# Ridge Road Solar Sites 3-9, West Penn Township

Ridge Road, West Penn Township, PA · other

In short: **Ridge Road Solar Sites 3-9, West Penn Township** is a development project in West Penn Township, Schuylkill County, PA. As of November 24, 2026, it is approved according to web research. Latest record: A Times News article from May 2026 says the West Penn supervisors gave conditional approval to the Ridge Road Solar final plan in August, after delaying the… What usually happens next: building and stormwater permits; site work often starts within 3 to 12 months.

Stage: Approved · A Times News article from May 2026 says the West Penn supervisors gave conditional approval to the Ridge Road Solar final plan in August, after delaying the vote in July. · web research checked Nov 15, 2026 · [source](https://www.tnonline.com/?p=282942) AI research

Usually next: building and stormwater permits; site work often starts within 3 to 12 months.

## About this project

Bollinger Solar LLC proposes a preliminary land development plan for solar sites 3 through 9 on Ridge Road in West Penn Township, parcel 37-15-0140.000. The agenda gives no acreage, panel, or capacity details.

- **Applicant:** [Bollinger Solar LLC](https://plannednearby.com/f/bollinger-solar-llc)
- **Plan type:** Preliminary land development
- **Land use:** other

## Project history

- **2024-12-11** · #7111 · Preliminary land development

[County plan review office →](https://www.schuylkillcountypa.gov/departments/planning___zoning/planning_commission_meetings.php)

Map pin is approximate.

## The full picture AI research · Nov 15, 2026

Bollinger Solar LLC proposes a solar farm on Ridge Road in West Penn Township, near Ash Circle. The county agenda lists it as solar sites 3 through 9 and gives no size. Local news coverage describes it as the Ridge Road Solar Land Development. It would cover about 79 acres and hold about 33,000 panels. The developer has described seven connected panel fields inside an 8-foot fence, with a driveway from Ash Circle and stormwater basins.

The township supervisors gave conditional approval to the preliminary plans, as reported in January 2025. They asked for a plan to remove the panels at the end of the project's life. The supervisors delayed their vote on the final plan in July 2025. In August 2025 they gave it conditional approval, after the developer submitted a decommissioning plan and two agreements. No source found shows construction starting.

The news articles do not say outright that "sites 3-9" and the Ridge Road Solar project are the same. The location, developer and seven array fields strongly suggest they are.

### What it could mean nearby

- Access would come from a new driveway off Ash Circle, which would put construction and maintenance traffic on that road.
- Stormwater basins and swales are part of the plan to manage runoff from the panel fields.
- The supervisors required a plan to remove the panels at the end of the project's life, so the land is meant to be restored.
- The records and news coverage found give no job counts, school effects or utility details.

### Where it stands

The township supervisors gave conditional approval to the final plan in August 2025, and the county planning commission reviewed the plans on 2024-12-11. After approval, the developer usually has to meet the conditions and get state stormwater and other permits before building. No source found shows those permits or construction starting. Note: The county record lists the stage as in review, but local news reports show the township supervisors later gave conditional approval to the final plan in August 2025.

- **Oct 2025** Supervisors approved a maintenance easement agreement tied to the project, per a May 2026 article
- **Aug 2025** Supervisors gave conditional approval to the final land development plan
- **Jul 2025** Supervisors tabled the final plan vote while waiting for a decommissioning plan and agreements
- **Jan 2025** Times News reported conditional approval of the preliminary plans by the supervisors, on the planning commission's recommendation
- **Dec 11, 2024** County planning commission reviewed the preliminary land development

### Who's behind it

Bollinger Solar LLC · A solar developer that proposes solar farms in Schuylkill County; a separate Bollinger request for a solar farm on Trachsville Hill Road was reportedly denied by a zoning board.

