Adams County · Conewago Township · #2024-08-elementary-school-additions-and-parking
Elementary school additions and parking, Conewago Twp
Conewago Township, PA · school
In short: Elementary school additions and parking, Conewago Twp is a school project in Conewago Township, Adams County, PA. As of November 24, 2026, it is under construction according to web research. Latest record: A May 16, 2026 news report quotes the superintendent saying work at the school is progressing well, with roofing, electrical, HVAC and plumbing work under way. What usually happens next: completion and occupancy.
Usually next: completion and occupancy.
About this project
Building additions and a reconfigured parking lot at the Conewago Township elementary school, with playground areas moved. The agenda does not give the size of the project or the existing site conditions.
- Plan type
- Land development (SLD submission)
- Land use
- school
Project history
- 2024-08-21 · #2024-08-elementary-school-additions-and-parking · Land development (SLD submission)
Map pin is approximate.
The full picture AI research · Nov 15, 2026
The Conewago Valley School District is adding to and renovating Conewago Township Elementary School. The county planning commission reviewed the land development part of the work in August 2024. That part covers the building additions, a reconfigured parking lot and relocated playground areas.
The architect's project page lists about 45,800 square feet of additions and 85,000 square feet of renovations. The additions include a classroom wing, a gym, and a new lobby and office area. In June 2025 the school board awarded construction contracts of roughly $33 million in total, on a split vote and after a community member spoke against the project. Work has since begun. A May 2026 report said the superintendent described construction as progressing well. It described a roof going on, electrical and plumbing work under way, and exterior brick and interior walls coming next. Students have been moved to other district buildings during construction. No completion date was found.
What it could mean nearby
- Construction activity at the school site is under way, and site work was part of the 2025 contracts.
- The reconfigured parking lot and relocated playground areas are part of the plan. The sources found give no detail on traffic changes.
- Kindergarten through grade 2 students have been moved to New Oxford Elementary, and third graders to Conewago Valley Intermediate School, during construction.
Where it stands
Construction is under way, according to a May 2026 news report. The county planning review was in August 2024, and the contracts were awarded in June 2025. The next milestones are finishing the addition and renovations and reopening the building. No completion date was found.
- May 2026 School district update: construction progressing, with roof, electrical, HVAC and plumbing work under way
- Nov 2025 Report that the classroom-wing addition is advancing, with several change orders pending
- Jun 2025 School board awards construction contracts for the project on a split vote
- Aug 21, 2024 County planning commission reviews the land development submission
Who's behind it
Conewago Valley School District · The public school district that owns and operates the school. It is also planning additions and renovations at New Oxford Elementary School.
Around the web
- Conewago Valley school board approves girls' wrestling, New Oxford Elementary construction bidsGettysburg Connection · May 16, 2026The superintendent reported that construction at Conewago Township Elementary was progressing well, with roof, electrical, HVAC and plumbing work under way.
- Conewago Valley school board approves budget tax hike, Conewago Elementary construction bidsGettysburg Connection · Jun 12, 2025The board awarded the general, HVAC, plumbing and electrical contracts, and site work was to begin once the contracts were finalized.
- Adams County Planning CommissionAdams County · Aug 21, 2024The page lists the August 21, 2024 commission meeting at which the land development submission was reviewed.
Planning terms explained
- Land development
- A township and county review of building additions, parking and other site changes on a property.
- SLD
- Short for subdivision and land development, the type of plan submission the county reviewed.
- Change order
- A formal change to a construction contract's scope or price after it is awarded.
- Act 34
- A Pennsylvania law that requires public notice and a hearing on school building project costs.
Researched by AI from public sources on Nov 15, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
How to comment officially
For this project: The Conewago Valley School Board makes the decisions on this project and takes public comment at its regular meetings.
In Pennsylvania, Conewago Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.
- Speak at the Conewago Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Conewago Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.
Find Conewago Township's meeting agendas →
Comments on this page are not sent to officials and are not part of the public record.
What neighbors think
Loading…
Scope estimate for contractors
Not enough detail to estimate.
Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →
More projects nearby
- Conewago Twp Elementary School additionsame area · school · Conewago Township · filed 2024-08-21
- Golf course subdivided from property, Conewagosame area · recreation · Conewago Township · filed 2024-11-20
- Elementary school additions and parking, Conewagosame area · school · Conewago Township · filed 2024-09-18
- Lot conveyance to two adjacent propertiessame area · lot line change · Conewago Township · filed 2024-09-18
- Divert Oxford Ave Integrated Diversion & Energy Facsame area · industrial · Conewago Township · filed 2025-10-08
- Homewood Plum Creek residential development, Conewago Twpsame area · other · Conewago Township · filed 2026-07-15