Bowen Development final major subdivision
Rockefeller & Zerbe Township, PA · subdivision (use not stated) · 19.3 acres
In short: Bowen Development final major subdivision is a subdivision in Rockefeller & Zerbe Township, Northumberland County, PA. The site is 19.3 acres. As of November 24, 2026, it is in review. Latest record: Final major subdivision filed for county review (October 23, 2025). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.
Usually next: a planning commission recommendation, then a vote by the town's governing body.
About this project
Final major subdivision of a 19.34-acre site in Rockefeller & Zerbe Township, submitted by Bowen Development, LLC. The agenda lists a revised DOP date but gives no detail on the lots or current use.
- Applicant
- Bowen Development, LLC
- Engineer / designer
- Zeigler Surveying, LLC
- Plan type
- Final major subdivision
- Land use
- other
Project history
- 2025-10-23 · #1025-104 · Final major subdivision
Map pin is approximate.
The full picture AI research · Nov 7, 2026
Bowen Development, LLC has asked for final approval to divide a 19.34-acre site in Rockefeller Township, Northumberland County. A final major subdivision is the last formal step in dividing land into several lots. The county record doesn't say how many lots are planned or what they would be used for (homes, businesses or something else). It also doesn't say what is on the land now.
The filing was submitted for county review on 2025-10-23. The county agenda mentions a revised review date but gives no other detail. Zeigler Surveying, LLC is also listed on the filing.
No news coverage, township meeting minutes, developer web page, property listing or construction notice was found for this project. Any statement about what will be built or whether work has begun would be a guess.
What it could mean nearby
- The records don't say how many lots or homes are proposed, so traffic, school and utility effects can't be estimated.
- The site is 19.34 acres. Any effect on open space depends on a lot layout that the records don't show.
Where it stands
The county records show the final major subdivision plan was filed for review on 2025-10-23. No source found shows a later approval, permit or start of work. After county review, the township supervisors normally decide on final approval, and the plan is then recorded with the county.
- Oct 23, 2025 Final major subdivision filed for county review
Who's behind it
Bowen Development, LLC
Planning terms explained
- Final major subdivision
- The last formal approval step for dividing a larger property into several new lots, usually with new streets or utilities.
- DOP date
- The county's review deadline date for a plan. The agenda lists a revised one for this plan.
- Subdivision
- The legal division of one parcel of land into two or more lots.
We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 7, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
How to comment officially
For this project: The Rockefeller Township supervisors usually make the final subdivision decision at a public meeting, and the Northumberland County Planning Commission reviews the plan first; neighbors can contact the township for meeting dates.
In Pennsylvania, Rockefeller & Zerbe Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.
- Speak at the Rockefeller & Zerbe Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Rockefeller & Zerbe Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.
Find Rockefeller & Zerbe Township's meeting agendas →
Comments on this page are not sent to officials and are not part of the public record.
What neighbors think
Loading…
Scope estimate for contractors
Not enough detail to estimate.
Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →