Monarch Products Building Expansion
Conewago Township, PA · 13,064 sq ft non-residential, industrial · 19.5 acres
About this project
A preliminary-final land development in Conewago Township proposes a 13,064-square-foot building addition on a 19.5-acre industrial site.
County recommendation: Consistent with county plan
- Engineer / designer
- Landworks Civil Design, LLC
- Plan type
- Preliminary Final Land development Building addition
- Land use
- Industrial
- Water
- Public water
- Sewer
- Public sewer
Filing history
- 2024-05-28 · #24-0108 · Preliminary Final Land development Building addition · 13,064 sq ft
The full picture AI research · Nov 1, 2026
The plan is to add a 13,064-square-foot addition to an existing industrial building owned by Monarch Products. The company's site covers about 19.5 acres in Conewago Township, York County. For scale, the addition is roughly the floor area of five or six average houses.
Township planning commission minutes from mid-2024 show the plan under review. The commission looked at a combined preliminary and final land development plan in June 2024. In July 2024 the project's civil design firm presented it and said it had answered an earlier review letter that covered many issues. No news coverage, opposition, or approval decision was found. No information on how the expansion will be used was found either.
What it could mean nearby
- The addition is small next to the 19.5-acre site, so a large change in activity is unlikely, but the records give no traffic or job figures.
- The work is on a property that is already industrial, so no new homes or school impact is indicated.
Where it stands
The plan was reviewed by the township planning commission in mid-2024, and the county's latest filing is dated 2024-05-28. The sources found do not show a final approval. After review, the township supervisors normally vote on approval, and construction permits follow once any conditions are met.
- Jul 22, 2024 Township planning commission discussed the Monarch building expansion with the project's design firm.
- Jun 24, 2024 Planning commission received the preliminary/final land development plan for review.
- May 28, 2024 Latest filing recorded by the county.
Want to weigh in? The Conewago Township Board of Supervisors would decide on the plan, and comments can be made at its public meetings or to the planning commission, which meets monthly. Check the township website for agendas.
Who's behind it
Monarch Products · Monarch Products is the industrial site owner proposing the addition, with civil design by Landworks Civil Design, LLC.
Around the web
- Conewago Township Planning Commission minutes, July 22, 2024Conewago Township · Jul 22, 2024Records the design firm's presentation of the Monarch building expansion and its response to an earlier review letter.
- Conewago Township Planning Commission minutes, June 24, 2024Conewago Township · Jun 24, 2024Shows the preliminary/final land development plan was submitted and briefly reviewed alongside a township engineer's comment letter.
Planning terms explained
- Land development plan
- A detailed site plan the township reviews before it allows new buildings or additions on a property.
- Preliminary/final plan
- A combined review that merges the two usual approval stages into one, common for small projects.
- Planning commission
- An appointed local board that reviews plans and advises the elected supervisors.
- Review letter
- A township engineer's list of comments the applicant must address before approval.
Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
Scope estimate for contractors
Estimated construction value: $1.7M
- ~130 roofing squares (assumes 1 story)
- ~32 tons of cooling (rule of thumb 400 sq ft/ton)
Contractor or supplier? Get projects like this in the counties you work, by email. Join contractor early access →