1035 Industrial Drive

1035 Industrial Drive, Middletown, DE 19709, Middletown, DE · 315,000 sq ft non-residential, warehouse & storage · 44.0 acres

About this project

Site plan review of a roughly 42-acre site at 1035 Industrial Drive in Middletown to assess placing 315,000 sq ft of warehouse and light industrial space.

Official description: Review of 42.33 acre site for feasibility of placing 315,000 square feet of warehouse/light industrial use.

Engineer / designer
Stephen C. Woodin, P.E.
Plan type
Site Plan Review
Land use
Light industrial/warehousing
Zoning
M-I (Manufacturing/Industrial) → M-I (Manufacturing/Industrial)
Sewer
Municipal
Status
Complete

Filing history

  • 2025-09-01 · #2025-09-03 · Site Plan Review

State agencies' comment letter (PDF) →

PLUS application (PDF) →

The full picture AI research · Nov 1, 2026

County planning records show a site plan review for 1035 Industrial Drive in Middletown, Delaware. The review looks at putting about 315,000 square feet of warehouse and light industrial space on a site of roughly 42 to 44 acres. That is about the floor area of five or six big-box stores.

The records don't say who would use the building, what is on the site now, or how many trucks and workers it would bring. A site plan review checks the layout of buildings, parking, driveways, stormwater and landscaping. It is different from a rezoning, which changes what uses are allowed.

No news coverage, meeting agendas or developer project page were found for this project. This explanation relies on the county filing alone.

What it could mean nearby

Where it stands

A site plan review was filed with the county, with the latest filing on 2025-09-01. Reviewers usually send comments to the applicant, who revises the plans. Approval or denial of the plan typically follows once the plans meet code.

Planning terms explained
Site plan review
A check by planning staff and agencies that a proposed layout of buildings, parking, driveways and drainage meets local rules.
Light industrial
Businesses such as assembly, light manufacturing and distribution that are generally less noisy and less polluting than heavy industry.
Stormwater management
Features such as basins that control rain runoff from roofs and pavement so it doesn't flood neighbors or pollute streams.

We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $41.0M