Schuylkill County · Butler Township · #2026-11-data-center-campus-highridge-park-rd-3-l · Data centers tracker

Data center campus, Highridge Park Rd (3 lots to 1)

North of Highridge Park Road, west of I-81, Butler Township, PA · 1,003,240 sq ft non-residential, data center

In short: Data center campus, Highridge Park Rd (3 lots to 1) is a data center project in Butler Township, Schuylkill County, PA. It would add 1,003,240 sq ft of non-residential space. Its estimated construction value is about $702.3M, a rough estimate from its size. As of November 24, 2026, it is permitted (building or site permits issued). Latest record: Construction stormwater permit PAD540030 issued (June 6, 2026). What usually happens next: site work and construction.

Permitted Construction stormwater permit PAD540030 issued · Jun 6, 2026 · source
  1. Proposed
  2. In review
  3. Approved
  4. PermittedJun 2026
  5. Under construction
  6. Completed

Usually next: site work and construction.

About this project

Consolidates three parcels into one lot north of Highridge Park Road and west of I-81 for a data center campus with two buildings. The site is currently agricultural and would use proposed public water and sewer.

County recommendation: Supports, with comments

Issues raised: UPI certification required, Owner signatures and certification missing, Waiver requests need stated hardship, Public water service letter needed, Public sewer service letter needed

Applicant
LLC / Highridge DC PropCo, LLC
Plan type
Preliminary land development
Land use
data-center
Zoning
I-1 (Industrial District)

Project history

  • 2026-10-01 · #2026-11-data-center-campus-highridge-park-rd-3-l · Preliminary land development · 1,003,240 sq ft
  • 2026-06-06 · Construction stormwater permit PAD540030 issued · source

County plan review office →

Map pin is approximate.

The full picture AI research · Nov 9, 2026

Nebius, an AI computing company, plans a data center campus in the Highridge Industrial Park in Butler Township. The site is north of Highridge Park Road and west of I-81. The filing joins three parcels (about 358 acres, bought from NorthPoint Development) into one lot for two buildings of about 1 million square feet. The maximum campus would be about 600 acres and 1.2 gigawatts. The land is farmland now. The plan calls for public water and sewer.

The first phase is drafted as one single-story and one two-story building. The company targets 260 MW of power by October 2027. Residents have raised concerns about stormwater, water use, noise and oversight. In August 2026 the township extended its data center zoning overlay to more land and lowered the noise limit. That vote was 2-1 and covered zoning only.

The site plan was scheduled for township planning commission review on Oct 22, 2026. No source shows that review's outcome, a final approval, or vertical construction.

What it could mean nearby

Where it stands

A stormwater permit was transferred to the current owner in June 2026, and the site plan was set for planning commission review on Oct 22, 2026. Land development approval from the township supervisors is still needed, and other state permits and building permits would follow. Note: The county record says the stormwater permit was issued Jun 6, 2026, but the state Bulletin shows that date was a transfer to the current owner, and the original permit went to NorthPoint Development in 2023.

Who's behind it

Nebius (Highridge DC PropCo, LLC) · Nebius is an Amsterdam-based AI infrastructure company that builds and operates AI data centers in several US states.

Around the web

Planning terms explained
Land development plan
A detailed site plan the township must approve before building starts.
Data Center Overlay
An added zoning layer that allows data centers on certain land.
Chapter 102 permit
A state erosion and stormwater permit for earth disturbance.
Megawatt (MW)
A measure of electric power; 1,000 MW equals 1 gigawatt.
Closed-loop cooling
A cooling system that recirculates the same water instead of using it once.

Researched by AI from public sources on Nov 9, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: The Butler Township Planning Commission reviews the site plan, then the Board of Supervisors decides; comments can go to the township at its public meetings.

In Pennsylvania, Butler Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

Find Butler Township's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Estimated construction value: $702.3M