258,150 sq ft warehouse
Franklin Township, NJ · 258,150 sq ft non-residential, warehouse & storage
In short: 258,150 sq ft warehouse is a warehouse and storage development in Franklin Township, Somerset County, NJ. It would add 258,150 sq ft of non-residential space. Its estimated construction value is about $33.6M, a rough estimate from its size. As of November 24, 2026, it is in review. Latest record: NJDEP freshwater wetlands permit 1808-04-0016.1: issued (September 13, 2025). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.
Usually next: a planning commission recommendation, then a vote by the town's governing body.
About this project
A warehouse of about 258,150 sq ft in Franklin Township, with parking, loading docks, access drives and stormwater facilities.
Official description: Construction of an approximately 258,150 square foot warehouse with parking, loading docks, access drives, and stormwater facilities.
- Applicant
- Ukranian Orthodox Church Of The USA
- Plan type
- State environmental permit application (NJDEP)
- Land use
- Warehouse & storage
- Status
- issued
Project history
- 2025-09-13 · #1808-04-0016.1 · State environmental permit application (NJDEP) · 258,150 sq ft
- 2025-09-13 · NJDEP freshwater wetlands permit 1808-04-0016.1: issued · source
- 2025-09-11 · NJDEP freshwater wetlands permit 1808-04-0016.1: approved · source
- 2025-09-09 · NJDEP freshwater wetlands permit 1808-04-0016.1: withdrawn · source
- 2025-05-19 · NJDEP freshwater wetlands permit 1808-04-0016.1: application filed · source
The full picture AI research · Nov 10, 2026
The Ukrainian Orthodox Church of the USA owns a roughly 32-acre property at Easton and Davidson avenues in Franklin Township, near I-287. Its plan is to split the property in two. About 17 acres on Davidson Avenue would be sold to a developer, which would build a warehouse of about 258,000 sq ft, roughly 40 feet tall, for multiple tenants. The church, its history center and offices would stay on the other lot of about 15 acres.
The warehouse would replace the Ukrainian Cultural Center, which would be demolished. The site is now the cultural center plus church grounds. Many community members oppose the sale and demolition. A petition against it had thousands of signatures by late 2025. The church says finances drove the sale. Warehouses are not allowed in this zone, so the project needs a use variance from the township zoning board.
No news coverage was found showing a final board decision or any construction.
What it could mean nearby
- Heavy truck traffic near I-287 and the Easton and Davidson avenue intersection, which the plan would redesign.
- Loss of the cultural center, a long-used community gathering space. Opponents say its events will not fit in the church's remaining social building.
- The warehouse is described as built on speculation, so no tenant or job count is known.
Where it stands
The zoning board of adjustment held hearings on the subdivision, use variances and warehouse from September 2025 onward. A May 2026 report said the hearing was carried to June 18, 2026, and no decision was found after that. A state wetlands permit for the site was issued on 2025-09-13, but the township still has to approve the project. Note: News coverage gives the warehouse as about 258,500 sq ft in one report and mentions larger versions elsewhere, against the county's 258,150 sq ft; also, the county record shows a state wetlands permit issued, but the township zoning approvals were still pending in the coverage found.
- Jun 18, 2026 Zoning board hearing reported as carried to this date (outcome not found)
- Nov 6, 2025 Zoning board hearing of nearly three hours; continued with no decision
- Sep 18, 2025 First zoning board hearing on the subdivision and warehouse
- Sep 13, 2025 NJDEP freshwater wetlands permit issued
- May 19, 2025 Wetlands permit application filed
Who's behind it
Creation Equity (reported buyer) · A Phoenix-based real estate firm reported by local news as the buyer that would build the warehouse; the county filing lists only the church.
Around the web
- Will Ukrainian center in Franklin be demolished for massive warehouse off Route 287?Yahoo News · Sep 25, 2025Describes the lot split, the roughly 17-acre warehouse lot, the needed use variances, and that no decision had been made.
- Zoning board continues hearing Ukrainian church warehouse applicationFranklin Reporter · Nov 7, 2025Reports the November 6, 2025 hearing ran nearly three hours with objectors questioning witnesses and no decision.
- Zoning board hearing on Ukrainian cultural center ends in chaosFranklin ReporterReports the 258,150 sq ft warehouse plan and the community reaction at the September hearing.
- Archbishop: Finances drove Ukrainian Orthodox Church to sell cultural center to developerFranklin ReporterGives the church's stated reason for the sale.
- Community witnesses tell Franklin board cultural center's activities won't fit in the proposed replacement spaceCitizen Portal · May 2026Search summary indicated the hearing was carried to June 18, 2026; the page itself could not be opened.
Planning terms explained
- Use variance
- Special permission from the zoning board to build something the zone does not normally allow, such as a warehouse.
- Subdivision
- Splitting one property into separate lots, here a church lot and a warehouse lot.
- Freshwater wetlands permit
- A state permit allowing work in or near protected wetlands.
- Zoning Board of Adjustment
- The township board that hears requests for variances and some site plans.
Researched by AI from public sources on Nov 10, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
How to comment officially
For this project: The Franklin Township Zoning Board of Adjustment decides the subdivision and use variances at public hearings, where residents can attend and comment.
In New Jersey, the Franklin Township planning board or zoning board of adjustment decides at a public hearing. Nearby property owners are notified by mail, and the hearing is advertised.
- Speaking at the hearing carries the most weight: anyone can testify or ask the applicant's experts questions, and it all goes on the record.
- You can also write to the board secretary before the hearing, though boards decide mainly on the testimony given at the hearing.
Find Franklin Township's meeting agendas →
Comments on this page are not sent to officials and are not part of the public record.
What neighbors think
Loading…
Scope estimate for contractors
Estimated construction value: $33.6M
- ~2,581 roofing squares (assumes 1 story)
- ~645 tons of cooling (rule of thumb 400 sq ft/ton)
Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →
More projects nearby
- Storage building, Block 507.14, Lot 610.3 mi · 76,230 sq ft non-residential, warehouse & storage · Franklin Township · filed 2024-12-17
- 212,500 SF warehouse at 1-3 Executive Drive0.4 mi · 212,500 sq ft non-residential, warehouse & storage · Franklin Township · filed 2025-01-02
- Mixed-use residential and commercial development0.5 mi · mixed use · Franklin Township · filed 2025-01-20
- 201,610 sq ft storage building, Franklin Twp0.6 mi · 201,610 sq ft non-residential, warehouse & storage · Franklin Township · filed 2026-01-12
- Storage building, Franklin Township0.7 mi · 40,000 sq ft non-residential, warehouse & storage · Franklin Township · filed 2024-02-02
- Block 512, Lot 12.010.8 mi · 8,770 sq ft non-residential, institutional · Franklin Township · filed 2024-01-23