In short: Mora Solar land development, Kidder Township is a development project in Kidder Township, Carbon County, PA. As of November 24, 2026, it is in review. Latest record: Preliminary land development reviewed at a meeting of the county planning commission (February 18, 2025). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.

In review Preliminary land development reviewed at a meeting of the county planning commission · Feb 18, 2025 · source
  1. Proposed
  2. In reviewFeb 2025
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

Usually next: a planning commission recommendation, then a vote by the town's governing body.

About this project

Preliminary land development plan for the Mora Solar project in Kidder Township, on land owned by Blue Ridge Real Estate Company. The agenda does not give the size of the project or the current use of the site.

County recommendation: Raises serious concerns

Issues raised: Multiple areas of non-compliance with Kidder Township land development and zoning ordinances

Applicant
Mora Solar LLC
Engineer / designer
Langan Engineering
Plan type
Preliminary land development
Land use
other

Project history

  • 2025-02-18 · #3977 · Preliminary land development

County plan review office →

Map pin is approximate.

The full picture AI research · Nov 14, 2026

Mora Solar LLC proposes a utility-scale solar park off Moseywood Road in Kidder Township, on land owned by Blue Ridge Real Estate Company. Local coverage describes about 455 acres. A state notice describes a 60-megawatt facility on about 390 acres. The county agenda gave no size or current use.

The site is wooded land with streams and wetlands. The plan would widen an existing dirt access road into a gravel road and fence the panel area, with a gap left for wildlife. The developer says panels would be routed around streams.

The plan has been in front of the township since 2021. Township supervisors gave conditional approval in early 2022. The state Department of Environmental Protection (DEP) held a June 2026 hearing on a stormwater permit. A local group, Save Carbon County, opposes the project over grading, tree clearing and wetland loss. No source shows that construction has started.

What it could mean nearby

Where it stands

The county planning commission reviewed the preliminary plan in February 2025 and made no recommendation. It listed eight pages of comments the developer must address. The state stormwater permit was still in draft form with a hearing held in June 2026, and no final decision was found. Township preliminary plan approval, then the state permit, would normally come before construction. Note: County records give no size, but local news reports about 455 acres, DEP-related notices describe 390 acres, and a June 2026 blog post says 300 acres.

Who's behind it

Mora Solar LLC · Mora Solar LLC is the project company for the solar park. Some sources link it to Cypress Creek Renewables, a solar developer, but no official project page was found.

Around the web

Planning terms explained
Preliminary land development plan
A detailed early-stage site plan that the township reviews before it can approve a final plan.
NPDES permit
A state-run permit that controls how stormwater runoff from construction is handled so it doesn't pollute streams.
Conditional use
A use the township allows only if the developer meets certain conditions set by the supervisors.
Decommissioning agreement
A commitment to remove the solar equipment and restore the site when the project ends, often backed by financial security.

Researched by AI from public sources on Nov 14, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: Kidder Township decides on the preliminary plan and DEP decides the stormwater permit. Residents can write to DEP's Northeast Regional Office, which accepted written and spoken comments for the June 2026 hearing, or attend Kidder Township meetings.

In Pennsylvania, Kidder Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

Find Kidder Township's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Not enough detail to estimate.

Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →

More projects nearby

See everything nearby on a map →