[Adams County](https://plannednearby.com/c/adams-pa/) · [Liberty Township](https://plannednearby.com/c/adams-pa/liberty-township) · #2024-09-new-operations-building-and-parking-rave

# New operations building and parking, Raven Rock

Raven Rock Mountain Complex, Liberty Township, PA · other

In short: **New operations building and parking, Raven Rock** is a development project at Raven Rock Mountain Complex in Liberty Township, Adams County, PA. As of November 24, 2026, the public records we track show nothing newer since September 18, 2024. The town may have acted since.

Stage: No recent records · Latest record we have · Sep 18, 2024

The public records we track show nothing newer in over two years. The town may have acted since: local decisions don't always reach these records.

## About this project

Construction of a new operations building and parking area at the Raven Rock Mountain Complex in Liberty Township. Listed among July 2024 submissions.

**County recommendation:** No position

- **Plan type:** Land development
- **Land use:** other

## Project history

- **2024-09-18** · #2024-09-new-operations-building-and-parking-rave · Land development

[County plan review office →](https://www.adamscountypa.gov/departments/officeofplanninganddevelopment/panningcommission)

Map pin is approximate.

## The full picture AI research · Nov 15, 2026

The project is a new operations building and parking area at the Raven Rock Mountain Complex in Liberty Township. The complex is a secure U.S. Department of Defense site. County and township planning commissions reviewed the plan in 2024.

A federal budget document appears to describe the same project as a 15,320 square foot Operations Facility. It lists offices, a kitchen, a gym, lockers, sleeping quarters and storage, plus paved roads, parking and sidewalks. That match is likely but isn't confirmed, because the federal notices place the site inconsistently in Pennsylvania and Maryland.

The federal plan listed a contract award in August 2026, a construction start in October 2026 and completion in October 2028. No confirmation of an award, groundbreaking or opening was found. Nothing was found about neighbor opposition.

### What it could mean nearby

- The site is a secured federal complex, so public access and details are limited, and the township planning commission was told discussion should be limited.
- Township records mention a wastewater treatment plant location in connection with a Raven Rock plan, so utilities are part of the review.
- Construction traffic is possible if work starts, but no traffic study or estimate was found.

### Where it stands

County and township planning commissions reviewed the plan in 2024, and the latest county filing is 2024-09-18. No final township approval was found. Federal documents suggest construction was scheduled to begin around October 2026, but no source confirms that work started. Note: Federal notices place the Operations Facility variously in Pennsylvania and Maryland, so it is not certain they describe the same project as the county's Liberty Township filing.

- **Oct 2026** Federal budget document's planned construction start for the Operations Facility (not confirmed)
- **Aug 2026** Planned federal contract award (not confirmed)
- **Oct 3, 2025** Army Corps sources-sought notice for the Operations Facility closed
- **Sep 18, 2024** Land development reviewed at a county planning commission meeting
- **Aug 20, 2024** Township planning commission reviewed a Raven Rock plan dated 05/29/2024
- **Feb 20, 2024** Township planning commission accepted the Raven Rock plan for review

### Who's behind it

U.S. Department of Defense (with the Army Corps of Engineers, Baltimore District, handling contracting) · The federal owner of the Raven Rock Mountain Complex. The Army Corps of Engineers solicits construction contractors for work at the complex.

