Adams County · Liberty Township · #2024-08-new-operations-building-and-parking-rave
New operations building and parking, Raven Rock
Raven Rock Mountain Complex, Liberty Township, PA · other
In short: New operations building and parking, Raven Rock is a development project at Raven Rock Mountain Complex in Liberty Township, Adams County, PA. As of November 24, 2026, the public records we track show nothing newer since August 21, 2024. The town may have acted since.
The public records we track show nothing newer in over two years. The town may have acted since: local decisions don't always reach these records.
About this project
Construction of a new operations building and parking area at the Raven Rock Mountain Complex in Liberty Township. The agenda does not give the size of the building or the existing use of the site.
- Plan type
- Land development (SLD submission)
- Land use
- other
Project history
- 2024-08-21 · #2024-08-new-operations-building-and-parking-rave · Land development (SLD submission)
Map pin is approximate.
The full picture AI research · Nov 15, 2026
The project is a new operations building and parking area at the Raven Rock Mountain Complex, a secure U.S. military site in Liberty Township. The county agenda doesn't give the building's size or what is on the site now.
The township's planning agendas show a Department of Defense land development plan for the complex, dated December 2023. The township took it up for review in early 2024 and granted extra review time. A May 2024 supervisors' meeting recorded that the plan was being revised, and a June 2024 planning agenda noted no updated plans had been received. Earlier county minutes describe a maintenance and support facility. Whether that is the same project as this operations building was not confirmed.
A separate federal budget document lists an Operations Facility addition of about 7,917 square feet at the complex. It projects a construction start in late 2026. This may be the same project, but no source ties it to this township filing. Some federal listings place that facility in Maryland.
What it could mean nearby
- No traffic, job or utility effects are described in the records found. The site is a secure federal facility, so public access is limited.
- The federal budget document lists site work, water, sewer and stormwater items for the operations facility. A link to this project was not confirmed.
Where it stands
The plan was last recorded in county review on 2024-08-21, and no township or county approval was found. Federal records suggest a possible construction start around late 2026 for a related operations facility. That has not been confirmed for this plan.
- Oct 2025 Federal sources-sought notice for an Operations Facility at the complex closed (not confirmed to be this project)
- Aug 21, 2024 County planning commission reviewed the land development submission
- Aug 20, 2024 Liberty Township Planning Commission met; its minutes could not be read
- May 7, 2024 Township supervisors' minutes noted the plans were being revised
- Feb 2024 Township planning commission accepted the Raven Rock plan for review
- Dec 18, 2023 Date on the Department of Defense land development plan
Who's behind it
U.S. Department of Defense (Raven Rock Mountain Complex) · The federal defense agency that operates the secure military complex. The township agendas list the plan applicant as US DOD RRMC.
Around the web
- Adams County Planning CommissionAdams County, PA · Aug 21, 2024The August 2024 meeting is listed, but the page doesn't mention Raven Rock.
- ACPC Min March24Adams County, PA · Mar 2024The county minutes list a Raven Rock support and maintenance facility project in Liberty Township.
- 2024 June 18 Planning Commission AgendaLiberty Township · Jun 18, 2024The agenda notes that no updated plans had been received.
- May 7, 2024 BOS Regular Meeting MinutesLiberty Township · May 7, 2024The minutes record no action and say the plans were being revised.
- FY2026 Military Construction Budget Justification, Washington Headquarters ServicesU.S. Department of War Comptroller · Jun 2025The budget lists a 7,917 sq ft Operations Facility addition at the complex, with award projected for 2026.
Planning terms explained
- Land development plan
- A detailed site plan that a municipality reviews before large buildings or parking areas are built.
- SLD submission
- A subdivision and land development plan filed with the county for review.
- Time extension
- An agreed extension of the legal deadline for a township to act on a plan.
- Sources sought notice
- A federal notice used to find contractors who could do a project.
Researched by AI from public sources on Nov 15, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
How to comment officially
For this project: The Liberty Township Planning Commission and Board of Supervisors review the plan, and comments can be given at their public meetings. The Adams County Planning Commission reviews it too, but only to advise.
In Pennsylvania, Liberty Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.
- Speak at the Liberty Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Liberty Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.
Find Liberty Township's meeting agendas →
Comments on this page are not sent to officials and are not part of the public record.
What neighbors think
Loading…
Scope estimate for contractors
Not enough detail to estimate.
Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →
More projects nearby
- Residential lot subdivision on Harbaugh Valley Rdsame area · 3 homes, single-family homes · Liberty Township · filed 2024-12-18
- Lot addition to adjacent residential lotsame area · lot line change · Liberty Township · filed 2024-03-20
- Public works and maintenance complex, Raven Rocksame area · government & utilities · Liberty Township · filed 2024-03-20
- New operations building and parking, Raven Rocksame area · other · Liberty Township · filed 2024-09-18
- Raven Rock Mountain Complex operations buildingsame area · 15,680 sq ft non-residential, institutional · Liberty Township · filed 2024-08-21
- Subdivision of 3-acre lot into one new lotsame area · 1 home, single-family homes · Liberty Township · filed 2026-01-21