PlannedNearby

Delaware County · Upper Darby Township · #7208

Secane Self Storage

Upper Darby Township, PA · 124,416 sq ft non-residential, warehouse & storage

About this project

Development of a 3.06-acre site in Upper Darby Township with a 124,416 sq. ft. self-storage facility.

Official description: Further develop 3.06 acres with a 124,416 sq. ft. self-storage facility

County recommendation: Revise and Resubmit

Applicant
GSI Secane, LLC
Engineer / designer
KCI Technologies, Inc.
Plan type
Land Development
Land use
Nonresidential

Filing history

  • 2025-02-20 · #7208 · Land Development

County plan review office →

The full picture AI research · Nov 1, 2026

A developer, GSI Secane, LLC, has proposed a self-storage facility of about 124,416 square feet on a 3.06-acre site in the Secane area of Upper Darby Township, Delaware County. Self-storage buildings rent out private units to households and businesses for belongings, inventory or equipment.

The county record doesn't say what is on the site now. Its latest filing is dated February 20, 2025. KCI Technologies, Inc. also appears on the filing. That is an engineering and design firm, which usually prepares site plans.

No news coverage, township meeting records, hearing notices or developer page about this project turned up online. The explanation here rests on the county facts alone. Nothing was found on opposition, approvals or who would operate the facility.

What it could mean nearby

Where it stands

The county shows a filing from February 2025, and no later approvals or hearings were found online. Projects like this usually go through township review of the land development plan, possibly a zoning hearing board decision, and then a local decision on the plan.

Want to weigh in? Upper Darby Township's planning commission and governing body (and the zoning hearing board, if relief is needed) typically review such plans. Residents can usually comment at their public meetings, which the township posts on its website.

Who's behind it

GSI Secane, LLC

Planning terms explained
Land development plan
A detailed site plan showing the buildings, parking, drainage and access that a township reviews before construction.
Zoning hearing board
A local board that decides requests for exceptions or variances from zoning rules.
Stormwater management
Design measures that control rain runoff from roofs and pavement so it doesn't cause flooding or pollution.

We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $16.2M

Contractor or supplier? Get projects like this in the counties you work, by email. Join contractor early access →