### Around the web

- [2024 July 16 Planning Commission Agenda](https://libertytwpadamspa.gov/getmedia/0a18e34e-191a-4b7f-a1d6-280fd7d2b217/2024-July-16-Planning-Commission-Agenda.pdf) — Liberty Township · Jul 16, 2024The Raven Rock land development plan was still on the township review agenda in July 2024.
- [2024 Aug 20 PC Minutes](https://liberty.adamscountypa.gov/getmedia/5655ef12-9213-4510-9da0-155c9f48613c/2024-Aug-20-PC-Minutes.pdf) — Liberty Township · Aug 20, 2024A revised Raven Rock plan dated 05/29/2024 was reviewed, including wastewater treatment plant details.
- [ACPC Min August24](https://adamscountypa.gov/getmedia/ba791f8e-5b9c-49ce-896b-62a417a91a75/ACPC_Min_August24.pdf) — Adams County Planning Commission · Aug 22, 2024County minutes list construction of a new operations building and parking area at Raven Rock.
- [2024 Feb 20 PC Minutes](https://www.libertytwpadamspa.gov/getmedia/61445536-d645-43d8-bc6e-7f049ba24adf/2024-Feb-20-PC-Minutes.pdf) — Liberty Township · Feb 20, 2024The plan was accepted for review and the review clock was set.
- [FY2026 Washington Headquarters Services Military Construction justification](https://comptroller.war.gov/Portals/45/Documents/defbudget/FY2026/budget_justification/pdfs/07_Military_Construction/13-Washington_Headquarters_Services.pdf) — U.S. Department of Defense · Jun 1, 2025Lists a 15,320 SF Operations Facility with planned award in August 2026 and construction start in October 2026.
- [Sources Sought: Raven Rock Mountain Complex (RRMC) Operations Facility](https://www.highergov.com/contract-opportunity/sources-sought-raven-rock-mountain-complex-rrmc-w912dr26ra0004-1-r-d3245/) — HigherGov · Oct 3, 2025Army Corps of Engineers Baltimore District sought contractors for a $10M to $25M Operations Facility.

Planning terms explained

- **Land development plan:** A formal site plan showing new buildings, parking and utilities, which the township reviews.
- **Planning commission:** An appointed local board that reviews plans and advises elected officials.
- **Sources sought:** A federal notice asking contractors if they can do a job, issued before a formal bid.
- **Review clock:** The legal time limit within which a township must act on a submitted plan.

Researched by AI from public sources on Nov 15, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

## How to comment officially

**For this project:** The Liberty Township planning commission and Board of Supervisors review land development plans at public meetings, and residents can comment there.

In Pennsylvania, Liberty Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

- Speak at the Liberty Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Liberty Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.

[Find Liberty Township's meeting agendas →](https://www.google.com/search?q=Liberty+Township+PA+planning+commission+meeting+agenda)

Comments on this page are not sent to officials and are not part of the public record.

## Scope estimate for contractors

Not enough detail to estimate.

**Contractor or supplier?** Get projects like this in the counties you work, by email. [Get free contractor alerts →](https://plannednearby.com/contractors)

## More projects nearby

- [Public works and maintenance complex, Raven Rock](https://plannednearby.com/x/adams-2024-03-public-works-and-maintenance-complex-rav) — same area · government & utilities · Liberty Township · filed 2024-03-20
- [Subdivision of lot along Topper Road](https://plannednearby.com/x/adams-sld-25-071) — same area · agricultural · Liberty Township · filed 2026-01-21
- [Two kennel buildings at Golden Wood facility](https://plannednearby.com/x/adams-sld-24-013) — same area · 4,044 sq ft non-residential, retail & commercial · Liberty Township · filed 2026-01-21
- [Lot reconfiguration along Middle Creek, Liberty Twp](https://plannednearby.com/x/adams-sld-24-053) — same area · lot line change · Liberty Township · filed 2024-08-21
- [Residential lot subdivision on Harbaugh Valley Rd](https://plannednearby.com/x/adams-sld-24-081) — same area · 3 homes, single-family homes · Liberty Township · filed 2024-12-18
- [Subdivision of 3-acre lot into one new lot](https://plannednearby.com/x/adams-sld-25-074) — same area · 1 home, single-family homes · Liberty Township · filed 2026-01-21

[See everything nearby on a map →](https://plannednearby.com/near#39.72860,-77.41894,Liberty%20Township)

---

Source page: https://plannednearby.com/x/adams-2024-09-new-operations-building-and-parking-rave

Data from public planning, zoning and permit records in Pennsylvania, New Jersey and Delaware: county planning commissions, Philadelphia permits and zoning appeals, New Jersey construction permits, Delaware's Preliminary Land Use Service (PLUS) and Pennsylvania DEP stormwater permits, processed automatically. Summaries are written by AI from those records. Estimates are rough order-of-magnitude and not engineering figures. Always verify with the municipality. Not affiliated with any county or state agency. Map data © OpenStreetMap contributors.