[Northumberland County](https://plannednearby.com/c/northumberland-pa/) · [West Chillisquaque Township](https://plannednearby.com/c/northumberland-pa/west-chillisquaque-township) · #125-007 · [Solar farms tracker](https://plannednearby.com/topics/solar-farms/)

# Solar land development, West Chillisquaque Twp

West Chillisquaque Township, PA · other · 1.6 acres

In short: **Solar land development, West Chillisquaque Twp** is a development project in West Chillisquaque Township, Northumberland County, PA. The site is 1.6 acres. As of November 24, 2026, it is in review. Latest record: Final land development filed for county review (January 13, 2025). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.

Stage: In review · Final land development filed for county review · Jan 13, 2025 · [source](https://northumberlandcountypa.gov/feed/?s=planning+commission+agenda&paged=3)

Usually next: a planning commission recommendation, then a vote by the town's governing body.

## About this project

Final land development plan for CSIU Solar in West Chillisquaque Township, about 1.6 acres. The agenda does not describe the size of the solar facility or the current use of the site.

- **Engineer / designer:** [RETTEW Associates, Inc.](https://plannednearby.com/f/rettew)
- **Plan type:** Final land development
- **Land use:** other

## Project history

- **2025-01-13** · #125-007 · Final land development

[County plan review office →](https://northumberlandcountypa.gov/feed/?s=planning+commission+agenda&paged=3)

Map pin is approximate.

## The full picture AI research · Nov 14, 2026

The Central Susquehanna Intermediate Unit (CSIU), a regional public education agency, plans a small solar array on about 1.6 acres of its headquarters grounds near Milton. County records list a final land development plan for "CSIU Solar" filed on 2025-01-13. The county agenda does not say how large the array is or what the land is used for now.

Local news coverage found through search describes the array as meant to cut the agency's own electric bill, with a contract of roughly $1 million and possible vehicle charging stations. Those articles could not be opened and carry no dates, so this detail is only partly confirmed. This is a small, owner-use project rather than a large commercial solar farm. No opposition was found.

### What it could mean nearby

- The site is a 1.6-acre piece of an existing institutional campus, so the footprint is small.
- The power appears to be for the agency's own use, so no large new grid connection or traffic is indicated.
- Little change in traffic is expected once panels are installed, since solar arrays need almost no staff on site.

### Where it stands

The county shows the final land development plan filed for review on 2025-01-13. No later approval, permit or construction record was found, and the next steps are normally plan approval, then permits and construction.

- **Jan 13, 2025** Final land development plan for CSIU Solar filed for county review

### Who's behind it

[Central Susquehanna Intermediate Unit (CSIU)](https://www.csiu.org/) · A regional public education agency serving schools in central Pennsylvania, with its headquarters near Milton.

### Around the web

- [Northumberland County planning commission agenda feed](https://northumberlandcountypa.gov/feed/?s=planning+commission+agenda&paged=3) — Northumberland County, PA · Jan 13, 2025County record of the final land development filing for CSIU Solar.
- [CSIU going solar](https://www.standard-journal.com/news/local/article_a1c20a70-1ec4-4214-a158-355ecaf81937.html) — Standard-JournalAs summarized in search results (the page itself could not be opened), the board approved a roughly $1 million contract for a solar array on a 1.6-acre plot at its headquarters.
- [CSIU looking to go solar](https://www.standard-journal.com/news/local/article_0f2079cc-4951-5db7-b905-01d950670fea.html) — Standard-JournalAs summarized in search results (the page itself could not be opened), the project was to cut electricity costs, be paid from reserves, and include vehicle charging stations.

Planning terms explained

- **Land development plan:** A detailed site plan a municipality and county review before building or major site changes can go ahead.
- **Final plan:** The last, detailed stage of plan review, after earlier sketch or preliminary stages.
- **Solar array:** A group of solar panels that turns sunlight into electricity.

Researched by AI from public sources on Nov 14, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

## How to comment officially

**For this project:** The county planning commission and the West Chillisquaque Township supervisors review land development plans at public meetings, so residents can comment through the county planning office or the township.

In Pennsylvania, West Chillisquaque Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

- Speak at the West Chillisquaque Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the West Chillisquaque Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.

[Find West Chillisquaque Township's meeting agendas →](https://www.google.com/search?q=West+Chillisquaque+Township+PA+planning+commission+meeting+agenda)

Comments on this page are not sent to officials and are not part of the public record.

## Scope estimate for contractors

Not enough detail to estimate.

**Contractor or supplier?** Get projects like this in the counties you work, by email. [Get free contractor alerts →](https://plannednearby.com/contractors)

## More projects nearby

- [Sheetz land development, West Chillisquaque Twp](https://plannednearby.com/x/northumberland-125-005) — same area · retail & commercial · West Chillisquaque Township · filed 2024-10-07
- [Weaver's Equipment Sales land development](https://plannednearby.com/x/northumberland-weaver-s-equipment-sales-land-developmen-a3d404) — same area · other · West Chillisquaque Township · filed 2026-09-14
- [Final land development in West Chillisquaque Twp](https://plannednearby.com/x/northumberland-924-085) — same area · other · West Chillisquaque Township · filed 2024-09-16
- [1.409-acre final land development, West Chillisquaque](https://plannednearby.com/x/northumberland-1-409-acre-final-land-development-west-c-49f0ba) — same area · other · West Chillisquaque · filed 2026-08-04
- [Birchwood Venue final land development](https://plannednearby.com/x/northumberland-824-072) — same area · recreation · West Chillisquaque Township · filed 2024-08-20
- [Final minor subdivision in West Chillisquaque Twp](https://plannednearby.com/x/northumberland-924-086) — same area · subdivision (use not stated) · West Chillisquaque Township · filed 2024-09-16

[See everything nearby on a map →](https://plannednearby.com/near#40.97145,-76.85564,West%20Chillisquaque%20Township)

---

Source page: https://plannednearby.com/x/northumberland-125-007

Data from public planning, zoning and permit records in Pennsylvania, New Jersey and Delaware: county planning commissions, Philadelphia permits and zoning appeals, New Jersey construction permits, Delaware's Preliminary Land Use Service (PLUS) and Pennsylvania DEP stormwater permits, processed automatically. Summaries are written by AI from those records. Estimates are rough order-of-magnitude and not engineering figures. Always verify with the municipality. Not affiliated with any county or state agency. Map data © OpenStreetMap contributors.