[Schuylkill County](https://plannednearby.com/c/schuylkill-pa/) · [Butler Township](https://plannednearby.com/c/schuylkill-pa/butler-township) · #2026-11-data-center-campus-highridge-park-rd-3-l · [Data centers tracker](https://plannednearby.com/topics/data-centers/)

# Data center campus, Highridge Park Rd (3 lots to 1)

North of Highridge Park Road, west of I-81, Butler Township, PA · 1,003,240 sq ft non-residential, data center

In short: **Data center campus, Highridge Park Rd (3 lots to 1)** is a data center project in Butler Township, Schuylkill County, PA. It would add 1,003,240 sq ft of non-residential space. Its estimated construction value is about $702.3M, a rough estimate from its size. As of November 24, 2026, it is permitted (building or site permits issued). Latest record: Construction stormwater permit PAD540030 issued (June 6, 2026). What usually happens next: site work and construction.

Stage: Permitted · Construction stormwater permit PAD540030 issued · Jun 6, 2026 · [source](https://www.pacodeandbulletin.gov/Display/pabull?file=/secure/pabulletin/data/vol56/56-23/799b.html)

Usually next: site work and construction.

## About this project

Consolidates three parcels into one lot north of Highridge Park Road and west of I-81 for a data center campus with two buildings. The site is currently agricultural and would use proposed public water and sewer.

**County recommendation:** Supports, with comments

Issues raised: UPI certification required, Owner signatures and certification missing, Waiver requests need stated hardship, Public water service letter needed, Public sewer service letter needed

- **Applicant:** [LLC / Highridge DC PropCo, LLC](https://plannednearby.com/f/nebius)
- **Plan type:** Preliminary land development
- **Land use:** data-center
- **Zoning:** I-1 (Industrial District)

## Project history

- **2026-10-01** · #2026-11-data-center-campus-highridge-park-rd-3-l · Preliminary land development · 1,003,240 sq ft
- **2026-06-06** · Construction stormwater permit PAD540030 issued · [source](https://www.pacodeandbulletin.gov/Display/pabull?file=/secure/pabulletin/data/vol56/56-23/799b.html)

[County plan review office →](https://www.schuylkillcountypa.gov/departments/planning___zoning/planning_commission_meetings.php)

Map pin is approximate.

## The full picture AI research · Nov 9, 2026

Nebius, an AI computing company, plans a data center campus in the Highridge Industrial Park in Butler Township. The site is north of Highridge Park Road and west of I-81. The filing joins three parcels (about 358 acres, bought from NorthPoint Development) into one lot for two buildings of about 1 million square feet. The maximum campus would be about 600 acres and 1.2 gigawatts. The land is farmland now. The plan calls for public water and sewer.

The first phase is drafted as one single-story and one two-story building. The company targets 260 MW of power by October 2027. Residents have raised concerns about stormwater, water use, noise and oversight. In August 2026 the township extended its data center zoning overlay to more land and lowered the noise limit. That vote was 2-1 and covered zoning only.

The site plan was scheduled for township planning commission review on Oct 22, 2026. No source shows that review's outcome, a final approval, or vertical construction.

### What it could mean nearby

- Traffic: no traffic study was found, but about 1,000 construction jobs are claimed (company figure, via local news), so construction traffic near I-81 is likely.
- Jobs: the company estimates 100-150 permanent jobs.
- Utilities: plans include public water, a well, a new electrical switchyard and substation, and backup generators.
- Noise and stormwater: the township cut its data center noise limit to 65 dBA at the property line, and residents have questioned runoff from the large paved and roofed area.

### Where it stands

A stormwater permit was transferred to the current owner in June 2026, and the site plan was set for planning commission review on Oct 22, 2026. Land development approval from the township supervisors is still needed, and other state permits and building permits would follow. Note: The county record says the stormwater permit was issued Jun 6, 2026, but the state Bulletin shows that date was a transfer to the current owner, and the original permit went to NorthPoint Development in 2023.

- **Oct 22, 2026** Butler Township Planning Commission scheduled to review the site plan (outcome not found)
- **Aug 31, 2026** Supervisors approved the data center overlay expansion (2-1) and a lower noise limit
- **Aug 15, 2026** Nebius presented plans to residents; local news covered their concerns
- **Jun 6, 2026** Bulletin published transfer of stormwater permit PAD540030 to Highridge DC Propco LLC
- **Apr 2026** About 358 acres bought from NorthPoint for $187.5 million
- **Feb 4, 2023** Original stormwater permit to NorthPoint published in the Bulletin

### Who's behind it

[Nebius (Highridge DC PropCo, LLC)](https://nebius.com/schuylkillcountypa) · Nebius is an Amsterdam-based AI infrastructure company that builds and operates AI data centers in several US states.

