In short: MKG single-family subdivision is a single-family home development in Bushkill Township, Northampton County, PA. As of November 24, 2026, it is permitted (building or site permits issued). Latest record: State construction stormwater permit issued Sep 9, 2025 (September 9, 2025). What usually happens next: site work and construction.

Permitted State construction stormwater permit issued Sep 9, 2025 · Sep 9, 2025 · source
  1. Proposed
  2. In reviewOct 2024
  3. Approved
  4. PermittedSep 2025
  5. Under construction
  6. Completed

Usually next: site work and construction.

About this project

A single-family residential subdivision in Bushkill Township, Northampton County, filed by MKG Estates LLC for a construction stormwater permit.

Applicant
MKG ESTATES LLC
Plan type
Construction stormwater permit (DEP)
Land use
Residential subdivision
Status
Site active

Project history

  • 2025-09-09 · State construction stormwater permit issued Sep 9, 2025 · source
  • 2024-10-11 · #PAD480223 · Construction stormwater permit (DEP)
  • 2024-10-11 · State construction stormwater permit application received Oct 11, 2024 · source

DEP site record (eFACTS) →

Map pin is approximate.

The full picture AI research · Nov 6, 2026

MKG Estates LLC proposes a single-family subdivision in Bushkill Township, Northampton County. Township documents place it on Lahr Road and East Douglasville Road. They list about 20 lots (one document says 19) in the Rural Residential zoning district, with a new cul-de-sac off Dontas Road.

The township planning commission recommended conditional approval of the preliminary plan in September 2024. Township minutes from May 2025 show the supervisors approved the preliminary plan with conditions. These included signed and notarized plans, corrected soil information under the stormwater basin, and answers to comments from the engineer and regional planners. In August 2025 the supervisors tabled a follow-up resolution for the project. The state construction stormwater permit was issued in September 2025.

No builder website, home listings or news coverage were found, and no evidence of construction or completed homes turned up.

What it could mean nearby

Where it stands

The state stormwater permit was issued in September 2025, and the township gave preliminary plan approval with conditions in 2025. No evidence was found of final plan approval, construction or completed homes. Usual next steps are final plan approval, building permits, then site work and home construction.

Who's behind it

MKG Estates LLC · A limited liability company named on the township and county filings for this subdivision. No further information about it was found.

Around the web

Planning terms explained
Preliminary major subdivision plan
A detailed first-stage plan to divide land into several lots, which must be approved before the final plan.
Lot line adjustment
A change to a shared property boundary that does not create new lots.
Rural Residential district
A zoning category that allows homes on fairly large lots in less built-up areas.
Construction stormwater permit
A state permit that controls erosion and runoff while land is being cleared and built on.
Cul-de-sac
A dead-end street with a circular turnaround.

Researched by AI from public sources on Nov 6, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: The Bushkill Township Board of Supervisors decides on plan approvals, and residents can comment at its public meetings or through the township office.

This is a state stormwater construction permit (NPDES) from the Pennsylvania Department of Environmental Protection. The building plans themselves are decided by Bushkill Township.

Find Bushkill Township's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Not enough detail to estimate.

Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →