About this project

A preliminary subdivision and land development plan for a 252,000-square-foot industrial warehouse on 53.2 acres in Carroll Township.

County recommendation: Consistent with county plan

Engineer / designer
Hyland Engineering
Plan type
Preliminary Subdivision Land development
Land use
Industrial
Water
Public water
Sewer
Public sewer

Filing history

  • 2024-03-01 · #24-0037 · Preliminary Subdivision Land development · 252,000 sq ft

County plan review office →

The full picture AI research · Nov 1, 2026

County records describe a proposed industrial warehouse of about 252,000 square feet on roughly 53 acres in Carroll Township, near Dillsburg. That is a little more than five acres of floor space per ten acres of land, about the size of four to five football fields under one roof. The records do not say what is on the land now, and they do not name a tenant.

The filing is a preliminary subdivision and land development plan. This is an early, detailed design stage in which the township reviews the building layout, driveways, stormwater controls and lot lines. The engineering firm on the filing is Hyland Engineering.

No news coverage, developer project page, or township agenda or minutes could be tied clearly to this project. Other warehouse proposals exist along the York Road corridor, but nothing confirmed they are the same project. They are not described here.

What it could mean nearby

Where it stands

The latest county filing, dated March 2024, was a preliminary plan, so the project was in early township review. Usually the township's planning commission and board of supervisors review the plan next, followed by a final plan and permits before construction. Its current status could not be confirmed online.

Want to weigh in? In Pennsylvania townships, the board of supervisors normally decides land development plans after the planning commission reviews them, and residents can comment at their public meetings; check the Carroll Township website for agendas.

Planning terms explained
Preliminary plan
An early, detailed version of a development plan that the township reviews before a final plan is approved.
Land development
The legal term for building or enlarging a structure or site, such as a warehouse, in a way that needs township plan review.
Subdivision
Dividing a property into separate lots or changing its boundaries.
Stormwater management
Features such as basins that control rain runoff from roofs and pavement so it does not flood neighbors.

We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $32.8M

Contractor or supplier? Get projects like this in the counties you work, by email. Join contractor early access →