### Around the web

- [Public hearing notice: Nebius Highridge East Data Center](https://www.noticeregistry.com/pennsylvania/notice/public-hearing-ashland-2481364) — Notice Registry (copy of township notice) · Oct 22, 2026Shows the Oct 22, 2026 planning commission review of the site plan by Highridge DC Prop Co.
- [Nebius Pennsylvania](https://northwiseproject.com/research/nebius-pennsylvania) — Northwise Project · Sep 3, 2026Reports permit PAD540030 went to Highridge DC Propco in June 2026, land-development approval is pending, and Phase 1 is one single-story and one two-story building.
- [Tech company discusses plans for AI factory amid residents' concerns](https://www.wvia.org/news/local/2026-08-15/tech-company-discusses-plans-for-ai-factory-in-schuylkill-county-amid-residents-concerns) — WVIA · Aug 15, 2026Describes the company's plans, job estimates and resident worries about stormwater, water and noise.
- [Highridge Business Park AI Factory](https://nebius.com/schuylkillcountypa) — NebiusGives the 600-acre size, 1.2 GW buildout and 260 MW by October 2027 target.
- [Nebius details plans for 1.2GW data center campus in Pennsylvania](https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/) — DatacenterDynamicsTrade coverage of the campus plans.
- [Pennsylvania Bulletin permit transfer notice](https://www.pacodeandbulletin.gov/Display/pabull?file=/secure/pabulletin/data/vol56/56-23/799.html) — Pennsylvania Bulletin · Jun 6, 2026Shows the June 6 item was a transfer to Highridge DC Propco LLC, not a new issuance.

Planning terms explained

- **Land development plan:** A detailed site plan the township must approve before building starts.
- **Data Center Overlay:** An added zoning layer that allows data centers on certain land.
- **Chapter 102 permit:** A state erosion and stormwater permit for earth disturbance.
- **Megawatt (MW):** A measure of electric power; 1,000 MW equals 1 gigawatt.
- **Closed-loop cooling:** A cooling system that recirculates the same water instead of using it once.

Researched by AI from public sources on Nov 9, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

## How to comment officially

**For this project:** The Butler Township Planning Commission reviews the site plan, then the Board of Supervisors decides; comments can go to the township at its public meetings.

In Pennsylvania, Butler Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

- Speak at the Butler Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Butler Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.

[Find Butler Township's meeting agendas →](https://www.google.com/search?q=Butler+Township+PA+planning+commission+meeting+agenda)

Comments on this page are not sent to officials and are not part of the public record.

## Scope estimate for contractors

Estimated construction value: **$702.3M**

- ~5,016 roofing squares (assumes 2 stories)
- ~2,508 tons of cooling (rule of thumb 400 sq ft/ton)

**Contractor or supplier?** Get projects like this in the counties you work, by email. [Get free contractor alerts →](https://plannednearby.com/contractors)

## More projects nearby

- [Lot annexation on Main Street, Butler Township](https://plannednearby.com/x/schuylkill-lot-annexation-on-main-street-butler-tow-97a512) — same area · lot line change · Butler Township · filed 2024-09-27
- [Lot annexation, 12 Paul Street](https://plannednearby.com/x/schuylkill-lot-annexation-12-paul-street-2234f4) — same area · lot line change · Butler Township · filed 2026-09-11
- [Lot annexation in Butler Township](https://plannednearby.com/x/schuylkill-lot-annexation-in-butler-township-e0a932) — same area · lot line change · Butler Township · filed 2026-04-08
- [Lot annexation, Butler Township](https://plannednearby.com/x/schuylkill-lot-annexation-butler-township-fcb71f) — same area · lot line change · Butler Township · filed 2024-10-09
- [Final annexation plan, Gordon Borough](https://plannednearby.com/x/schuylkill-46-02-013100046-03-0001000) — same area · lot line change · Gordon Borough · filed 2025-05-14
- [Preliminary-final lot annexation, Butler Twp](https://plannednearby.com/x/schuylkill-preliminary-final-lot-annexation-butler-9521fd) — same area · lot line change · Butler Township · filed 2025-12-18

[See everything nearby on a map →](https://plannednearby.com/near#40.76652,-76.35594,Butler%20Township)

---

Source page: https://plannednearby.com/x/schuylkill-data-center-campus-highridge-park-rd-3-l-c7bcae

Data from public planning, zoning and permit records in Pennsylvania, New Jersey and Delaware: county planning commissions, Philadelphia permits and zoning appeals, New Jersey construction permits, Delaware's Preliminary Land Use Service (PLUS) and Pennsylvania DEP stormwater permits, processed automatically. Summaries are written by AI from those records. Estimates are rough order-of-magnitude and not engineering figures. Always verify with the municipality. Not affiliated with any county or state agency. Map data © OpenStreetMap contributors.