About this project
A site plan for a cannabis cultivation facility at 567 US Highway 9 in Ocean Township, Ocean County, NJ, on about 5 acres with roughly 16,350 square feet of building space.
Official description: Cannabis Cultivation Facility
- Applicant
- JRSY Girl Growers, LLC
- Engineer / designer
- Van Cleef Engineering Asociates, LLC
- Plan type
- Site plan
- Land use
- Industrial
- Status
- Approved
The full picture AI research · Nov 1, 2026
A company called JRSY Girl Growers, LLC has filed a site plan for a cannabis cultivation facility at 567 US Highway 9 in Ocean Township, Ocean County. The site covers about 5 acres. The plan shows roughly 16,350 square feet of building space, which is about the size of a large warehouse. The county classifies it as industrial use.
A site plan is the detailed layout a town reviews before construction. It shows the building, parking, drainage and access. The latest county filing is dated July 16, 2025.
No news coverage, township meeting records, hearing notices or company pages specific to this project were found online. The records reviewed do not show what is on the site now, whether the project has been approved, or whether anyone has objected.
What it could mean nearby
- Highway 9 is a busy state road, so driveway access and truck or employee trips would likely be reviewed during site plan review. The records found do not show traffic figures.
- Indoor cultivation facilities usually add some jobs, but no job count was found for this project.
- Utility needs such as water, sewer and power are normally checked during review. No details were found.
Where it stands
The county record shows a site plan filing as of July 2025. No approval or hearing result was found online. Next, the township land use board would normally hold a public hearing and then vote to approve, approve with conditions, or deny the plan.
- Jul 16, 2025 Latest county planning filing for the site plan
Want to weigh in? The Ocean Township land use or planning board would likely decide, and residents can usually comment at its public hearing. Hearing notices are normally mailed to nearby property owners and posted on the township website.
Who's behind it
JRSY Girl Growers, LLC
Planning terms explained
- Site plan
- A detailed drawing and application showing how a property will be developed, including buildings, parking, drainage and access.
- Cultivation facility
- A place where cannabis plants are grown, usually indoors, as opposed to a store that sells it.
- Non-residential square footage
- The amount of building floor area used for something other than housing.
- Planning board
- A local appointed board that reviews development applications and holds public hearings.
We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
Scope estimate for contractors
Estimated construction value: $2.1M
- ~163 roofing squares (assumes 1 story)
- ~40 tons of cooling (rule of thumb 400 sq ft/ton)