[Adams County](https://plannednearby.com/c/adams-pa/) · [Franklin Township](https://plannednearby.com/c/adams-pa/franklin-township) · #2026-03-adams-norman-utility-scale-solar-project · [Solar farms tracker](https://plannednearby.com/topics/solar-farms/)

# Adams Norman utility-scale solar project

Franklin Township, PA · industrial

In short: **Adams Norman utility-scale solar project** is an industrial development in Franklin Township, Adams County, PA. As of November 24, 2026, it is in review. Latest record: Franklin Township Planning Commission: land development plan review (November 18, 2026). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.

Stage: In review · Franklin Township Planning Commission: land development plan review · Nov 18, 2026 · [source](https://franklintwp.us/wp-content/uploads/2026/11/11-November-18-2026-Planning-Commission-Agenda.pdf)

Usually next: a planning commission recommendation, then a vote by the town's governing body.

## About this project

This plan covers a utility-scale solar project in Franklin Township. The agenda gives no acreage or other site details.

- **Plan type:** SLD submission (type not specified)
- **Land use:** other

## Project history

- **2026-11-18** · Franklin Township Planning Commission · Land development plan review · [source](https://franklintwp.us/wp-content/uploads/2026/11/11-November-18-2026-Planning-Commission-Agenda.pdf)
- **2026-03-18** · #2026-03-adams-norman-utility-scale-solar-project · SLD submission (type not specified)

[County plan review office →](https://www.adamscountypa.gov/departments/officeofplanninganddevelopment/panningcommission)

Map pin is approximate.

## The full picture AI research · Nov 23, 2026

The Adams Norman project is a privately developed, ground-mounted solar farm in Franklin Township. It would sit on a roughly 166-acre farm parcel on Chambersburg Road. News coverage ties the property to the owner's surname, but no government record seen confirms it is the same site. The 166 acres is the whole parcel, and the size of the solar array was not found.

In April 2025 the township supervisors approved a conditional use, which is the zoning permission for a solar farm on farmland, with conditions. A detailed land development plan has since been in front of the township Planning Commission. Meeting summaries show it tabled several times in 2026 while the applicant's revised plans and comments from the county were awaited. Residents have raised concerns about truck traffic and road impacts.

No developer website, construction notice, or state stormwater permit was found. The site appears to still be farmland.

### What it could mean nearby

- Residents have raised truck traffic and road impact concerns at Planning Commission meetings, so construction traffic on Chambersburg Road is a likely topic.
- The township requires stormwater management approval for solar systems under its solar ordinance.
- The project would take about 166 acres of the parcel out of farm use if built, based on the parcel size reported in news.
- Solar farms add few permanent jobs or new homes. Nothing found says this one adds any.

### Where it stands

The formal land development plan is under review by the Franklin Township Planning Commission, which has tabled it repeatedly pending revisions, and the latest listing is the 2026-11-18 agenda. Planning Commission review is usually followed by a recommendation to the township supervisors, who vote on the plan, and then by permits before any construction. Note: The page lists the type as government and utilities, but the township minutes and news describe a privately developed solar farm, so the type is wrong.

- **Nov 18, 2026** Planning Commission land development plan review on the agenda
- **Aug 19, 2026** Planning Commission agenda lists the Adams Norman plan
- **Jun 17, 2026** Planning Commission minutes show the plan tabled pending revisions
- **Mar 18, 2026** Plan reviewed at a county planning commission meeting
- **Jan 2026** Planning Commission tabled the plan until the Zoning Hearing Board decision letter arrived
- **Apr 3, 2025** Township supervisors voted to approve the conditional use with conditions

