Monmouth County · Colts Neck Township · #1309-21-0003.1

68-unit townhouse and condominium development

193 Stone Hill Rd, Colts Neck Township, NJ · 68 homes, townhomes

In short: 68-unit townhouse and condominium development is a townhome development at 193 Stone Hill Rd in Colts Neck Township, Monmouth County, NJ. It would add 68 homes. Its estimated construction value is about $25.2M, a rough estimate from its size. As of November 24, 2026, it is approved according to web research. Latest record: A December 2022 Two River Times article reports the Planning Board unanimously approved the 68-unit Charleston Meadows site plan, and the state wetlands permit… What usually happens next: building and stormwater permits; site work often starts within 3 to 12 months.

Approved A December 2022 Two River Times article reports the Planning Board unanimously approved the 68-unit Charleston Meadows site plan, and the state wetlands permit was approved 2025-09-15. · web research checked Nov 10, 2026 · source AI research
  1. Proposed
  2. In reviewJan 2025
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

Usually next: building and stormwater permits; site work often starts within 3 to 12 months.

About this project

Nine buildings with 52 townhouse units and 16 condominium units at 193 Stone Hill Road in Colts Neck Township, with site improvements.

Official description: Development of nine buildings containing 52 townhouse units and 16 condominium units with site improvements.

Applicant
Countryside Developers Inc
Plan type
State environmental permit application (NJDEP)
Land use
Townhomes
Status
approved

Project history

  • 2025-09-15 · #1309-21-0003.1 · State environmental permit application (NJDEP)
  • 2025-09-15 · NJDEP freshwater wetlands permit 1309-21-0003.1: approved · source
  • 2025-01-31 · NJDEP freshwater wetlands permit 1309-21-0003.1: application filed · source

County plan review office →

The full picture AI research · Nov 10, 2026

Charleston Meadows is a 68-unit housing development planned for 193 Stone Hill Road in Colts Neck. County records describe nine buildings: 52 townhouses and 16 condominiums, plus roads, drainage and other site work. Countryside Developers is the firm on the filing. The site is a roughly 26-acre parcel that has been used as agricultural land.

A December 2022 news report says the Planning Board unanimously approved the site plan earlier that year. The development includes affordable homes. A township farmland plan describes the project as 68 units with 15 affordable rentals. That differs from the county's townhouse and condominium description, and the plan's unit counts do not add up to 68. The developer still needed state environmental approvals, and the state wetlands permit was approved on 2025-09-15.

No evidence was found of construction starting, homes for sale, or a model open.

What it could mean nearby

Where it stands

The Planning Board approved the site plan in 2022, and the state wetlands permit was approved on 2025-09-15. Other state permits, building permits and a construction start are the usual next steps, and none was found. Note: A township farmland plan describes the project as 68 units with 15 affordable rentals, which differs from the county's 52 townhouses plus 16 condominiums, and the planning-board and news sources call it multifamily.

Who's behind it

Countryside Developers Inc · The company is the developer on the filing. No official website or information about its other projects was found.

Around the web

Planning terms explained
Freshwater wetlands permit
A state environmental approval needed to build in or near protected wetlands.
Site plan
A detailed layout of buildings, roads, parking and drainage that a planning board reviews.
Preliminary subdivision approval
An early board approval to divide land into lots, which is followed by final approval.
Stormwater
Rain runoff that must be collected and drained so it doesn't cause flooding or pollution.
Affordable housing
Homes reserved for households under certain income limits at controlled prices or rents.

Researched by AI from public sources on Nov 10, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: The Planning Board has already approved the site plan, so remaining decisions are mainly state permits and township building and construction reviews; residents can contact Colts Neck Township's planning office.

In New Jersey, the Colts Neck Township planning board or zoning board of adjustment decides at a public hearing. Nearby property owners are notified by mail, and the hearing is advertised.

Find Colts Neck Township's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Estimated construction value: $25.2M

Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →