Hudson County · Jersey City · #0906-20-0008.1

Two high-rise residential buildings (permit extension)

242 Hudson Street, Jersey City, NJ · apartments

In short: Two high-rise residential buildings (permit extension) is an apartment development at 242 Hudson Street in Jersey City, Hudson County, NJ. As of November 24, 2026, it is under construction according to web research. Latest record: A Jersey Digs article dated July 28, 2025 reports that piledriving has begun at Harborside 8, and a later article on the land sale says the developer has… What usually happens next: completion and occupancy.

Under construction A Jersey Digs article dated July 28, 2025 reports that piledriving has begun at Harborside 8, and a later article on the land sale says the developer has started work. · web research checked Nov 12, 2026 · source AI research
  1. Proposed
  2. In reviewJul 2025
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

Usually next: completion and occupancy.

About this project

An extension of the permit to continue building two multi-residential high-rise buildings at 242 Hudson Street in Jersey City. The project also includes a waterfront public access area with four one-story amenity buildings.

Official description: Extend the permit to continue construction of two multi-residential high-rise buildings and a waterfront public access area with four one-story amenity buildings.

Applicant
Plaza VIII & IX Associates LLC
Plan type
State environmental permit application (NJDEP)
Land use
Apartments
Status
approved

Project history

  • 2025-11-25 · #0906-20-0008.1 · State environmental permit application (NJDEP)
  • 2025-11-25 · NJDEP flood hazard permit 0906-20-0008.1: approved · source
  • 2025-07-29 · NJDEP flood hazard permit 0906-20-0008.1: application filed · source

County plan review office →

The full picture AI research · Nov 12, 2026

Two high-rise apartment towers, called Harborside 8 and Harborside 9, are planned at 242 Hudson Street on the Jersey City waterfront. News reports describe Harborside 8 as a tower of about 65 to 68 stories with roughly 678 to 680 rentals. Harborside 9 is described as a 57-story tower with about 579 units. The county filing is a state flood-hazard permit extension to keep building. It also covers a waterfront public access area with four one-story amenity buildings.

The site was a surface parking lot. Reports say Harborside 8 has started work, with piledriving under way. The developer bought the land in December 2025 and lined up about $384 million in financing for the first tower. Harborside 9's development rights were reported as sold to a different Jersey City firm, which aims to start in 2027.

No leasing, move-in or occupancy information was found for either tower.

What it could mean nearby

Where it stands

The state flood-hazard permit extension was approved on 2025-11-25, and news reports say Harborside 8 is already under construction. Work on Harborside 9 is reported as not yet started, with a target of 2027. Note: The page's headline stage of 'In review' contradicts its own record showing the NJDEP permit approved on 2025-11-25, and news reports show Harborside 8 under construction.

Who's behind it

Panepinto Properties (with AJD Construction); permit filed by Plaza VIII & IX Associates LLC · A Jersey City-based developer that bought the site from Veris Residential, the earlier owner. Harborside 9's development rights were reported as sold to GN Management.

Around the web

Planning terms explained
Flood hazard permit
A state permit required for building in or near flood-prone areas such as the waterfront.
Permit extension
More time granted to keep working under an existing permit.
Piledriving
Driving deep support columns into the ground to hold up a large building.
Inclusionary housing
A city rule requiring some new apartments to be set aside as affordable.

Researched by AI from public sources on Nov 12, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: The planning approvals were already granted, and the state environmental agency (NJDEP) handled the flood permit. No upcoming public hearing was found.

In New Jersey, the Jersey City planning board or zoning board of adjustment decides at a public hearing. Nearby property owners are notified by mail, and the hearing is advertised.

Find Jersey City's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Not enough detail to estimate.

Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →