In short: Encore Renewables solar project on McCartney Rd is a development project at McCartney Road in Perry Township/Fairview Township, Mercer County, PA. As of November 24, 2026, it is in review. Latest record: Preliminary land development reviewed at a meeting of the county planning commission (September 23, 2025). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.

In review Preliminary land development reviewed at a meeting of the county planning commission · Sep 23, 2025 · source
  1. Proposed
  2. In reviewSep 2025
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

Usually next: a planning commission recommendation, then a vote by the town's governing body.

About this project

Encore Renewables has a preliminary land development plan for a solar project on McCartney Road, listed for Perry Township and Fairview Township. The agenda gives no details on the project's size.

Plan type
Preliminary land development
Land use
other

Project history

  • 2025-09-23 · #2025-09-encore-renewables-solar-project-on-mccar · Preliminary land development

County plan review office →

Map pin is approximate.

The full picture AI research · Nov 7, 2026

Encore Renewables has filed a preliminary plan to build a solar energy facility on McCartney Road. The site straddles Perry Township and Fairview Township in Mercer County. County meeting records describe five groups of solar panels (arrays) on two parcels. The inverters, which convert the power for the grid, would sit nearer McCartney Road, where the project would connect to the electric grid.

The county records give no megawatt rating or acreage. No news coverage, developer project page, construction notice, or state stormwater permit record was found for this site. Nothing found shows opposition, a named power buyer, or work on the ground. The land is presumably undeveloped, but no source confirms that.

What it could mean nearby

Where it stands

The preliminary land development plan was filed for county review on 2025-09-23. A county committee reviewed it on 2025-09-16, according to draft minutes. Municipal approval, state permits and construction normally follow, and none were found.

Who's behind it

Encore Renewables (Encore Renewable Energy) · A clean energy company that develops commercial, industrial and community-scale solar projects, mostly in the northeastern U.S. Its news page showed no Mercer County project.

Around the web

Planning terms explained
Preliminary land development plan
An early formal site plan showing what will be built and where, which is reviewed before the final plan is approved.
Regional planning commission
A county-level body that reviews local development plans and gives advice. Townships make the final decisions.
Inverter
Equipment that converts solar panel electricity into the form the power grid uses.
Array
A group of solar panels installed together.

Researched by AI from public sources on Nov 7, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: The Perry Township and Fairview Township supervisors and planning bodies make the local land development decisions, and residents can comment at their public meetings. The county planning commission only gives advisory review.

In Pennsylvania, Perry Township/Fairview Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

Find Perry Township/Fairview Township's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Not enough detail to estimate.

Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →