# Nuclear station maintenance shed and building expansions

End Of Alloway Creek Neck Road, Lower Alloways Creek Township, NJ · industrial

In short: **Nuclear station maintenance shed and building expansions** is an industrial development at End Of Alloway Creek Neck Road in Lower Alloways Creek Township, Salem County, NJ. As of November 24, 2026, it is approved according to web research. Latest record: County records list the state coastal permit 1704-02-0001.14 as approved on 2025-11-17, and the page's own record list shows the same approval. What usually happens next: building and stormwater permits; site work often starts within 3 to 12 months.

Stage: Approved · County records list the state coastal permit 1704-02-0001.14 as approved on 2025-11-17, and the page's own record list shows the same approval. · web research checked Nov 23, 2026 · [source](https://dspace.njstatelib.org/items/085e301f-a7a7-46cb-8f13-7f7a35ee7f10) AI research

Usually next: building and stormwater permits; site work often starts within 3 to 12 months.

## About this project

A yard maintenance shed and a cell tower, plus expansions of two condensate polisher buildings, at the Salem and Hope Creek Generating Station at the end of Alloway Creek Neck Road in Lower Alloways Creek.

Official description: Development of a yard maintenance shed and a cell tower, plus expansion of two condensate polisher buildings at the Salem and Hope Creek Generating Station.

- **Plan type:** State environmental permit application (NJDEP)
- **Land use:** Industrial
- **Status:** approved

## Project history

- **2025-11-17** · #1704-02-0001.14 · State environmental permit application (NJDEP)
- **2025-11-17** · NJDEP coastal (CAFRA) permit 1704-02-0001.14: approved · [source](https://dspace.njstatelib.org/items/085e301f-a7a7-46cb-8f13-7f7a35ee7f10)
- **2025-05-08** · NJDEP coastal (CAFRA) permit 1704-02-0001.14: application filed · [source](https://dspace.njstatelib.org/items/085e301f-a7a7-46cb-8f13-7f7a35ee7f10)
- **2025-03-05** · NJDEP coastal (CAFRA) permit 1704-02-0001.12: approved · [source](https://dspace.njstatelib.org/items/00ae1484-66bb-4cd4-a13c-53b30d0c2759)
- **2025-03-05** · NJDEP coastal (CAFRA) permit 1704-02-0001.12: cancelled · [source](https://dspace.njstatelib.org/items/00ae1484-66bb-4cd4-a13c-53b30d0c2759)
- **2024-05-19** · NJDEP coastal (CAFRA) permit 1704-02-0001.12: application filed · [source](https://dspace.njstatelib.org/items/00ae1484-66bb-4cd4-a13c-53b30d0c2759)

[County plan review office →](https://dspace.njstatelib.org/items/085e301f-a7a7-46cb-8f13-7f7a35ee7f10)

## The full picture AI research · Nov 23, 2026

PSEG's Salem and Hope Creek nuclear power station sits at the end of Alloway Creek Neck Road in Lower Alloways Creek Township. County records describe a small package of site work there. It includes a new yard maintenance shed, a new cell tower, and larger buildings for two condensate polisher buildings. Condensate polishers are plant equipment that clean the water used in the plant's steam system.

The records give no sizes, costs or construction schedule. The work is described as additions to an operating industrial site, not a new stand-alone development, and no homes are involved.

The state coastal permit for this work was listed as approved on 2025-11-17. Searches found no news coverage, township meeting items, company project page or later permit notices for it. Nothing found shows whether work has started.

### What it could mean nearby

- The work is inside an existing power-plant site at the end of the road, so no new homes, schools or open-space changes are indicated.
- A new cell tower could improve mobile coverage near the plant, but the records do not say who will use it or how tall it will be.
- Construction traffic would use Alloway Creek Neck Road, but no source describes the scale or timing.

