In short: Pleasant Grove SD is a single-family home development in Silver Spring Township, Cumberland County, PA. As of November 24, 2026, it is in review. Latest record: Township project list: pending subdivision plan, original submission. What usually happens next: a planning commission recommendation, then a vote by the town's governing body.
Usually next: a planning commission recommendation, then a vote by the town's governing body.
About this project
Combines two existing lots and resubdivides them into three residential lots in Silver Spring Township.
Official description: THE PURPOSE OF THIS PLAN IS TO COMBINE TWO LOTS AND THEN SUBDIVIDE INTO THREE RESIDENTIAL LOTS .
- Plan type
- Plan: county review report
Project history
- 2026-11-17 · Township project list · Pending subdivision plan, original submission · source
- 2026-11-04 · Township project list · Subdivision plan, original submission · source
- 2026-09-23 · Board of Supervisors · Final plan · source
- 2026-09-03 · Planning Commission · Subdivision plan · source
- 2026-07-15 · #3210 · Plan: county review report
The full picture AI research · Nov 11, 2026
The Pleasant Grove SD plan in Silver Spring Township would combine two existing lots and then divide the land into three residential lots. The county labels it a final subdivision plan. It is more than a simple lot line change, because the result is a new lot.
The records reviewed give no street address, acreage, owner or home count. The county review report and the township agenda PDFs could not be read in full because their text could not be extracted. No builder page, news story, listing or construction notice was found for this project. Nothing online shows work on the ground.
The township's project list shows the plan as an original submission. The page's own history shows county review in July 2026, a Planning Commission agenda item on 3 September and a Board of Supervisors agenda item on 23 September.
What it could mean nearby
- The plan appears to add one net lot (two lots become three), so any added traffic, school or utility demand would likely be small. The records do not quantify it.
- No road, sewer, water or open-space details could be read in the records reviewed.
Where it stands
The plan is in formal review. The county filed its review report in July 2026, the township's Planning Commission and Board of Supervisors had it on agendas in September, and the township's list still shows it as an original submission. A final approval or an approval condition was not confirmed in the readable records. If approved, the lots would normally be recorded before any building permits are sought. Note: The township's list labels the plan an original submission, while the page's history shows earlier Planning Commission and Board of Supervisors agenda items and a county report titled 'Final SD'. The agenda contents could not be read, so the order of events is unclear.
- Nov 4, 2026 Township project list shows the subdivision plan as an original submission
- Sep 23, 2026 Board of Supervisors agenda lists the final plan
- Sep 3, 2026 Planning Commission agenda lists the subdivision plan
- Jul 15, 2026 County planning review report filed for the final subdivision plan
Around the web
- Current Plans – Silver Spring TownshipSilver Spring Township · Nov 4, 2026Lists Pleasant Grove SD (2026-3) as an active subdivision plan with the status 'Original Submission'.
- Pleasant Grove School District Final SD Review ReportCumberland County Planning Department · Jul 15, 2026The county filed a review report titled 'Final SD'. The text could not be extracted, so only the title and date were confirmed.
- Board of Supervisors agenda, 23 September 2026 (amended)Silver Spring Township · Sep 23, 2026This is the page's record of a final-plan item. The agenda text could not be read, so no decision was confirmed.
- Planning Commission agenda, 3 September 2026Silver Spring Township · Sep 3, 2026This is the page's record of a subdivision plan item. The text could not be read.
Planning terms explained
- Subdivision (SD)
- Dividing land into more lots, or reshaping lots so that a new lot is created.
- Lot line change
- Moving a boundary between existing lots without creating a new lot.
- Final plan
- The detailed plan the township votes on after earlier review, which is recorded once approved.
- County review report
- Advisory comments from the county planning department to the township. The township makes the decision.
- Original submission
- The township's label for a plan that has been filed but has not yet been revised or approved.
We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 11, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
How to comment officially
For this project: The Silver Spring Township Board of Supervisors makes the decision on subdivision plans. Residents can comment at its public meetings or through the township community development office, using the township website's agendas and project list.
In Pennsylvania, Silver Spring Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.
- Speak at the Silver Spring Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Silver Spring Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.
Find Silver Spring Township's meeting agendas →
Comments on this page are not sent to officials and are not part of the public record.
What neighbors think
Loading…
Scope estimate for contractors
Not enough detail to estimate.
Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →
More projects nearby
- Silver Spring Storage0.8 mi · 34,000 sq ft non-residential, warehouse & storage · Silver Spring Township · filed 2024-02-09
- Ahmadiyya Cemetery Mechanicsburg0.9 mi · 480 sq ft non-residential, institutional · Silver Spring Township · filed 2025-05-06
- 7166 Wertzville Road: 2-lot subdivision1.2 mi · lot line change · Silver Spring Township · filed 2024-12-02
- Lot subdivision in Silver Spring Township1.4 mi · lot line change · Silver Spring Township · filed 2026-08-25
- Two-lot combination with conservation easement1.5 mi · lot line change · Silver Spring Township · filed 2026-09-01
- Two-tract subdivision in Silver Spring Township1.7 mi · lot line change · Silver Spring Township · filed 2026-03-02