Schuylkill County · Washington Township · #2025-12-cve-solar-project-washington-township · Solar farms tracker
CVE solar project, Washington Township
Washington Township, PA · other
In short: CVE solar project, Washington Township is a development project in Washington Township, Schuylkill County, PA. As of November 24, 2026, it is in review. Latest record: Final land development plan reviewed at a meeting of the county planning commission (October 28, 2025). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.
Usually next: a planning commission recommendation, then a vote by the town's governing body.
About this project
Final land development plan for a solar energy facility on two separately owned parcels in Washington Township (Agricultural zoning). Preliminary approval was granted in October 2024. One panel area has been removed from one parcel, and conditional final approval is on the agenda.
County recommendation: Supports, with comments
Issues raised: Limit of disturbance must be shown on LD sheets 200-202, Access and utility easement across both parcels must be shown and drafted, Highway occupancy permit may be needed for access from T-645, Development agreement, schedule and cost estimates required
- Applicant
- CVE
- Engineer / designer
- TRC (Scranton, PA)
- Plan type
- Final land development plan
- Land use
- other
- Zoning
- Agricultural District
Project history
- 2025-10-28 · #2025-12-cve-solar-project-washington-township · Final land development plan
Map pin is approximate.
The full picture AI research · Nov 7, 2026
County records describe a solar energy facility proposed on two separately owned parcels in Washington Township, Schuylkill County. Both parcels are zoned Agricultural. The developer is listed as CVE, and the engineering firm TRC (Scranton) is also named on the filing.
The township granted preliminary approval in October 2024. Since then, one block of solar panels has been removed from one of the parcels. A final land development plan was filed for county review on 2025-10-28, and the county records say conditional final approval is on an agenda.
No news coverage, developer project page, meeting minutes, listing or state permit record was found for this specific project. What is on the site today could not be confirmed. The explanation here rests on the county records alone.
What it could mean nearby
- The records give no traffic, job or utility figures, so the effect on traffic and access is unknown.
- The land is zoned Agricultural, so farmland or open land on the two parcels would likely be converted to a solar use if the plan is built.
- The removal of one panel area suggests the layout was reduced during review, but the records do not say why.
Where it stands
The project has preliminary approval from October 2024. The final land development plan was filed for county review on 2025-10-28, and conditional final approval is on the agenda. If final approval is granted, the usual next steps are meeting any listed conditions, getting stormwater and other permits, and then starting construction.
- Oct 28, 2025 Final land development plan filed for county review
- Oct 2024 Preliminary approval granted
Who's behind it
CVE
Planning terms explained
- Land development plan
- A detailed site plan showing what will be built on a property, including layout, drainage and access, which the municipality reviews and approves.
- Preliminary approval
- An early approval of the overall design that lets the applicant go on to prepare the final plan.
- Conditional final approval
- Final approval that depends on the applicant meeting listed requirements before the plan can be recorded and work can begin.
- Agricultural zoning
- A zoning category meant mainly for farming and open land, where other uses such as solar may be allowed only under certain rules.
We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 7, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
How to comment officially
For this project: The Washington Township supervisors and the Schuylkill County Planning Commission handle land development reviews, and residents can usually comment at their public meetings. Contact the township office for meeting dates.
In Pennsylvania, Washington Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.
- Speak at the Washington Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Washington Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.
Find Washington Township's meeting agendas →
Comments on this page are not sent to officials and are not part of the public record.
What neighbors think
Loading…
Scope estimate for contractors
Not enough detail to estimate.
Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →
More projects nearby
- Three-parcel annexation plan, Washington Townshipsame area · lot line change · Washington Township · filed 2026-06-10
- Annexation plan, Washington Townshipsame area · lot line change · Washington Township · filed 2026-02-11
- Subdivision plan, Washington Township (extension)same area · subdivision (use not stated) · Washington Township · filed 2024-11-13
- Sketch plan for septic easement, Washington Townshipsame area · lot line change · Washington Township · filed 2024-07-15
- Ag operation land development, Washington Twpsame area · agricultural · Washington Township · filed 2026-03-11
- Minor subdivision in Washington Townshipsame area · subdivision (use not stated) · Washington Township · filed 2026-10-14