Adams County · Berwick Township · #SLD-25-059
Proposed Wawa store and fueling station
6115 York Rd, Berwick Township, PA · 6,049 sq ft non-residential, retail & commercial · 12.8 acres
In short: Proposed Wawa store and fueling station is a retail and commercial development at 6115 York Rd in Berwick Township, Adams County, PA. It would add 6,049 sq ft of non-residential space on 12.8 acres. Its estimated construction value is about $1.3M, a rough estimate from its size. As of November 24, 2026, it is in review. Latest record: Commercial reviewed at a meeting of the county planning commission (October 15, 2025). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.
Named in the records: Wawa
Usually next: a planning commission recommendation, then a vote by the town's governing body.
About this project
Proposes a Wawa convenience store and fueling station on about 12.8 acres of commercially zoned land. The report lists about 6,049 square feet of building space.
- Plan type
- Commercial
- Land use
- retail
- Zoning
- HC
Project history
- 2025-10-15 · #SLD-25-059 · Commercial · 6,049 sq ft
Map pin is approximate.
The full picture AI research · Nov 15, 2026
A Wawa convenience store with a fuel station is proposed at 6115 York Road in Berwick Township, Adams County. The county lists about 6,049 square feet of building on roughly 12.8 acres of commercially zoned land.
The township's February 9, 2026 supervisors' minutes name the applicant as Berwick 30 Developers LLC, which is acting for Wawa. The minutes show the supervisors granted an extension on the combined preliminary/final land development plan. The deadline to act moved from March 2 to June 2, 2026. Earlier township planning commission minutes from August 2024 discuss a Wawa on York Road, listed there as 6145, with Wawa's representatives present.
No news coverage, Wawa announcement, or opening notice was found. No evidence of construction or an opening was found either. What happened after the June 2026 deadline could not be confirmed.
What it could mean nearby
- A fueling station on York Road would likely add customer and fuel-delivery traffic. No traffic study was found, so the size of the effect is unknown.
- The minutes list a sewer capacity request for the project, so connection to public sewer appears to be part of the plan.
Where it stands
The latest evidence is the township's February 2026 vote to extend the review deadline to June 2, 2026. The plan was still under review then. No source found shows an approval, permit or start of construction, and the outcome after June 2026 was not found.
- Jun 2, 2026 Extended deadline for the township supervisors to act on the land development plan
- Feb 9, 2026 Township supervisors granted the extension; the minutes name Berwick 30 Developers LLC (Wawa) as applicant
- Oct 15, 2025 County planning commission reviewed the commercial plan
- Aug 7, 2024 Township planning commission discussed a proposed Wawa on York Road
Who's behind it
Berwick 30 Developers LLC (for Wawa) · The applicant LLC is named in township minutes as acting for Wawa, a convenience store and fuel chain that is expanding in central Pennsylvania.
Around the web
- Adams County Planning CommissionAdams County · Oct 15, 2025County planning commission reviewed the commercial plan.
Planning terms explained
- Land development plan
- A detailed site plan showing buildings, parking, drainage and utilities that the township must approve before building.
- Preliminary/final plan
- A single submission that the township reviews as both the preliminary and the final plan.
- Time extension
- The applicant agrees to let the township take longer to decide, so the plan is not automatically approved when the legal deadline passes.
- Sewer capacity
- Confirmation that the public sewer system can handle the wastewater the new use would produce.
Researched by AI from public sources on Nov 15, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
How to comment officially
For this project: The Berwick Township Board of Supervisors decides on the land development plan, and residents can comment at its public meetings or by contacting the township office.
In Pennsylvania, Berwick Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.
- Speak at the Berwick Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Berwick Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.
Find Berwick Township's meeting agendas →
Comments on this page are not sent to officials and are not part of the public record.
What neighbors think
Loading…
Scope estimate for contractors
Estimated construction value: $1.3M
- ~60 roofing squares (assumes 1 story)
- ~15 tons of cooling (rule of thumb 400 sq ft/ton)
Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →
More projects nearby
- Wawa convenience store and fuel station, Berwicksame area · retail & commercial · Berwick Township · filed 2026-01-21
- Paved area for garden and contractor supply usesame area · retail & commercial · Berwick · filed 2024-03-20
- Eliminate interior tract lines on Woodridge Drsame area · lot line change · Berwick Township · filed 2026-01-21
- Wawa food market and fueling stationsame area · retail & commercial · Berwick Township · filed 2025-10-15
- New Rutters convenience, gas, and truck parkingsame area · retail & commercial · Berwick Township · filed 2026-03-18
- Lot addition to adjacent lot on Maple Grove Rdsame area · lot line change · Berwick Township · filed 2026-01-21