Schuylkill County · Porter Township · #2025-03-solar-facility-land-development-porter-t · Solar farms tracker
Solar facility land development, Porter Township
Access from Clarks Valley Road (SR 0325), Porter Township, PA · other · 40.0 acres
In short: Solar facility land development, Porter Township is a development project at Access from Clarks Valley Road (SR 0325) in Porter Township, Schuylkill County, PA. The site is 40.0 acres. As of November 24, 2026, it is in review. Latest record: Final land development plan (now major preliminary) reviewed at a meeting of the county planning commission (March 12, 2025). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.
Usually next: a planning commission recommendation, then a vote by the town's governing body.
About this project
A solar energy facility on two lease areas of 7.2 and 5.4 acres within a 39.95-acre parcel in Porter Township. The county review asked for more detail on grading, stormwater, and the driveway permit before final approval.
County recommendation: No position
Issues raised: Disturbance area of 19,515 sq ft (about 4%) looks unrealistic, Stormwater calcs cover only 2-yr volume, not peak flow or detention, PennDOT highway occupancy permit needed for Clarks Valley Road, Grading and stabilization plans needed for steep areas and access roads, Conservation District and DEP E&S/PCSM approvals needed
- Engineer / designer
- Burget & Associates, Inc.
- Plan type
- Final land development plan (now major preliminary)
- Land use
- other
- Zoning
- Agricultural District
Project history
- 2025-03-12 · #2025-03-solar-facility-land-development-porter-t · Final land development plan (now major preliminary)
Map pin is approximate.
The full picture AI research · Nov 14, 2026
A solar energy facility is proposed on two lease areas, of 7.2 and 5.4 acres, inside a 39.95-acre parcel in Porter Township, Schuylkill County. Access would be from Clarks Valley Road (SR 0325). The county records list Burget & Associates, Inc. on the filing.
The county planning commission reviewed the plan on 2025-03-12. It asked for more detail on grading, stormwater and the driveway permit before final approval. The plan was also reclassified from a final plan to a major preliminary plan.
Six web searches found no news coverage, township minutes, developer page, listing or state permit record for this site. Nothing shows whether construction has started, so the county record is the latest known status.
What it could mean nearby
- Access would be from Clarks Valley Road, a state road, so a driveway permit is needed. The county review specifically asked for more detail on it.
- The county asked for more detail on grading and stormwater, so runoff control is a review issue.
- Only about 12.6 acres of the 39.95-acre parcel are leased for solar, so the rest of the parcel is not part of the leased area.
Where it stands
The plan was under county planning commission review as of 2025-03-12, with a request for more detail on grading, stormwater and the driveway permit. A revised plan would normally go back through review, and the township supervisors would then decide on approval.
- Mar 12, 2025 County planning commission reviewed the plan, now treated as a major preliminary land development plan
Around the web
- Planning Commission MeetingsSchuylkill County · Mar 12, 2025This is the county meeting index. The page text does not describe individual agenda items, so the project details come from the county record supplied.
Planning terms explained
- Land development plan
- A detailed site plan showing what will be built on a parcel, which the township must approve.
- Major preliminary plan
- An early formal stage for a larger project. It is reviewed in detail before the final plan is approved.
- Lease area
- The part of a larger parcel that a solar company rents from the landowner for its equipment.
- Stormwater
- Rain runoff from roofs, panels and driveways that has to be managed so it does not flood neighbors or erode soil.
- Driveway permit
- State approval, here from PennDOT, for a new entrance onto a state road such as SR 0325.
We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 14, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
How to comment officially
For this project: The Porter Township supervisors normally decide on land development plans, and residents can usually comment at their public meetings. The county planning commission only gives advice.
In Pennsylvania, Porter Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.
- Speak at the Porter Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Porter Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.
Find Porter Township's meeting agendas →
Comments on this page are not sent to officials and are not part of the public record.
What neighbors think
Loading…
Scope estimate for contractors
Not enough detail to estimate.
Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →
More projects nearby
- Annexation final plan in Porter Townshipsame area · lot line change · Porter Township · filed 2025-03-12
- Minor subdivision at 32 VPT Roadsame area · subdivision (use not stated) · Porter Township · filed 2026-04-08
- Subdivision and annexation in Porter Townshipsame area · lot line change · Porter Township · filed 2026-04-08
- Major land development preliminary plan, Porter Twpsame area · other · Porter Township · filed 2025-04-09
- Solar energy facility, Porter Townshipsame area · other · Porter Township · filed 2026-02-11
- Major land development final plan, Porter Townshipsame area · other · Porter Township · filed 2025-10-08