Cumberland County · Middlesex Township · #3062 · Data centers tracker

Project Bolt data center campus

Middlesex Township, PA · data center

In short: Project Bolt data center campus is a data center project in Middlesex Township, Cumberland County, PA. As of November 24, 2026, it is under construction according to web research. Latest record: The developer's campus page describes the project as under construction with delivery scheduled for Q4 2027, and local TV news reports that zoning was approved… What usually happens next: completion and occupancy.

Under construction The developer's campus page describes the project as under construction with delivery scheduled for Q4 2027, and local TV news reports that zoning was approved and work is under way. · web research checked Nov 4, 2026 · source AI research
  1. Proposed
  2. In reviewAug 2025
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

Usually next: completion and occupancy.

About this project

Project Bolt is a 693-acre data center development along Country Club Road in Middlesex Township, with three campuses, substations, a central water and sewer storage facility and a new public access road. This plan consolidates four parcels into five lots.

Official description: PROJECT BOLT IS A 693-ACRE DATA CENTER DEVELOPMENT IN MIDDLESEX TOWNSHIP, CUMBERLAND COUNTY, PA, ALONG COUNTRY CLUB RD, BORDERED BY THE CONODOGUINET CREEK AND INTERSTATE 81. THE PROJECT IS COMPRISED OF THREE CAMPUSES, A PPL SUBSTATION, 3 CUSTOMER SUBSTATIONS, A CENTRAL WATER AND SEWER STORAGE FACILITY, A NEW PROPOSED PUBLIC ACCESS ROAD "PA DATA DRIVE" IS PROPOSED. THIS PLAN SHOWS THE PROPOSED PRIVATE RIGHT-OF-WAY FOR THIS PUBLIC STREET TO BE BUILT TO PUBLIC STANDARDS. THIS PLAN INCLUDES THE CONSOLIDATION AND RESUBDIVISION OF FOUR (4) EXISTING PARCELS TO CREATE FIVE (5) PROPOSED LOTS OVER THE CAMPUS.

Plan type
Preliminary subdivision plan: county review report

Project history

  • 2025-08-19 · #3062 · Preliminary subdivision plan: county review report
  • 2025-07-15 · Land sold to Carlisle Development Partners LLC for $14.0M · Cumberland County parcel records

County review letter →

County plan review office →

The full picture AI research · Nov 4, 2026

Project Bolt is the county-record name for a large data center campus now publicly called Pennsylvania Digital 1 (PAX-1). It sits on about 693 to 700 acres along Country Club Road in Middlesex Township. The plan is three campuses with roughly 16 to 18 buildings, plus electrical substations and a new access road. A data center is a group of large buildings that house computer servers.

The county file stops at a plan under review (filed 2025-08-19). Other sources show the project has moved further. The township supervisors approved subdivision and preliminary plans, and the developer's page and local news say construction is under way, with blasting and heavy trucks reported. Final votes on individual buildings were postponed in August 2026 after a crowd of more than 150 people overfilled the meeting room. No tenant has been named.

Some neighbors oppose the project and have taken it to court. A judge has so far declined to halt work.

What it could mean nearby

Where it stands

The county shows the plan in review, but news and the developer's page show zoning and preliminary approvals are done and site work has started. Final land development votes on individual buildings were still pending as of the latest reports, and a court appeal by opponents continues. Note: County records show only a plan in review as of 2025-08-19, but the developer's page and local news report that construction is already under way.

Who's behind it

Pennsylvania Data Center Partners LLC (with PowerHouse Data Centers; some news reports name Carlisle Development Partners) · A data center development group that has proposed other Pennsylvania campuses, including one in nearby Monroe Township.

Around the web

Planning terms explained
Land development plan
A detailed site plan for buildings, roads, drainage and utilities that the township must approve before building.
Subdivision
Dividing or reorganizing land into separate lots; here four parcels become five lots.
Planning commission
An advisory township board that reviews plans and recommends action to the elected supervisors.
Spot zoning
A claim, made here by opponents, that a small area was rezoned unfairly to benefit one owner.
Substation
A facility that steps electricity down to a usable voltage for large users.

Researched by AI from public sources on Nov 4, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: The Middlesex Township Board of Supervisors decides the remaining building-by-building land development votes at public meetings, where residents can comment; the Cumberland County court is also hearing the opponents' appeal.

In Pennsylvania, Middlesex Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

Find Middlesex Township's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Not enough detail to estimate.

Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →