# Phased solar arrays, Hubley Township

East Main Street, west of Pine Drive, Hubley Township, PA · other

In short: **Phased solar arrays, Hubley Township** is a development project in Hubley Township, Schuylkill County, PA. As of November 24, 2026, it is in review. Latest record: Minor land development final plan reviewed at a meeting of the county planning commission (October 6, 2025). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.

Stage: In review · Minor land development final plan reviewed at a meeting of the county planning commission · Oct 6, 2025 · [source](https://www.schuylkillcountypa.gov/departments/planning___zoning/planning_commission_meetings.php)

Usually next: a planning commission recommendation, then a vote by the town's governing body.

## About this project

Phased solar panel structures and stormwater facilities on two existing tracts along East Main Street in Hubley Township. The tracts are vacant now and are proposed for agricultural use. The plan creates no new lots.

**County recommendation:** Supports, with comments

Issues raised: Highway occupancy permit needed for two driveways onto East Main Street (SR 0025), Engineer/surveyor seal and certification missing, Owner signatures and notarization missing, Two stamped copies needed for recording

- **Applicant:** [Triple R Farm, LLC](https://plannednearby.com/f/triple-r-farm-llc)
- **Plan type:** Minor land development final plan
- **Land use:** other
- **Zoning:** A-Agricultural

## Project history

- **2025-10-06** · #2025-12-phased-solar-arrays-hubley-township · Minor land development final plan

[County plan review office →](https://www.schuylkillcountypa.gov/departments/planning___zoning/planning_commission_meetings.php)

Map pin is approximate.

## The full picture AI research · Nov 7, 2026

The plan is for phased solar panel structures and stormwater facilities on two existing tracts along East Main Street, west of Pine Drive, in Hubley Township. The landowner on the filing is Triple R Farm, LLC. The tracts are vacant now, and the county summary says they are proposed for agricultural use. The plan creates no new lots and no homes.

The county filing describes a minor land development final plan. County planners received it for review on 2025-10-06. That is the latest step in the records.

No news coverage, township meeting records, developer page, listing, permit record or construction notice was found for this site. The county facts are the only information available, so the current condition of the land is unknown.

### What it could mean nearby

- Solar arrays usually generate little traffic once running. Construction could bring temporary truck and equipment trips on East Main Street.
- The plan creates no new lots or homes, so it adds no new school students or household demand for utilities.
- Stormwater facilities are part of the plan, so drainage design is a likely point of review.

### Where it stands

The final plan was filed for county review on 2025-10-06, and no later approval, permit or construction was found. After review, the plan normally goes to the township for a decision, and site and stormwater permits come before any building.

- **Oct 6, 2025** Minor land development final plan filed for county review

### Who's behind it

Triple R Farm, LLC

Planning terms explained

- **Minor land development:** A small building or site project that goes through formal plan review but does not subdivide the land into several lots.
- **Final plan:** The detailed plan submitted for last review and approval before work can start.
- **Stormwater facilities:** Basins, swales or similar features that collect and slow rain runoff from a site.

We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 7, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

## How to comment officially

**For this project:** The Hubley Township supervisors and planning commission, along with the Schuylkill County planning office, handle the plan. Residents can comment at their public meetings, but no meeting dates were found.

In Pennsylvania, Hubley Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

- Speak at the Hubley Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Hubley Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.

[Find Hubley Township's meeting agendas →](https://www.google.com/search?q=Hubley+Township+PA+planning+commission+meeting+agenda)

Comments on this page are not sent to officials and are not part of the public record.

## Scope estimate for contractors

Not enough detail to estimate.

**Contractor or supplier?** Get projects like this in the counties you work, by email. [Get free contractor alerts →](https://plannednearby.com/contractors)

## More projects nearby

- [Parcel A subdivision, Hubley Township](https://plannednearby.com/x/schuylkill-2025-06-parcel-a-subdivision-hubley-township) — same area · subdivision (use not stated) · Hubley Township · filed 2025-06-11
- [Minor land development final plan, Hubley Township](https://plannednearby.com/x/schuylkill-minor-land-development-final-plan-hubley-0adbac) — same area · other · Hubley Township · filed 2025-11-12
- [Final land development, Hubley Township](https://plannednearby.com/x/schuylkill-815) — same area · other · Hubley Township · filed 2026-03-11
- [Subdivision and lot annexation, Hubley](https://plannednearby.com/x/schuylkill-45-07-0059000) — same area · lot line change · Hubley Township · filed 2026-02-11
- [Preliminary/final subdivision in Hubley Township](https://plannednearby.com/x/schuylkill-preliminary-final-subdivision-in-hubley-df8507) — same area · subdivision (use not stated) · Hubley Township · filed 2025-03-12
- [Property consolidation, Hubley Township](https://plannednearby.com/x/schuylkill-2024-11-property-consolidation-hubley-township) — same area · lot line change · Hubley Township · filed 2024-11-13

[See everything nearby on a map →](https://plannednearby.com/near#40.63118,-76.63223,Hubley%20Township)

---

Source page: https://plannednearby.com/x/schuylkill-phased-solar-arrays-hubley-township-0adbac

Data from public planning, zoning and permit records in Pennsylvania, New Jersey and Delaware: county planning commissions, Philadelphia permits and zoning appeals, New Jersey construction permits, Delaware's Preliminary Land Use Service (PLUS) and Pennsylvania DEP stormwater permits, processed automatically. Summaries are written by AI from those records. Estimates are rough order-of-magnitude and not engineering figures. Always verify with the municipality. Not affiliated with any county or state agency. Map data © OpenStreetMap contributors.