In short: Dark Star Solar is a development project in West Pennsboro Township, Cumberland County, PA. As of November 24, 2026, it is in review. Latest record: Preliminary/final land development plan: county review report filed for county review (August 29, 2025). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.

In review Preliminary/final land development plan: county review report filed for county review · Aug 29, 2025 · source
  1. Proposed
  2. In reviewAug 2025
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

Usually next: a planning commission recommendation, then a vote by the town's governing body.

About this project

A 3 MWac solar energy facility on about 25 acres in West Pennsboro Township, set back more than 300 feet from Creek Road and screened by existing and proposed vegetation.

Official description: The Applicant proposes to improve approximately 25 acres of land situated in West Pennsboro Township with a 3MWac solar energy facility. The facility will be setback 300+ feet from Creek Road and screened by existing and proposed vegetation.

Plan type
Preliminary/final land development plan: county review report

Project history

  • 2025-08-29 · #3071 · Preliminary/final land development plan: county review report

County review letter →

County plan review office →

The full picture AI research · Nov 4, 2026

Dark Star Solar is a proposed solar energy facility in West Pennsboro Township, Cumberland County. County records describe a 3-megawatt (AC) array on about 25 acres. It would sit more than 300 feet back from Creek Road and be screened by existing and new vegetation. A project this size would feed electricity into the local power grid and would not be a power plant in the traditional sense.

The plan was filed for county review on 2025-08-29, and that is the latest record found. Searches for the project name, the road, the township and the likely developer entity turned up no developer website, news coverage, township agenda or minutes, or hearing notice. They also turned up no construction reports, listings or state stormwater permit information. Nothing found shows opposition, approval, or work on the ground.

The county facts are therefore the only basis for this summary. Treat the project as under review until a township or county source shows otherwise.

What it could mean nearby

Where it stands

The plan was filed for county review on 2025-08-29, and no later decision was found online. Next steps usually include comments from the county and township, any township approval the zoning rules require, and then erosion and stormwater permits before construction.

Planning terms explained
MWac
Megawatts of alternating-current power, which is the electricity the facility can send to the grid. One megawatt can power roughly several hundred homes.
Setback
The minimum distance a structure must sit back from a road or property line.
Screening
Trees, shrubs or fencing planted to block or soften the view of a site.
Land development plan
A plan submitted to local and county planners showing how a site will be built or changed, which they review for rules compliance.

We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 4, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: The West Pennsboro Township supervisors and planning commission handle local land-use matters. Residents can comment at their public meetings, and the township website lists agendas and minutes.

In Pennsylvania, West Pennsboro Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

Find West Pennsboro Township's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Not enough detail to estimate.

Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →