2.4 MW solar farm on Mill Road, Barry Township

West side of Mill Road (T-403), Barry Township, Barry Township, PA · agricultural · 9.3 acres

In short: 2.4 MW solar farm on Mill Road, Barry Township is an agricultural project in Barry Township, Schuylkill County, PA. The site is 9.3 acres. As of November 24, 2026, the public records we track show nothing newer since November 13, 2024. The town may have acted since.

No recent records Latest record we have · Nov 13, 2024
  1. Proposed
  2. In reviewNov 2024
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

The public records we track show nothing newer in over two years. The town may have acted since: local decisions don't always reach these records.

About this project

A 2.4 MW AC solar farm on a 9.35-acre site that is currently a cultivated field, which will be converted to meadow cover. The preliminary plan was approved in June 2024, and this final plan is under review.

County recommendation: Supports, with comments

Issues raised: Erosion and sediment control approval from the Schuylkill Conservation District is required before final approval, Conveyances and lease information must be shown on a revised cover sheet, A development agreement and financial guarantee are required, Stormwater plan must meet Section 1121 and Chapter 102/NPDES requirements, Driveway permit from Mill Road will be issued by the township after county approval

Applicant
Nescopeck Solar LLC
Engineer / designer
ARM Group, LLC
Plan type
Final land development plan (second submission)
Land use
other
Zoning
Agricultural

Project history

  • 2024-11-13 · #2024-11-2-4-mw-solar-farm-on-mill-road-barry-tow · Final land development plan (second submission)

County plan review office →

Map pin is approximate.

The full picture AI research · Nov 13, 2026

A company called Nescopeck Solar LLC has proposed a 2.4-megawatt solar farm on the west side of Mill Road in Barry Township, Schuylkill County. It would cover about 9.35 acres that are now a cultivated farm field. The county summary says the field would be converted to meadow cover under the panels.

The county records show the preliminary plan was approved in June 2024. The final land development plan was on the county planning commission's agenda on 2024-11-13, in its second submission. No news coverage, developer page, township minutes or state permit listing specific to this site was found online. Whether construction has started or the plan has since been approved is not shown in any source found.

What it could mean nearby

Where it stands

The latest county record, from 2024-11-13, shows the final land development plan under review after a second submission, following preliminary approval in June 2024. The usual next steps are final approval by the township, then site and building permits and construction, but no source shows any of these has happened.

Who's behind it

Nescopeck Solar LLC · Nescopeck Solar LLC is the lessee named on the filing, and no company website or other projects were found. ARM Group, LLC, an engineering firm, is also named.

Around the web

Planning terms explained
Land development plan
A detailed site plan the township must approve before a project is built.
Preliminary plan
An early approval of the layout, which comes before the final plan.
Lessee
A company that rents the land, rather than owning it.
MW AC
Megawatts of alternating current, the power the solar farm can send to the grid.
County planning commission
A county body that reviews plans and gives advice, while the township decides.

We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 13, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: The Barry Township supervisors decide on final land development plans and take public comment at their meetings; the county planning commission only advises and meets on the schedule on its meetings page.

In Pennsylvania, Barry Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

Find Barry Township's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Not enough detail to estimate.