In short: Convenience store with fuel canopy is a retail and commercial development at 801 & 831 Parkway Ave in Ewing Township, Mercer County, NJ. As of November 24, 2026, it is approved according to web research. Latest record: A Mercer County planning review says the applicant was granted preliminary and final major site plan approval and conditional use approval, with design… What usually happens next: building and stormwater permits; site work often starts within 3 to 12 months.

Approved A Mercer County planning review says the applicant was granted preliminary and final major site plan approval and conditional use approval, with design waivers, for the store and gas station. · web research checked Nov 12, 2026 · source AI research
  1. Proposed
  2. In reviewApr 2025
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

Usually next: building and stormwater permits; site work often starts within 3 to 12 months.

About this project

The sites at 801 and 831 Parkway Avenue in Ewing Township would be cleared to build a convenience store with a fuel canopy and pumps, plus parking, lighting and landscaping. Ewing Lexington LLC is the applicant.

Official description: The site at 801 & 831 Parkway Ave would be redeveloped by razing existing structures to build a convenience store and fuel canopy with pumps, plus parking, lighting, and landscaping.

Applicant
Ewing Lexington LLC
Plan type
State environmental permit application (NJDEP)
Land use
Retail & commercial
Status
application

Project history

  • 2025-04-18 · #1102-06-0003.2 · State environmental permit application (NJDEP)
  • 2025-04-18 · NJDEP freshwater wetlands permit 1102-06-0003.2: application filed · source

County plan review office →

The full picture AI research · Nov 12, 2026

Ewing Lexington LLC wants to clear two corner properties at 801 and 831 Parkway Avenue, at Lexington Avenue, and build a convenience store with gas pumps. Mercer County's review describes a store of about 5,670 square feet. It would sit beside a fuel canopy of about 5,878 square feet covering eight fuel dispensers. The plan also includes parking, lighting and landscaping, and three driveways onto Parkway and Lexington Avenues.

The county review calls the project a QuickChek. The Ewing Planning Board approved the site plan and the conditional use, with design waivers, at an April 3 meeting. The county document is undated, and one agenda result gave 2024 rather than 2025 for that meeting. Existing buildings on the site would be demolished. A broker listing for 831 Parkway Avenue showed it as for sale and pending in early 2025.

The state wetlands permit application (filed 2025-04-18) is the last step in the records on this page. No reports of demolition, construction or an opening were found.

What it could mean nearby

Where it stands

The Ewing Planning Board has approved the site plan, and the state wetlands permit was still shown as under review at the last record on this page. The project would normally need that wetlands permit, any other outside agency approvals, and building permits before work starts.

Who's behind it

Ewing Lexington LLC · The applicant company on the filings. The county review describes the project as a QuickChek, but no company page was found.

Around the web

Planning terms explained
Preliminary and final major site plan approval
The planning board's approval of the full layout of buildings, driveways, parking and drainage.
Conditional use
A use the zoning allows only if the project meets extra conditions.
Design waiver
Permission to depart from a specific design standard in the township's rules.
Freshwater wetlands permit
A state permit needed to build in or near protected wetlands.
Fuel canopy
The roof over the gas pumps.

Researched by AI from public sources on Nov 12, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: The Ewing Township Planning Board has already acted. Residents can ask the township planning office about any later changes, and the state environmental agency (NJDEP) handles the wetlands permit.

In New Jersey, the Ewing Township planning board or zoning board of adjustment decides at a public hearing. Nearby property owners are notified by mail, and the hearing is advertised.

Find Ewing Township's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Not enough detail to estimate.

Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →

More projects nearby