About this project

The Pennsbury School District plans to combine nine parcels into a 118.5-acre campus and rebuild the Pennsbury High School site. The plan adds a 497,000-square-foot high school along with a bus maintenance garage, transportation office, field maintenance building and concession building. Two existing high schools, an elementary school, accessory buildings and parking areas would be demolished.

County recommendation: Supports, with comments

Issues raised: Right-turn lane needed on Hood Boulevard, Adequacy of parking lot buffer, Parking within 15 feet of buildings, Street tree too close to driveway and sight triangle, Requested waivers from tree survey and stormwater standards

Applicant
Pennsbury School District
Plan type
Preliminary land development
Land use
school
Zoning
IN Institutional District

Filing history

  • 2025-08-22 · #13-25-SD1 · Preliminary land development · 509,071 sq ft

County review packet (meeting materials) →

Map pin is approximate.

The full picture AI research · Nov 1, 2026

Pennsbury School District is replacing its two high school buildings (East and West) with one new campus for grades 9 through 12 on Hood Boulevard in Falls Township. The main building would be about 497,000 square feet and three stories. It would sit on the south side of the existing campus, so students can stay in the current schools during construction. The site would combine nine parcels into about 118.5 acres.

The plan also adds a bus maintenance garage, a transportation office, a field maintenance building and a concession building. After the new school opens, both old high schools, Village Park Elementary School and several smaller buildings and parking areas would be demolished.

The township supervisors approved the plan in early 2026. Local news reports say tree removal and site preparation began in May 2026. The district has put the cost at roughly $270 million. Some residents have raised concerns about cost and debt. The school is expected to open in September 2029.

What it could mean nearby

Where it stands

The Falls Township Supervisors gave preliminary and final land development approval in January 2026, and construction began in spring 2026. Next come building construction, then opening in 2029 and demolition of the old buildings. A major change to the plans would need an amended approval.

Want to weigh in? Approval is already granted, so residents can still raise concerns at Falls Township Board of Supervisors and Pennsbury School Board public meetings.

Who's behind it

Pennsbury School District · The public school district serving Falls Township and nearby parts of lower Bucks County, which is the owner of this campus redevelopment.

Around the web

Planning terms explained
Land development approval
A township's formal sign-off that a site plan meets local rules for layout, drainage, parking and similar items.
Preliminary and final approval
Two approval steps granted together, which lets the project move straight toward permits and construction.
Planning commission
An advisory township board that reviews plans and recommends action to the elected supervisors.
Amended land development approval
A new review needed if the approved plans change significantly.
Parcel consolidation
Merging several separate lots into one larger property.

Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $178.2M

Contractor or supplier? Get projects like this in the counties you work, by email. Join contractor early access →