# New water treatment plant

830 Canning House Lane, Cape May City, NJ · government & utilities

In short: **New water treatment plant** is a government or utility project at 830 Canning House Lane in Cape May City, Cape May County, NJ. As of November 24, 2026, it is permitted (building or site permits issued) according to web research. Latest record: The city's construction page says Phase 1A has been awarded and construction is expected to start in fall 2026. What usually happens next: site work and construction.

Stage: Permitted · The city's construction page says Phase 1A has been awarded and construction is expected to start in fall 2026. It reports no work under way, and no source found shows the CAFRA permit being issued. · web research checked Nov 14, 2026 · [source](https://www.capemaycity.com/constructionprojects) AI research

Usually next: site work and construction.

## About this project

Construction of a new water treatment plant for the City of Cape May at 830 Canning House Lane.

Official description: Construction of a new water treatment plant for the City of Cape May.

- **Plan type:** State environmental permit application (NJDEP)
- **Land use:** Institutional
- **Status:** application

## Project history

- **2025-01-28** · #0500-22-0001.2 · State environmental permit application (NJDEP)
- **2025-01-28** · NJDEP coastal (CAFRA) permit 0500-22-0001.2: application filed · [source](https://dspace.njstatelib.org/items/e481a698-5f62-45a9-a917-a3d6e8e44d37)

[County plan review office →](https://dspace.njstatelib.org/items/e481a698-5f62-45a9-a917-a3d6e8e44d37)

## The full picture AI research · Nov 14, 2026

The City of Cape May plans a new water treatment plant beside its existing plant at the Public Works Yard, off Canning House Lane. One building would hold a desalination plant of about 3 million gallons a day and an iron-removal plant of about 1 million gallons a day. Desalination takes salt out of the water. The city's own page gives the desalination size as 3.24 million gallons a day, while the state Water Bank says 3.0.

The city says the existing 1998 plant is too small for current demand and can't be expanded inside its building. The new building's floor would sit about 2 feet above the FEMA 500-year flood level. The city estimates construction at about $40 million.

The city's project page says the first phase (Phase 1A) was awarded to a contractor for about $11.98 million. It expects construction to start in fall 2026. No source found confirms that work has begun.

### What it could mean nearby

- The plant would serve Cape May City, West Cape May, Cape May Point, parts of Lower Township and the Coast Guard Training Center.
- The city says the new plant is meant to give a safer, more reliable water supply because the old plant lacks spare capacity.
- Construction at the Public Works Yard and Canning House Lane will probably bring contractor trucks and deliveries, though no traffic plan was found.
- The critical equipment is designed to sit above flood levels, and the plant will include solar panels and a backup generator.

### Where it stands

The state coastal (CAFRA) permit application was filed on 2025-01-28. The city has since closed financing and awarded the first construction phase, so the project has moved past planning. Construction was expected to start in fall 2026, but no start has been confirmed. Note: The city's page gives the desalination plant as 3.24 million gallons a day, while the NJ Water Bank release says 3.0.

- **Sep 21, 2026** City construction page last updated: Phase 1A awarded, start expected fall 2026
- **Jun 23, 2026** NJ Water Bank reports Cape May closed a $14 million loan for the plant
- **May 27, 2026** Bids for Phase 1A due
- **May 4, 2026** Pre-bid site meeting at 830 Canning House Lane
- **Apr 25, 2025** City project narrative explains why a new plant was chosen
- **Jan 28, 2025** CAFRA permit application filed with NJDEP

### Who's behind it

[City of Cape May](https://www.capemaycity.com/) · The city owns and runs its own water and sewer system, and Coppola Services Inc. is named as the Phase 1A contractor.