### Around the web

- [West Penn OKs extension for solar farm](https://www.tnonline.com/?p=282942) — Times News · May 21, 2026Recaps the August conditional final approval and the October easement agreement for Ridge Road Solar, with no construction details.
- [Ridge Road Solar final plan article](https://www.tnonline.com/?p=274896) — Times News · Aug 14, 2025Supervisors unanimously gave conditional approval to the final plan for about 33,000 panels on 79 acres after the developer submitted the requested documents.
- [Ridge Road Solar vote tabled](https://www.tnonline.com/?p=276203) — Times News · Jul 2025The supervisors tabled the final plan vote over who would be responsible for decommissioning.
- [W. Penn approves solar farm](https://tnonline.com/?p=268291) — Times News · Jan 8, 2025Names Bollinger Solar as the developer and reports conditional preliminary approval for 79.87 acres near Ash Circle and Ridge Road.
- [Planning Commission Meetings](https://www.schuylkillcountypa.gov/departments/planning___zoning/planning_commission_meetings.php) — Schuylkill County · Dec 11, 2024County meeting page that lists the planning commission review.

Planning terms explained

- **Preliminary land development plan:** An early formal site plan that the township and county review before a final plan.
- **Conditional approval:** Approval that depends on the developer meeting listed requirements.
- **Decommissioning plan:** A plan for removing the panels and equipment when the project ends.
- **Stormwater basin:** A shallow basin that collects and slows rainwater runoff from a site.

Researched by AI from public sources on Nov 15, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

## How to comment officially

**For this project:** The West Penn Township supervisors decided the plan at public meetings, and residents can raise concerns with the township about any remaining conditions or permits.

In Pennsylvania, West Penn Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

- Speak at the West Penn Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the West Penn Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.

[Find West Penn Township's meeting agendas →](https://www.google.com/search?q=West+Penn+Township+PA+planning+commission+meeting+agenda)

Comments on this page are not sent to officials and are not part of the public record.

## Scope estimate for contractors

Not enough detail to estimate.

**Contractor or supplier?** Get projects like this in the counties you work, by email. [Get free contractor alerts →](https://plannednearby.com/contractors)

## More projects nearby

- [Lot line adjustment minor subdivision, West Penn](https://plannednearby.com/x/schuylkill-lot-line-adjustment-minor-subdivision-we-8c3467) — same area · lot line change · West Penn Township · filed 2026-06-10
- [309 Self Storage facility, West Penn Township](https://plannednearby.com/x/schuylkill-2025-04-309-self-storage-facility-west-penn-town) — same area · warehouse & storage · West Penn Township · filed 2025-04-09
- [Final minor subdivision, West Penn Twp](https://plannednearby.com/x/schuylkill-37-05-0083000) — same area · subdivision (use not stated) · West Penn Township · filed 2025-05-14
- [Final subdivision for annexation, West Penn Twp](https://plannednearby.com/x/schuylkill-final-subdivision-for-annexation-west-pe-4fa2da) — same area · lot line change · West Penn Township · filed 2025-02-12
- [Lot consolidation on Golf Road, West Penn Twp](https://plannednearby.com/x/schuylkill-lot-consolidation-on-golf-road-west-penn-7748d3) — same area · lot line change · West Penn Township · filed 2025-07-09
- [Land development final plan, West Penn Township](https://plannednearby.com/x/schuylkill-2024-03-land-development-final-plan-west-penn-to) — same area · other · West Penn Township · filed 2024-03-13

[See everything nearby on a map →](https://plannednearby.com/near#40.73766,-75.90923,West%20Penn%20Township)

---

Source page: https://plannednearby.com/x/schuylkill-7111

Data from public planning, zoning and permit records in Pennsylvania, New Jersey and Delaware: county planning commissions, Philadelphia permits and zoning appeals, New Jersey construction permits, Delaware's Preliminary Land Use Service (PLUS) and Pennsylvania DEP stormwater permits, processed automatically. Summaries are written by AI from those records. Estimates are rough order-of-magnitude and not engineering figures. Always verify with the municipality. Not affiliated with any county or state agency. Map data © OpenStreetMap contributors.