PlannedNearby

Burlington County · Mount Laurel Township · #25CP0689

33 Beaver Ave

33 Beaver Ave, Mount Laurel Township, NJ · 292,842 sq ft non-residential, warehouse & storage

About this project

A new 292,842 sq ft storage building of moderate hazard classification is proposed at 33 Beaver Avenue in Mount Laurel Township, Burlington County.

Official description: Storage building, moderate hazard; reported construction cost $7,911,834

Plan type
Building permit (new construction)
Land use
Storage building, moderate hazard
Status
Certificate

Filing history

  • 2025-07-01 · #25CP0689 · Building permit (new construction) · 292,842 sq ft

NJ construction permit data (DCA) →

The full picture AI research · Nov 1, 2026

County records show a proposal for a new storage building of about 292,842 square feet at 33 Beaver Avenue in Mount Laurel Township, Burlington County. That is a very large building, roughly the size of five or six football fields of floor space. The county classifies it as a moderate-hazard building. That means the stored goods are expected to burn at a moderate rate, which sets the fire-safety rules it must meet.

The county record does not say who would use the building. It also does not say what is on the site today. No news coverage, township agenda or developer page was found that clearly matches this address and size. Other Beaver Avenue storage proposals turned up in searches, but they were smaller and could not be tied to this one, so they are not used here.

What it could mean nearby

Where it stands

The county's latest filing is dated July 1, 2025, which suggests the project is at the permit-review stage. No township approval status was found. A project this size usually needs township planning board site plan approval and state or county permits before construction begins.

Want to weigh in? The Mount Laurel Township Planning Board normally hears site plans for projects like this at public meetings. Residents can usually comment there, and the township can confirm whether this project is on an agenda.

Planning terms explained
Site plan approval
A local board's review of a project's layout, including parking, driveways, drainage and landscaping.
Hazard classification
A building-code rating of how much fire risk the stored contents pose, which sets the required safety features.
Planning board
The township body of appointed residents that reviews development applications at public meetings.

We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $38.1M

Contractor or supplier? Get projects like this in the counties you work, by email. Join contractor early access →