PlannedNearby

Mercer County · Perry Township/Fairview Township · #2025-09-18-mw-solar-facility-off-mccartney-road · Solar farms tracker

18 MW solar facility off McCartney Road

Off McCartney Road, across three parcels, Perry Township/Fairview Township, PA · other · 56.0 acres

In short: 18 MW solar facility off McCartney Road is a development project in Perry Township/Fairview Township, Mercer County, PA. The site is 56.0 acres. As of November 24, 2026, it is in review. Latest record: Preliminary land development reviewed at a meeting of the county planning commission (September 16, 2025). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.

In review Preliminary land development reviewed at a meeting of the county planning commission · Sep 16, 2025 · source
  1. Proposed
  2. In reviewSep 2025
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

Usually next: a planning commission recommendation, then a vote by the town's governing body.

About this project

A ground-mounted solar energy facility with six arrays and associated infrastructure is proposed across three parcels in Perry and Fairview Townships. It would have an 18.00 MW AC capacity on approximately 56 acres.

Plan type
Preliminary land development
Land use
other

Project history

  • 2025-09-16 · #2025-09-18-mw-solar-facility-off-mccartney-road · Preliminary land development

County plan review office →

Map pin is approximate.

The full picture AI research · Nov 7, 2026

A solar developer has proposed a ground-mounted solar farm off McCartney Road. It would sit on about 56 acres across three parcels in Perry and Fairview Townships, Mercer County. County records describe six arrays of panels plus supporting equipment, with a combined output of 18 megawatts. That is enough to supply a few thousand homes' worth of electricity, depending on how it is measured.

The project was on the Mercer County Regional Planning Commission's September 2025 agenda for preliminary land development review. Its minutes list the developer as Encore Renewables. No news coverage, opposition, or neighbor comments were found. No developer project page, construction notice, or state stormwater permit status was found either. Nothing online shows that work has started.

What it could mean nearby

Where it stands

The preliminary land development plan was filed for county review on 2025-09-16 and appeared on the county planning commission's September 2025 agenda. No later approval, permit or construction was found. Final plan approval by the townships and stormwater and other permits usually come next, and construction follows those. Note: The planning commission's September 2025 minutes, as quoted in search results, describe five arrays on two parcels, while the county record lists six arrays on three parcels. This may reflect a revised plan.

Who's behind it

Encore Renewables · The developer is named in county planning commission minutes. No official company page for this project was found, so nothing further can be confirmed about the company.

Around the web

Planning terms explained
Preliminary land development plan
An early detailed site plan that local and county reviewers check before the final plan can be approved.
Array
A block of solar panels mounted together on racks.
MW AC
Megawatts of alternating current, which is the electricity the facility can send to the power grid.
Regional planning commission
A county body that reviews development plans and gives advice to local governments.

Researched by AI from public sources on Nov 7, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: The Mercer County Regional Planning Commission reviews the plan and advises the townships. Perry Township and Fairview Township then decide on it at their public meetings, where residents can comment.

In Pennsylvania, Perry Township/Fairview Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

Find Perry Township/Fairview Township's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Not enough detail to estimate.

Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →