Storage shed land development, Herndon Borough

Herndon Borough, PA · warehouse & storage · 5.6 acres

In short: Storage shed land development, Herndon Borough is a warehouse and storage development in Herndon Borough, Northumberland County, PA. The site is 5.6 acres. As of November 24, 2026, it is in review. Latest record: Final land development filed for county review (December 12, 2024). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.

In review Final land development filed for county review · Dec 12, 2024 · source
  1. Proposed
  2. In reviewDec 2024
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

Usually next: a planning commission recommendation, then a vote by the town's governing body.

About this project

Final land development for a storage shed at Herndon Reload Company in Herndon Borough, on about 5.57 acres. The agenda does not give the building size.

Applicant
Herndon Reload Company
Engineer / designer
Cole Boyer, P.E.
Plan type
Final land development
Land use
warehouse

Project history

  • 2024-12-12 · #125-012 · Final land development

County plan review office →

Map pin is approximate.

The full picture AI research · Nov 15, 2026

A final land development plan was filed with the county for a storage shed at Herndon Reload Company in Herndon Borough. The site is about 5.57 acres. The county agenda does not give the building's size.

The company's own website describes a working rail-served reload and warehousing operation, a wood-products plant, and a bedding operation at its Pennsylvania Avenue site. A 2023 trade-magazine profile says the company started in 2005 on a former factory site with a surrounding tract of about 25 acres, with a rail siding and several warehouses. The new shed would most likely add storage space to that existing operation. That reading is an inference, because no document describing the shed itself was found.

No news coverage, borough meeting minutes, permits or opening notices for the shed turned up online.

What it could mean nearby

Where it stands

County records show the final land development plan was filed for county review on 2024-12-12, and no later approval, permit or construction record was found. After county and borough review, a plan like this usually needs borough approval, then building permits, before construction starts.

Who's behind it

Herndon Reload Company · A Herndon, PA company that runs a rail-served reload and warehousing business and makes wood bed-foundation parts and animal bedding.

Around the web

Planning terms explained
Final land development
The last detailed plan stage, showing a building, parking, drainage and utilities for review before approval.
Reload facility
A site where freight is moved between rail cars and trucks and often stored in between.
Acre
A unit of land area, a little smaller than a football field including the end zones.

Researched by AI from public sources on Nov 15, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: Herndon Borough and the Northumberland County planning commission review land development plans, so residents can ask them about comment opportunities at their public meetings.

In Pennsylvania, Herndon Borough decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

Find Herndon Borough's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Not enough detail to estimate.

Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →

More projects nearby

See everything nearby on a map →