Morgan's Crossing Townhouses Phase II

South Middleton Township, PA · 39 homes, townhomes

About this project

Phase II of Morgan's Crossing in South Middleton Township adds 39 townhouse lots, about 750 linear feet of public street extending Blackston Run, one open space lot and one residual lot.

Official description: Phase II portion of project. Construct 39 Townhouse Lots along with 750 Linear Feet of Public Street extending Blackston Run, and 1 open space lot, and 1 residual lot.

Filing history

  • 2026-04-09 · #3173 · Submission · 39 lots/units

State agencies' comment letter (PDF) →

County plan review office →

The full picture AI research · Nov 1, 2026

Phase II of Morgan's Crossing would add 39 townhouse lots in South Middleton Township, Cumberland County. The plan also includes about 750 feet of new public street that extends Blackston Run, one lot kept as open space and one leftover lot.

This is the second phase of an existing neighborhood. Earlier townhomes there are already being built and sold, based on general real-estate listings. Those listings do not clearly tie a builder to this phase.

No news coverage, township meeting records, or developer project page was found that is clearly about Phase II. The details here come from the county filing alone.

What it could mean nearby

Where it stands

The county's latest filing is dated April 9, 2026, which suggests the plan is in the subdivision and land development review stage. Township and county review usually comes first, then a decision on approval, and construction can start after approval and permits.

Want to weigh in? Subdivision plans like this are usually decided by the South Middleton Township supervisors after the planning commission reviews them, and residents can comment at those public meetings. Dates were not found, so the township office can confirm the schedule.

Planning terms explained
Land development / subdivision plan
A plan that divides land into lots and lays out the streets and utilities to serve them.
Residual lot
A leftover parcel of the original land that is not part of the new building lots.
Open space lot
A lot set aside to stay undeveloped, such as for green space or stormwater features.
Public street
A road built to township standards that the township takes over for maintenance once it is accepted.

We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $14.4M

Contractor or supplier? Get projects like this in the counties you work, by email. Join contractor early access →