### Around the web

- [November 18, 2026 Planning Commission Agenda](https://franklintwp.us/wp-content/uploads/2026/11/11-November-18-2026-Planning-Commission-Agenda.pdf) — Franklin Township · Nov 18, 2026Lists the land development plan review as the latest county-record step.
- [August 19, 2026 Planning Commission Agenda](https://franklintwp.us/wp-content/uploads/2026/08/8-August-19-2026-Planning-Commission-Agenda.pdf) — Franklin Township · Aug 19, 2026Lists the Adams Norman Solar Land Development Plans as an agenda item.
- [June 17, 2026 Planning Commission Minutes](https://franklintwp.us/wp-content/uploads/2026/07/06-June-17-2026-PLanning-Commission-Minutes.pdf) — Franklin Township · Jun 17, 2026Refers to the solar company and its engineer, which shows a private solar farm.
- [March 2026 Planning Commission Minutes](https://franklintwp.us/wp-content/uploads/2026/05/3-March-2026-Planning-Commission-Minutes.pdf) — Franklin Township · Mar 2026Shows the plan tabled again and a 60-day extension recommended.
- [January 2026 Planning Commission Minutes](https://franklintwp.us/wp-content/uploads/2026/03/01-January-2026-Planning-Commission-Meeting-Minutes.pdf) — Franklin Township · Jan 2026Plan tabled until the Zoning Hearing Board decision letter arrived.
- [April 2025 Board of Supervisors Regular Meeting Minutes](https://franklintwp.us/wp-content/uploads/2025/05/04-April-2025-BOS-Regular-Meeting-Mintues.pdf) — Franklin Township · Apr 2025Search results indicate the supervisors voted 3-0 to approve the solar facility conditional use at 2408 Chambersburg Road.
- [Solar plans move forward in Franklin](https://ground.news/article/solar-plans-move-forward-in-franklin) — Ground News (Gettysburg Times) · Apr 11, 2025Reports the conditional use approval for a ground-mounted solar system on a 166-acre farm parcel at 2408 Chambersburg Road.

Planning terms explained

- **Conditional use:** A use allowed in a zoning district only after the supervisors hold a hearing and set conditions.
- **Land development plan:** The detailed site plan showing layout, drainage, access and other features that the township must approve before building.
- **Tabled:** Put on hold with no decision, usually until more information arrives.
- **Zoning Hearing Board:** A local board that rules on variances and other zoning appeals.

Researched by AI from public sources on Nov 23, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

## How to comment officially

**For this project:** The Franklin Township Planning Commission reviews the plan next and then the township supervisors decide, so residents can comment at their public meetings. Agendas are posted at franklintwp.us.

In Pennsylvania, Franklin Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

- Speak at the Franklin Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Franklin Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.

[Find Franklin Township's meeting agendas →](https://www.google.com/search?q=Franklin+Township+PA+planning+commission+meeting+agenda)

Comments on this page are not sent to officials and are not part of the public record.

## Scope estimate for contractors

Not enough detail to estimate.

**Contractor or supplier?** Get projects like this in the counties you work, by email. [Get free contractor alerts →](https://plannednearby.com/contractors)

## More projects nearby

- [Lot additions to orchard properties on Old Rt 30](https://plannednearby.com/x/adams-sld-23-107) — same area · lot line change · Franklin Township · filed 2024-02-21
- [Campsites and ropes course on Chambersburg Rd](https://plannednearby.com/x/adams-sld-25-085) — same area · 462 sq ft non-residential, recreation · Franklin Township · filed 2026-01-21
- [1-lot residential subdivision on Mt Carmel Rd](https://plannednearby.com/x/adams-sld-25-067) — same area · 1 home, single-family homes · Franklin Township · filed 2025-10-15
- [0.14-acre lot addition, Chambersburg Rd](https://plannednearby.com/x/adams-sld-24-048) — same area · lot line change · Franklin Township · filed 2024-07-17
- [Lot addition to school district property](https://plannednearby.com/x/adams-sld-23-108) — same area · lot line change · Franklin Township · filed 2024-02-21
- [Agricultural buildings, Seven Stars Rd](https://plannednearby.com/x/adams-sld-24-044) — same area · 1 home, 18,401 sq ft non-residential, agricultural · Franklin Township · filed 2024-07-17

[See everything nearby on a map →](https://plannednearby.com/near#39.88060,-77.36376,Franklin%20Township)

---

Source page: https://plannednearby.com/x/adams-2026-03-adams-norman-utility-scale-solar-project

Data from public planning, zoning and permit records in Pennsylvania, New Jersey and Delaware: county planning commissions, Philadelphia permits and zoning appeals, New Jersey construction permits, Delaware's Preliminary Land Use Service (PLUS) and Pennsylvania DEP stormwater permits, processed automatically. Summaries are written by AI from those records. Estimates are rough order-of-magnitude and not engineering figures. Always verify with the municipality. Not affiliated with any county or state agency. Map data © OpenStreetMap contributors.