### Where it stands

The NJ Department of Environmental Protection coastal permit was listed as approved on 2025-11-17. No later permits, inspections or construction were found, so the next steps would likely be local building approvals and the start of work. Note: The fact-check's claim that permit suffix .12 belongs to a different project, the NJ Wind Port, could not be confirmed because the bulletin PDFs were unreadable, so the county record's .12 history is left as shown.

- **Nov 17, 2025** State coastal (CAFRA) permit 1704-02-0001.14 listed as approved
- **May 8, 2025** Application for permit .14 filed, per county records; the fact-check cited a 06/11/2025 date in a state bulletin, which could not be read
- **Mar 5, 2025** Earlier permit .12 listed as approved and cancelled
- **May 19, 2024** Application for permit .12 filed

Planning terms explained

- **CAFRA permit:** A New Jersey Coastal Area Facility Review Act permit, which the state requires for certain building projects near the coast.
- **Condensate polisher:** Plant equipment that cleans the water recycled through a power station's steam system.
- **Permit suffix (.12, .14):** The number added to a base permit file number to mark a separate application or revision filed under that file.

We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 23, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

## How to comment officially

**For this project:** The state permit is already listed as approved; any remaining local approvals would go through Lower Alloways Creek Township, whose public notices page lists board meetings, but no pending hearing for this work was found.

In New Jersey, the Lower Alloways Creek Township planning board or zoning board of adjustment decides at a public hearing. Nearby property owners are notified by mail, and the hearing is advertised.

- Speaking at the hearing carries the most weight: anyone can testify or ask the applicant's experts questions, and it all goes on the record.
- You can also write to the board secretary before the hearing, though boards decide mainly on the testimony given at the hearing.

[Find Lower Alloways Creek Township's meeting agendas →](https://www.google.com/search?q=Lower+Alloways+Creek+Township+NJ+planning+commission+meeting+agenda)

Comments on this page are not sent to officials and are not part of the public record.

## Scope estimate for contractors

Not enough detail to estimate.

**Contractor or supplier?** Get projects like this in the counties you work, by email. [Get free contractor alerts →](https://plannednearby.com/contractors)

## More projects nearby

- [Light industrial building](https://plannednearby.com/x/njb-1711-16-0002) — 5.3 mi · industrial · Quinton Township · filed 2026-09-16
- [122 Old Cohansey Rd](https://plannednearby.com/x/njp-0612-4-9) — 7.4 mi · 10,756 sq ft non-residential, office · Stow Creek Township · filed 2024-10-07
- [83 Kerlin Rd single-family home](https://plannednearby.com/x/njp-1701-3-38) — 8.2 mi · 1 home, single-family homes · Alloway Township · filed 2025-04-17
- [623 Shiloh Pike](https://plannednearby.com/x/njp-0607-35-09-11) — 9.5 mi · 19,800 sq ft non-residential, other · Hopewell Township · filed 2025-04-02
- [Accessory structures at 46 Shoemaker Rd](https://plannednearby.com/x/njp-0607-21-2) — 9.5 mi · 21,600 sq ft non-residential, other · Hopewell Township · filed 2025-05-14
- [Block 80, Lot 8.02, Hopewell Township](https://plannednearby.com/x/njp-0607-80-8-02) — 9.6 mi · 20,700 sq ft non-residential, other · Hopewell Township · filed 2024-12-06

[See everything nearby on a map →](https://plannednearby.com/near#39.46648,-75.44028,Lower%20Alloways%20Creek%20Township)

---

Source page: https://plannednearby.com/x/njb-1704-02-0001

Data from public planning, zoning and permit records in Pennsylvania, New Jersey and Delaware: county planning commissions, Philadelphia permits and zoning appeals, New Jersey construction permits, Delaware's Preliminary Land Use Service (PLUS) and Pennsylvania DEP stormwater permits, processed automatically. Summaries are written by AI from those records. Estimates are rough order-of-magnitude and not engineering figures. Always verify with the municipality. Not affiliated with any county or state agency. Map data © OpenStreetMap contributors.