Bucks County · Solebury Township · #13063

22,400 sq ft pickleball building at 6538 Lower York Rd

6538 Lower York Road (US 202), southern side at Gazebo Place, Solebury Township, PA · 22,400 sq ft non-residential, recreation · 5.0 acres

About this project

Construct a 22,400 square foot pickleball court building on a 5-acre site that is now rural residential. An existing farmhouse would become a clubhouse, an existing barn would be used for storage, and an existing framed dwelling would be removed. The site would have 76 parking spaces and public water and sewer.

County recommendation: Supports, with comments

Issues raised: Waiver requests lack stated hardship reasons, Stormwater waivers must be resolved before approval, Multi-use trail along Route 202 frontage, Tree protection fencing not shown for retained trees, TNC design guideline compliance required

Applicant
Shire York Holdings, LLC
Engineer / designer
Van Cleef Engineering Associates, LLC
Plan type
Preliminary land development
Land use
recreation
Zoning
TNC Traditional Neighborhood Commercial

Filing history

  • 2025-08-05 · #13063 · Preliminary land development · 22,400 sq ft

County review packet (meeting materials) →

Map pin is approximate.

The full picture AI research · Nov 1, 2026

A company called Shire York Holdings proposes a 22,400-square-foot indoor pickleball building on a 5-acre site on the south side of Lower York Road (US 202) at Gazebo Place in Solebury Township. The site is now rural residential. The plans keep the existing farmhouse as a clubhouse and the barn for storage. A smaller frame house would be removed.

The plans show 76 parking spaces and connections to public water and sewer.

Township parks and recreation minutes from September 2025 appear to cover this project. They describe a private, membership-based club. The applicant asked to be excused from the usual requirement to donate land or pay a fee for public recreation. It pointed to a possible trail extension along Shire Drive and some public uses, such as school use and charity events. Board members questioned whether that was enough. No news coverage, opposition or final approvals were found.

What it could mean nearby

Where it stands

The project is in township review. The latest county filing was 2025-08-05, and the township parks and recreation board discussed it in September 2025. Next steps usually include planning commission and supervisors review, then any needed zoning relief and land development approval. No final decision was found.

Want to weigh in? The Solebury Township planning commission and board of supervisors decide next, and residents can comment at their public meetings, which are listed on the township website.

Who's behind it

Shire York Holdings, LLC · The county filing lists this company as the applicant, with Van Cleef Engineering Associates, LLC as the engineering firm. No official company website was found.

Around the web

Planning terms explained
Land development
The township's formal review of a site plan for new buildings, parking and utilities.
Fee in lieu
A payment a developer can make instead of donating land for public parks and recreation.
Parks and recreation board
A township advisory board that reviews recreation impacts and advises the supervisors.
Public water and sewer
Connection to municipal utility systems instead of a private well and septic system.

Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $4.5M