SILVER SPRING WATER TREATMENT PLANT PFAS TREATMENT ADDITION

Silver Spring Township, PA · 8,024 sq ft non-residential, government & utilities

About this project

Upgrades to the Silver Spring Township water treatment plant to add PFAS treatment. The project includes a new filter building of about 8,024 sq ft, relocated on-site piping, new paved parking and a drive aisle, and stormwater facilities.

Official description: The purpose of the plan is to make upgrades to the existing water treatment facility to include PFAS treatment. This involves the construction of a new filter building, relocation of on site piping, new paved parking and drive isle and associated stormwater management facilities. Please note that in the Firm section we were not able to coordinate the incorporation of our company name GHD, so a placeholder firm name was selected and must be corrected.

Filing history

  • 2025-11-20 · #3113 · Submission · 8,024 sq ft

State agencies' comment letter (PDF) →

County plan review office →

The full picture AI research · Nov 1, 2026

Pennsylvania American Water is adding PFAS treatment at the Silver Spring water treatment plant in Silver Spring Township. PFAS are long-lasting chemicals that upcoming federal drinking-water rules limit. County records describe a new filter building of about 8,024 square feet. The work also includes rerouted piping on the site, a new parking area and drive aisle, and stormwater facilities.

A state press release says the plan includes twelve large carbon filters arranged in pairs. It also includes new pumps and upgraded monitoring and control systems. The plant serves over 85,000 people. The release puts the total investment at about $30 million, and the state funding agency PENNVEST approved a grant and a low-interest loan. This is an addition to an existing utility site, not a new neighborhood development. No opposition was found in the sources reviewed.

What it could mean nearby

Where it stands

The county filing dates to November 2025, and a March 2026 Planning Commission report said the township supervisors had granted time extensions for the PFAS treatment plant plans. A final approval was not confirmed. Next steps are usually final plan approval, permits and then construction.

Want to weigh in? The Silver Spring Township Planning Commission and Board of Supervisors review the plans at public meetings, so residents can comment there or check the township's agendas.

Who's behind it

Pennsylvania American Water Company · A regulated water utility that runs water systems across Pennsylvania and received the state funding for this project.

Around the web

Planning terms explained
PFAS
A group of long-lasting synthetic chemicals that can build up in water and the body and are now regulated in drinking water.
Granular activated carbon
A filter material that traps chemicals like PFAS as water passes through it.
Time extension
Extra time the township grants for a plan review to be completed.
Stormwater facilities
Basins, pipes or similar features that manage rain runoff from new paved or built areas.
PENNVEST
A Pennsylvania agency that provides low-interest loans and grants for water infrastructure.

Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $2.8M

Contractor or supplier? Get projects like this in the counties you work, by email. Join contractor early access →