# Ridge Road solar sites 3-9, West Penn Township

Ridge Road, West Penn Township, PA · other

In short: **Ridge Road solar sites 3-9, West Penn Township** is a development project in West Penn Township, Schuylkill County, PA. As of November 24, 2026, it is approved according to web research. Latest record: A Times News report from August 2025 says the township supervisors voted unanimously to conditionally approve the final plan for the 79-acre, ~33,000-panel… What usually happens next: building and stormwater permits; site work often starts within 3 to 12 months.

Stage: Approved · A Times News report from August 2025 says the township supervisors voted unanimously to conditionally approve the final plan for the 79-acre, ~33,000-panel Ridge Road Solar project. · web research checked Nov 14, 2026 · [source](https://www.tnonline.com/20250814/west-penn-gives-ok-for-large-solar-field/) AI research

Usually next: building and stormwater permits; site work often starts within 3 to 12 months.

## About this project

Preliminary land development plan by Bollinger Solar LLC for solar sites 3 through 9 on Ridge Road in West Penn Township. The agenda gives no acreage or other details.

- **Applicant:** [Bollinger Solar LLC](https://plannednearby.com/f/bollinger-solar-llc)
- **Plan type:** Preliminary land development
- **Land use:** other

## Project history

- **2024-11-13** · #2024-11-ridge-road-solar-sites-3-9-west-penn-tow · Preliminary land development

[County plan review office →](https://www.schuylkillcountypa.gov/departments/planning___zoning/planning_commission_meetings.php)

Map pin is approximate.

## The full picture AI research · Nov 14, 2026

Bollinger Solar LLC proposed a solar farm on Ridge Road in West Penn Township, near Ash Circle. News coverage says it covers about 79 acres and would hold roughly 33,000 panels. One report describes seven linked panel fields behind an 8-foot fence. The county's 2024 agenda gave no size or details.

The township supervisors tabled the final plan in July 2025 because they wanted a plan for removing the panels at the end of their life. The developer then submitted a decommissioning agreement, a land development agreement and a stormwater agreement. The supervisors gave conditional approval to the final plan in August 2025.

No construction notice, permit record or opposition was found. The project adds no homes.

### What it could mean nearby

- The site is about 79 acres of panels behind a fence, which changes the look of the land for nearby neighbors.
- The decommissioning agreement is meant to make sure the panels are removed when the project ends.
- A stormwater agreement was required, which covers how rain runoff from the site is handled.
- Solar farms usually bring little regular traffic once built, but no traffic study was found for this site.

### Where it stands

The township supervisors gave conditional approval to the final plan in August 2025. Next steps usually are meeting the remaining conditions, then obtaining state stormwater and local construction permits before work begins. No source shows whether those have happened. Note: The county's 2024 agenda gave no size or details, but later news coverage reports 79 acres and about 33,000 panels, and one search summary put the supervisors' tabling vote and final-plan approval in 2024 while the dated article places them in 2025.

- **May 2026** A news report recaps the August 2025 conditional approval of the final plan.
- **Sep 2025** Bollinger Solar's Towamensing Township solar request was denied by that township's zoning board, per Times News.
- **Aug 2025** Supervisors gave conditional approval to the final plan after the developer submitted the decommissioning, land development and stormwater agreements.
- **Jul 2025** Supervisors tabled the final plan vote pending a decommissioning plan.
- **Nov 13, 2024** County planning commission reviewed the preliminary land development plan for solar sites 3-9.

### Who's behind it

Bollinger Solar LLC · A solar developer named in news coverage for projects in West Penn Township, Franklin Township (about 9 acres, conditionally approved in August 2024) and Towamensing Township (zoning board denial in September 2025).

### Around the web

- [West Penn gives OK for large solar field](https://www.tnonline.com/20250814/west-penn-gives-ok-for-large-solar-field/) — Times News · Aug 14, 2025Reports 79 acres, about 33,000 panels, and conditional final plan approval after the decommissioning, land development and stormwater agreements.
- [Times News report on Bollinger Solar projects](https://www.tnonline.com/?p=276203) — Times News · Sep 30, 2025Describes the tabled July vote and Bollinger Solar's Towamensing and Franklin Township projects.
- [West Penn Township supervisors report](https://www.tnonline.com/?p=282942) — Times News · May 21, 2026Recaps the August conditional approval of the Ridge Road Solar final plan and says nothing about construction.
- [Planning Commission Meetings](https://www.schuylkillcountypa.gov/departments/planning___zoning/planning_commission_meetings.php) — Schuylkill County · Nov 13, 2024County listing for the preliminary plan review.

Planning terms explained

- **Land development plan:** A detailed site plan showing what will be built and how it meets local rules.
- **Conditional approval:** Approval that depends on the developer meeting listed requirements.
- **Decommissioning plan:** A plan for removing the solar panels and restoring the land when the project ends.
- **Stormwater agreement:** A commitment to manage rain runoff from the site so it doesn't harm neighbors or streams.

Researched by AI from public sources on Nov 14, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

## How to comment officially

**For this project:** The West Penn Township supervisors decide township-level matters and meet publicly, so residents can comment at their meetings or through the township office.

In Pennsylvania, West Penn Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

- Speak at the West Penn Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the West Penn Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.

[Find West Penn Township's meeting agendas →](https://www.google.com/search?q=West+Penn+Township+PA+planning+commission+meeting+agenda)

Comments on this page are not sent to officials and are not part of the public record.

## Scope estimate for contractors

Not enough detail to estimate.

**Contractor or supplier?** Get projects like this in the counties you work, by email. [Get free contractor alerts →](https://plannednearby.com/contractors)

## More projects nearby

- [Lot line adjustment, West Penn Township](https://plannednearby.com/x/schuylkill-2024-07-lot-line-adjustment-west-penn-township) — same area · lot line change · West Penn Township · filed 2024-07-15
- [Annexation II plan, West Penn Township](https://plannednearby.com/x/schuylkill-annexation-ii-plan-west-penn-township-b47dd6) — same area · lot line change · West Penn Township · filed 2025-11-12
- [Subdivision at 453 Pine Hill Road](https://plannednearby.com/x/schuylkill-subdivision-at-453-pine-hill-road-0decdf) — same area · subdivision (use not stated) · West Penn Township · filed 2025-06-11
- [2-lot subdivision, West Penn Township](https://plannednearby.com/x/schuylkill-2024-08-2-lot-subdivision-west-penn-township) — same area · subdivision (use not stated) · West Penn Township · filed 2024-08-14
- [Minor subdivision final plan, West Penn Township](https://plannednearby.com/x/schuylkill-2025-06-minor-subdivision-final-plan-west-penn-t) — same area · subdivision (use not stated) · West Penn Township · filed 2025-06-11
- [Final land development, West Penn Township](https://plannednearby.com/x/schuylkill-2024-07-final-land-development-west-penn-townshi) — same area · other · West Penn Township · filed 2024-07-15

[See everything nearby on a map →](https://plannednearby.com/near#40.74344,-75.92213,West%20Penn%20Township)

---

Source page: https://plannednearby.com/x/schuylkill-ridge-road-solar-sites-3-9-west-penn-tow-1d8118

Data from public planning, zoning and permit records in Pennsylvania, New Jersey and Delaware: county planning commissions, Philadelphia permits and zoning appeals, New Jersey construction permits, Delaware's Preliminary Land Use Service (PLUS) and Pennsylvania DEP stormwater permits, processed automatically. Summaries are written by AI from those records. Estimates are rough order-of-magnitude and not engineering figures. Always verify with the municipality. Not affiliated with any county or state agency. Map data © OpenStreetMap contributors.