In short: Adams Norman utility-scale solar project is an industrial development in Franklin Township, Adams County, PA. As of November 24, 2026, it is in review. Latest record: Franklin Township Planning Commission: land development plan review (November 18, 2026). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.
Usually next: a planning commission recommendation, then a vote by the town's governing body.
About this project
This plan covers a utility-scale solar project in Franklin Township. The agenda gives no acreage or other site details.
- Plan type
- SLD submission (type not specified)
- Land use
- other
Project history
- 2026-11-18 · Franklin Township Planning Commission · Land development plan review · source
- 2026-03-18 · #2026-03-adams-norman-utility-scale-solar-project · SLD submission (type not specified)
Map pin is approximate.
The full picture AI research · Nov 23, 2026
The Adams Norman project is a privately developed, ground-mounted solar farm in Franklin Township. It would sit on a roughly 166-acre farm parcel on Chambersburg Road. News coverage ties the property to the owner's surname, but no government record seen confirms it is the same site. The 166 acres is the whole parcel, and the size of the solar array was not found.
In April 2025 the township supervisors approved a conditional use, which is the zoning permission for a solar farm on farmland, with conditions. A detailed land development plan has since been in front of the township Planning Commission. Meeting summaries show it tabled several times in 2026 while the applicant's revised plans and comments from the county were awaited. Residents have raised concerns about truck traffic and road impacts.
No developer website, construction notice, or state stormwater permit was found. The site appears to still be farmland.
What it could mean nearby
- Residents have raised truck traffic and road impact concerns at Planning Commission meetings, so construction traffic on Chambersburg Road is a likely topic.
- The township requires stormwater management approval for solar systems under its solar ordinance.
- The project would take about 166 acres of the parcel out of farm use if built, based on the parcel size reported in news.
- Solar farms add few permanent jobs or new homes. Nothing found says this one adds any.
Where it stands
The formal land development plan is under review by the Franklin Township Planning Commission, which has tabled it repeatedly pending revisions, and the latest listing is the 2026-11-18 agenda. Planning Commission review is usually followed by a recommendation to the township supervisors, who vote on the plan, and then by permits before any construction. Note: The page lists the type as government and utilities, but the township minutes and news describe a privately developed solar farm, so the type is wrong.
- Nov 18, 2026 Planning Commission land development plan review on the agenda
- Aug 19, 2026 Planning Commission agenda lists the Adams Norman plan
- Jun 17, 2026 Planning Commission minutes show the plan tabled pending revisions
- Mar 18, 2026 Plan reviewed at a county planning commission meeting
- Jan 2026 Planning Commission tabled the plan until the Zoning Hearing Board decision letter arrived
- Apr 3, 2025 Township supervisors voted to approve the conditional use with conditions
Around the web
- November 18, 2026 Planning Commission AgendaFranklin Township · Nov 18, 2026Lists the land development plan review as the latest county-record step.
- August 19, 2026 Planning Commission AgendaFranklin Township · Aug 19, 2026Lists the Adams Norman Solar Land Development Plans as an agenda item.
- June 17, 2026 Planning Commission MinutesFranklin Township · Jun 17, 2026Refers to the solar company and its engineer, which shows a private solar farm.
- March 2026 Planning Commission MinutesFranklin Township · Mar 2026Shows the plan tabled again and a 60-day extension recommended.
- January 2026 Planning Commission MinutesFranklin Township · Jan 2026Plan tabled until the Zoning Hearing Board decision letter arrived.
- April 2025 Board of Supervisors Regular Meeting MinutesFranklin Township · Apr 2025Search results indicate the supervisors voted 3-0 to approve the solar facility conditional use at 2408 Chambersburg Road.
- Solar plans move forward in FranklinGround News (Gettysburg Times) · Apr 11, 2025Reports the conditional use approval for a ground-mounted solar system on a 166-acre farm parcel at 2408 Chambersburg Road.
Planning terms explained
- Conditional use
- A use allowed in a zoning district only after the supervisors hold a hearing and set conditions.
- Land development plan
- The detailed site plan showing layout, drainage, access and other features that the township must approve before building.
- Tabled
- Put on hold with no decision, usually until more information arrives.
- Zoning Hearing Board
- A local board that rules on variances and other zoning appeals.
Researched by AI from public sources on Nov 23, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
How to comment officially
For this project: The Franklin Township Planning Commission reviews the plan next and then the township supervisors decide, so residents can comment at their public meetings. Agendas are posted at franklintwp.us.
In Pennsylvania, Franklin Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.
- Speak at the Franklin Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Franklin Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.
Find Franklin Township's meeting agendas →
Comments on this page are not sent to officials and are not part of the public record.
What neighbors think
Loading…
Scope estimate for contractors
Not enough detail to estimate.
Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →
More projects nearby
- Lot additions to orchard properties on Old Rt 30same area · lot line change · Franklin Township · filed 2024-02-21
- Campsites and ropes course on Chambersburg Rdsame area · 462 sq ft non-residential, recreation · Franklin Township · filed 2026-01-21
- 1-lot residential subdivision on Mt Carmel Rdsame area · 1 home, single-family homes · Franklin Township · filed 2025-10-15
- 0.14-acre lot addition, Chambersburg Rdsame area · lot line change · Franklin Township · filed 2024-07-17
- Lot addition to school district propertysame area · lot line change · Franklin Township · filed 2024-02-21
- Agricultural buildings, Seven Stars Rdsame area · 1 home, 18,401 sq ft non-residential, agricultural · Franklin Township · filed 2024-07-17