Warren County · Belvidere Town · #25100+A
Storage building, Belvidere Town
Belvidere Town, NJ · 353,525 sq ft non-residential, warehouse & storage
About this project
A new storage building of about 353,525 sq ft, with a reported construction cost of about $29.5 million, is planned in Belvidere Town, Warren County.
Official description: Storage building, moderate hazard; reported construction cost $29,523,517
- Plan type
- Building permit (new construction)
- Land use
- Storage building, moderate hazard
- Status
- Permit
Filing history
- 2026-01-29 · #25100+A · Building permit (new construction) · 353,525 sq ft
- 2025-10-21 · #25-100 · Building permit (new construction) · 353,525 sq ft
The full picture AI research · Nov 1, 2026
A single large storage and distribution warehouse of about 353,525 square feet is planned. County records put its construction cost at roughly $29.5 million. Online listings tie this size to a building at 120 Manunka Chunk Road in the Belvidere area. The developer's engineer describes it as a general-storage warehouse, with a two-story office section, on a site of about 37 acres.
The developer is Belvidere Urban Renewal LLC. A February 2026 bank announcement says construction is underway and due to finish in early 2027. It also says the site is about a mile from Route 46 and three miles from Pennsylvania. No tenant was named in the sources found.
The engineer's page says the plan needed no variances. It says a landscaping plan is meant to screen nearby homes. Its approval is described as coming from the Belvidere Planning Board in January 2024 at a slightly larger 370,000 sq ft. That page places the site in Belvidere Township, while the county record says Belvidere Town. The two descriptions may not refer to the same municipality, so the match rests on the size and the address.
What it could mean nearby
- The engineer's page says the site design stops large trucks from turning left when leaving, which is meant to limit local truck traffic.
- The plan has 92 loading spaces and 82 trailer spaces, so regular truck activity should be expected.
- The engineer's page says the general-storage use should keep traffic low, but no traffic study was found.
- Landscaping is planned to screen the building from neighboring homes.
Where it stands
Based on the sources found, the project appears approved and under construction, with completion expected in early 2027. Next steps are usually finishing construction, getting occupancy approvals, and leasing to a tenant.
- Feb 2026 Kearny Bank announced $37.25 million in financing; construction underway, completion expected early 2027
- Jan 29, 2026 Latest county filing for the project
- Jan 2, 2024 Planning board approval of a 370,000 sq ft warehouse on about 37 acres, according to the engineer
Want to weigh in? The approval appears to be already granted, so the local planning board holds no further known hearing. Residents can still ask the municipal land-use office about construction conditions or any amended plans.
Who's behind it
Belvidere Urban Renewal LLC · A project company described in the bank announcement as an affiliate of a Ramsey, NJ development firm, Krame Development Co.
Around the web
- $37 million loan from Kearny Bank paves way for Belvidere warehouse projectROI-NJ · Feb 6, 2026Names the developer entity, says construction is underway, and gives early 2027 as the completion date.
- Bohler Project Approved in BelvidereBohler Engineering · Jan 2, 2024Describes the 37-acre site on Manunka Chunk Road, its variance-free plan, screening, truck routing and January 2024 planning board approval.
- 120 Manunka Chunk RoadCommercialCafeA leasing listing for a 353,525 sq ft warehouse, matching the county record's size.
Planning terms explained
- Planning board
- A local volunteer body that reviews development plans and decides whether they meet local rules.
- Variance
- Permission to depart from a zoning rule; the engineer says this plan needed none.
- Site plan
- A plan showing a building's location, parking, access, drainage and landscaping.
- Urban renewal entity
- A special company set up for a project, often to qualify for tax or financing arrangements.
Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
Scope estimate for contractors
Estimated construction value: $46.0M
- ~3,535 roofing squares (assumes 1 story)
- ~883 tons of cooling (rule of thumb 400 sq ft/ton)
Contractor or supplier? Get projects like this in the counties you work, by email. Join contractor early access →