Adams County · Straban Township · #SLD-24-008
Gettysburg Plant Building Expansion
2000 Proline Place, Straban Township, PA · 64,995 sq ft non-residential, industrial · 74.4 acres
In short: Gettysburg Plant Building Expansion is an industrial development at 2000 Proline Place in Straban Township, Adams County, PA. It will add 64,995 sq ft of non-residential space on 74.4 acres. Its estimated construction value is about $8.4M, a rough estimate from its size. As of November 24, 2026, it is under construction according to web research. Latest record: An October 2024 news report says the roughly 66,000 sq ft expansion at the Pella plant was nearing completion, with construction having started in June 2024. What usually happens next: completion and occupancy.
Usually next: completion and occupancy.
About this project
Adds a 64,995 sq ft building addition to the existing Pella facility on a 74-acre site. About 1.5 acres is converted.
- Plan type
- Industrial land development
- Land use
- industrial
- Zoning
- EC-1
Project history
- 2024-02-21 · #SLD-24-008 · Industrial land development · 64,995 sq ft
Map pin is approximate.
The full picture AI research · Nov 7, 2026
Pella Corporation runs a window and door factory at 2000 Proline Place in Straban Township, just east of Gettysburg. County records show a plan for a building addition of about 65,000 square feet on the 74-acre site, with about 1.5 acres of land changed.
News coverage from October 2024 says the addition was close to finished. It describes an expansion of about 66,000 square feet that adds receiving and warehouse docks and puts the factory's operations under one roof. The coverage says construction began in June 2024. It says the building was due to be done by the end of October 2024, with site work to follow by the end of that year. The expanded plant would total about 330,791 square feet.
No opposition was found. No completion report or certificate of occupancy was found either, so the finished state is unconfirmed.
What it could mean nearby
- The addition is on land that already holds a factory in an established industrial and commerce park, so the surroundings are not changing in character.
- New receiving and warehouse docks could change how trucks move on the site. No traffic study was found.
- The coverage did not mention new jobs.
Where it stands
County records stop at a filing on 2024-02-21, but a news report from October 2024 shows construction began in June 2024 and was nearly complete. No later report confirming completion was found. Note: The news report gives the addition as about 66,000 sq ft, against 64,995 sq ft in the county records. This is a rounding-level difference and probably the same project.
- Oct 18, 2024 News report says the expansion is nearing completion, with the building due by the end of October 2024
- Jun 2024 Construction reportedly began on the addition
- Feb 21, 2024 Latest county planning filing
Who's behind it
Pella Corporation · Pella Corporation is an Iowa-based maker of windows and doors that owns and operates the existing Gettysburg-area factory.
Around the web
- Gettysburg factory nears completion of 66,000 square-foot expansionAOL (syndicated news) · Oct 18, 2024Reports the Pella factory expansion was nearing completion, adds receiving and warehouse docks, and brings the plant to about 330,791 sq ft.
- Gettysburg manufacturing plant expandingCentral Penn Business JournalSearch summary of this article reports the expansion's construction start in June 2024. The page itself could not be opened.
- Property Record, 2000 Proline PlLoopNetShows 2000 Proline Pl as an industrial parcel of about 74 acres, with no sale or building status.
Planning terms explained
- Land development plan
- A site plan that shows a township how a property will be built on, including buildings, parking and stormwater.
- Stormwater
- Rain runoff from roofs and paved areas that must be managed so it does not flood neighbors.
- Certificate of occupancy
- A municipal document confirming a finished building is safe to use.
Researched by AI from public sources on Nov 7, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
How to comment officially
In Pennsylvania, Straban Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.
- Speak at the Straban Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Straban Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.
Find Straban Township's meeting agendas →
Comments on this page are not sent to officials and are not part of the public record.
What neighbors think
Loading…
Scope estimate for contractors
Estimated construction value: $8.4M
- ~649 roofing squares (assumes 1 story)
- ~162 tons of cooling (rule of thumb 400 sq ft/ton)
Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →
More projects nearby
- Amblebrook Section E residential, Straban Townshipsame area · 528 homes, single-family homes · Straban Township · filed 2024-11-20
- Popeyes and shopping center, Straban Townshipsame area · 10,098 sq ft non-residential, mixed use · Straban Township · filed 2024-11-20
- Dairy farmstead on Swift Run Rdsame area · 9,680 sq ft non-residential, agricultural · Straban Township · filed 2024-12-18
- Standalone retail with two drive-thru lanessame area · retail & commercial · Straban Township · filed 2024-07-17
- Adams Miller Buohl solar project, Straban Twpsame area · government & utilities · Straban Township · filed 2024-07-17
- Utility-scale solar farm on Miller Rdsame area · government & utilities · Straban Township · filed 2024-12-18