### Around the web

- [Construction Projects](https://www.capemaycity.com/constructionprojects) — City of Cape May · Sep 21, 2026Lists the Phase 1A award of about $11.98 million, an expected fall 2026 start, a roughly $40 million total cost, and the plant's scope and location.
- [Cape May Water Treatment Plant Replacement](https://www.njib.gov/news/cape-may-water-treatment-plant-replacement-6a32fec9396dc) — NJ Water Bank · Jun 23, 2026Reports a $14 million loan for a new desalination facility and an iron removal facility at the existing site.
- [Project Narrative - Cape May Water Treatment Plant](https://www.capemaycity.com/media/City%20Manager/Project%20Narrative%20-%20Cape%20May%20Water%20Treatment%20Plant.pdf) — City of Cape May · Apr 25, 2025Explains that the 1998 plant lacks capacity and can't be expanded, so a new plant was chosen.
- [Notice to bidders: Water Treatment Plant Phase 1A](https://www.capemaycity.com/media/General%20City%20Notices/ntb-water-treatment-phase-1a.pdf) — City of Cape MayGives the bid schedule, including the pre-bid meeting at 830 Canning House Lane and the May 27, 2026 bid opening.
- [Water & Sewer](https://www.capemaycity.com/directory/WaterSewer) — City of Cape MayShows 830 Canning House Lane as the city's water and sewer administrative office.

Planning terms explained

- **CAFRA:** The Coastal Area Facility Review Act, under which NJDEP reviews larger projects near the coast.
- **Desalination:** Removing salt from brackish or salty water so it can be used as drinking water.
- **MGD:** Million gallons per day, a measure of how much water a plant can treat.
- **Iron removal:** A treatment step that filters out iron from well water.
- **Phase 1A:** The first construction package for the plant, awarded to a contractor.

Researched by AI from public sources on Nov 14, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

## How to comment officially

**For this project:** NJDEP decides the coastal permit and Cape May City Council oversees the project, so residents can comment at council meetings or contact the city's water and sewer office.

In New Jersey, the Cape May City planning board or zoning board of adjustment decides at a public hearing. Nearby property owners are notified by mail, and the hearing is advertised.

- Speaking at the hearing carries the most weight: anyone can testify or ask the applicant's experts questions, and it all goes on the record.
- You can also write to the board secretary before the hearing, though boards decide mainly on the testimony given at the hearing.

[Find Cape May City's meeting agendas →](https://www.google.com/search?q=Cape+May+City+NJ+planning+commission+meeting+agenda)

Comments on this page are not sent to officials and are not part of the public record.

## Scope estimate for contractors

Not enough detail to estimate.

**Contractor or supplier?** Get projects like this in the counties you work, by email. [Get free contractor alerts →](https://plannednearby.com/contractors)

## More projects nearby

- [3 Pharo Lane](https://plannednearby.com/x/njp-0502-1061-101-06) — 0.8 mi · 1 home, single-family homes · Cape May City · filed 2024-10-11
- [301 Fow Ave](https://plannednearby.com/x/njp-0512-29-1) — 0.8 mi · 1 home, single-family homes · West Borough · filed 2024-10-28
- [230 Grant St](https://plannednearby.com/x/njp-0502-1019-14) — 0.9 mi · single-family homes · Cape May City · filed 2025-07-18
- [1516 Yacht Ave](https://plannednearby.com/x/njp-0502-1160-40) — 1.0 mi · 1 home, single-family homes · Cape May City · filed 2025-01-03
- [1317 Beach Ave hotel building](https://plannednearby.com/x/njp-0502-1146-10) — 1.5 mi · 2,352 sq ft non-residential, retail & commercial · Cape May City · filed 2024-01-17
- [1511 Velvento Ave](https://plannednearby.com/x/njp-0502-1176-01-1-06) — 1.6 mi · single-family homes · Cape May City · filed 2025-07-11

[See everything nearby on a map →](https://plannednearby.com/near#38.94524,-74.92712,Cape%20May%20City)

---

Source page: https://plannednearby.com/x/njb-0500-22-0001

Data from public planning, zoning and permit records in Pennsylvania, New Jersey and Delaware: county planning commissions, Philadelphia permits and zoning appeals, New Jersey construction permits, Delaware's Preliminary Land Use Service (PLUS) and Pennsylvania DEP stormwater permits, processed automatically. Summaries are written by AI from those records. Estimates are rough order-of-magnitude and not engineering figures. Always verify with the municipality. Not affiliated with any county or state agency. Map data © OpenStreetMap contributors.