South data center, Mt. Carmel Twp (616,500 SF)

Mt. Carmel Township, PA · 616,500 sq ft non-residential, data center

In short: South data center, Mt. Carmel Twp (616,500 SF) is a data center project in Mt. Carmel Township, Northumberland County, PA. It would add 616,500 sq ft of non-residential space. Its estimated construction value is about $431.6M, a rough estimate from its size. As of November 24, 2026, it is in review. Latest record: Preliminary land development filed for county review (October 9, 2026). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.

In review Preliminary land development filed for county review · Oct 9, 2026 · source
  1. Proposed
  2. In reviewOct 2026
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

Usually next: a planning commission recommendation, then a vote by the town's governing body.

About this project

Preliminary land development plan for a proposed 616,500 sq ft data center by Blue Creek Investments in Mt. Carmel Township. The agenda does not describe the existing site.

Applicant
Blue Creek Investments
Engineer / designer
Kimley-Horn & Associates Inc.
Plan type
Preliminary land development
Land use
data-center

Project history

  • 2026-10-09 · #2026-10-south-data-center-mt-carmel-twp-616-500 · Preliminary land development · 616,500 sq ft

County plan review office →

Map pin is approximate.

The full picture AI research · Nov 18, 2026

Blue Creek Investments has filed a preliminary land development plan with the county for a data center of about 616,500 square feet in Mt. Carmel Township. That is roughly the footprint of several large warehouses. The county's agenda doesn't describe the site as it is today, and no web source confirmed its exact location.

No news story, township agenda or developer page was found that ties this filing to a specific parcel or a tenant. Separately, other online sources describe a different data center idea for reclaimed mine land near Natalie in the same township. That one is linked to Fit Energy, and a petition opposes a data center there. Nothing found connects it to Blue Creek or to this filing, so the two should not be assumed to be the same project.

The same sources say the township adopted a temporary pause on data center applications in May 2026 and is drafting rules. That detail comes from a tracker site and was not confirmed in township records.

What it could mean nearby

Where it stands

The plan is in county review as a preliminary land development filing dated 2026-10-09. The next steps are usually comments from the county and the township, then township decisions on the plan, and later final plan approval and permits.

Who's behind it

Blue Creek Investments · Blue Creek Investments appears in a marketing flyer for a roughly 150-acre industrial park in Mount Carmel Township, but no official company website was found.

Around the web

Planning terms explained
Preliminary land development plan
An early formal site plan showing buildings, roads and stormwater, which reviewers check before final approval.
Moratorium
A temporary pause on accepting or approving certain applications while a township writes new rules.
Substation
A utility facility that steps electricity up or down so large users can connect to the grid.
Land development
A township-regulated project that builds on a site, such as non-residential buildings, beyond simply dividing land.

Researched by AI from public sources on Nov 18, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: The Northumberland County Planning Commission reviews the filing and the Mt. Carmel Township supervisors decide on the land development plan; residents can comment at their public meetings, though no hearing date was found.

In Pennsylvania, Mt. Carmel Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

Find Mt. Carmel Township's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Estimated construction value: $431.6M

Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →