In short: Land development, Kulpmont Borough is a development project in Kulpmont Borough, Northumberland County, PA. The site is 4.8 acres. As of November 24, 2026, it is in review. Latest record: Preliminary/final land development filed for county review (May 28, 2025). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.

In review Preliminary/final land development filed for county review · May 28, 2025 · source
  1. Proposed
  2. In reviewMay 2025
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

Usually next: a planning commission recommendation, then a vote by the town's governing body.

About this project

A 4.8-acre preliminary/final land development in Kulpmont Borough, submitted by Freedom 40 LLC. The agenda does not describe the project or current use.

Applicant
Freedom 40 LLC
Engineer / designer
FWH Associates
Plan type
Preliminary/final land development
Land use
other

Project history

  • 2025-05-28 · #925-097 · Preliminary/final land development

County plan review office →

Map pin is approximate.

The full picture AI research · Nov 8, 2026

Freedom 40 LLC has proposed a land development on 4.8 acres in Kulpmont Borough. The county records don't say what will be built or what the land is used for now. The plan is a combined preliminary and final submission, so the developer asked for both approval steps at once.

No developer website, news story, listing, business page or borough notice was found for this site. Nothing found shows work started, a tenant or a sale.

The Northumberland County Planning Commission's 2026 agendas and minutes still list the item under county review. Search excerpts of the June 2026 minutes say the item was tabled. They say the developer had filed a stormwater (MDS) permit, but review comments were still open. The full minutes PDFs could not be read, so no final action is confirmed.

What it could mean nearby

Where it stands

The plan was filed for county review on 2025-05-28 and was still on county planning agendas in 2026, with the June 2026 minutes reportedly tabling it while comments were resolved. After county comments are resolved, the borough usually takes its own action on the plan, then site work and building permits follow.

Who's behind it

Freedom 40 LLC

Around the web

Planning terms explained
Preliminary/final land development
A single plan submission that asks for both the early and the last approval steps together.
Tabled
A board postponed the item to a later meeting without deciding it.
MDS permit
A stormwater (drainage) permit filing, as referred to in the county minutes.
Land development
Building or site work on a parcel that goes beyond a simple lot split, such as new buildings or parking.

Researched by AI from public sources on Nov 8, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: The Northumberland County Planning Commission reviews the plan, and Kulpmont Borough's governing body and planning officials act on it locally. Residents can contact the borough office or attend its public meetings.

In Pennsylvania, Kulpmont Borough decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

Find Kulpmont Borough's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Not enough detail to estimate.

Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →