.
- [Cumberland Township tables board action regarding Straban solar energy farm project](https://gettysburgconnection.org/?p=86575) — Gettysburg Connection · Jan 28, 2025The project is 3 MW on 123 acres, with 7.43 acres in Cumberland Township, and Cumberland also tabled its review.

Planning terms explained

- **Preliminary land development plan:** The first detailed site plan a township reviews before it grants final approval.
- **Tabled:** A board postponed action without approving or denying the item.
- **Inverter:** Equipment that converts the panels' direct-current power into the alternating current that the grid uses.
- **Stormwater management:** The plan for handling rain runoff so a site doesn't cause erosion or flooding downstream.

Researched by AI from public sources on Nov 17, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

## How to comment officially

**For this project:** The Straban Township Board of Supervisors decides on the plan at its public meetings, and Cumberland Township's supervisors have also reviewed the part of the site in their township.

In Pennsylvania, Straban Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

- Speak at the Straban Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Straban Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.

[Find Straban Township's meeting agendas →](https://www.google.com/search?q=Straban+Township+PA+planning+commission+meeting+agenda)

Comments on this page are not sent to officials and are not part of the public record.

## Scope estimate for contractors

Not enough detail to estimate.

**Contractor or supplier?** Get projects like this in the counties you work, by email. [Get free contractor alerts →](https://plannednearby.com/contractors)

## More projects nearby

- [Industrial site: 2 structures and rail siding](https://plannednearby.com/x/adams-sld-25-056) — same area · 59,296 sq ft non-residential, industrial · Straban Township · filed 2025-10-15
- [Agricultural lot split into two lots](https://plannednearby.com/x/adams-agricultural-lot-split-into-two-lots-237dd0) — same area · lot line change · Straban Township · filed 2025-08-20
- [Parking lot for industrial facility on Granite Station Rd](https://plannednearby.com/x/adams-sld-24-029) — same area · industrial · Straban · filed 2024-05-15
- [Agricultural Commodities facility, Straban Township](https://plannednearby.com/x/adams-2026-01-agricultural-commodities-facility-straba) — same area · industrial · Straban Township · filed 2026-01-21
- [Pella building addition at existing facility](https://plannednearby.com/x/adams-2024-02-pella-building-addition-at-existing-faci) — same area · subdivision (use not stated) · Straban Township · filed 2024-02-21
- [189 single-family and 76 townhome units, Straban](https://plannednearby.com/x/adams-2024-07-189-single-family-and-76-townhome-units) — same area · 265 homes, single-family homes · Straban Township · filed 2024-07-17

[See everything nearby on a map →](https://plannednearby.com/near#39.86833,-77.16502,Straban%20Township)

---

Source page: https://plannednearby.com/x/adams-2024-05-utility-scale-solar-project-adams-miller

Data from public planning, zoning and permit records in Pennsylvania, New Jersey and Delaware: county planning commissions, Philadelphia permits and zoning appeals, New Jersey construction permits, Delaware's Preliminary Land Use Service (PLUS) and Pennsylvania DEP stormwater permits, processed automatically. Summaries are written by AI from those records. Estimates are rough order-of-magnitude and not engineering figures. Always verify with the municipality. Not affiliated with any county or state agency. Map data © OpenStreetMap contributors.