York County · Springettsbury Township · #25-0162
Molimo, LLC Building Addition
Springettsbury Township, PA · 20,000 sq ft non-residential, industrial · 9.0 acres
About this project
Preliminary final land development for a 20,000-square-foot industrial building addition on a 9-acre site in Springettsbury Township.
County recommendation: Consistent with county plan
- Engineer / designer
- Site Design Concepts
- Plan type
- Preliminary Final Land development Building addition
- Land use
- Industrial
- Water
- Public water
- Sewer
- Public sewer
Filing history
- 2025-08-14 · #25-0162 · Preliminary Final Land development Building addition · 20,000 sq ft
The full picture AI research · Nov 1, 2026
Molimo, LLC has filed a plan with York County for a 20,000-square-foot addition to an industrial building in Springettsbury Township. The addition would be on a site of about 9 acres. County records describe the filing as a preliminary final land development plan, which is a detailed site plan the township reviews before allowing construction.
The records don't say what the building is used for now, what the addition would be used for, or who would occupy it. The search found no news coverage, township meeting agendas or minutes, hearing notices, or developer webpages that clearly refer to this project. No opposition or approvals were found online. The most recent county filing is dated August 14, 2025. A site design firm, Site Design Concepts, is listed on the filing.
What it could mean nearby
- The addition is small, about 20,000 square feet, on a 9-acre site. The records don't show a major change in traffic, but they don't include a traffic study either.
- The records don't mention new homes, jobs, schools or utility changes.
Where it stands
The plan was last filed with the county on 2025-08-14 and appears to be under township and county review. After that review, the township supervisors usually vote to approve, conditionally approve or deny the plan. No township action on this project was found online.
- Aug 14, 2025 Latest county filing for the preliminary final land development plan
Want to weigh in? The Springettsbury Township planning commission and board of supervisors usually review land development plans at public meetings. Residents can ask the township for agendas and comment at those meetings.
Who's behind it
Molimo, LLC
Planning terms explained
- Land development
- A formal township review of plans to build or expand a building and its parking, drainage and access.
- Preliminary final plan
- A single plan submission that the township reviews as both the preliminary and the final plan.
- Industrial
- A use category for manufacturing, warehousing and similar businesses.
We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
Scope estimate for contractors
Estimated construction value: $2.6M
- ~200 roofing squares (assumes 1 story)
- ~50 tons of cooling (rule of thumb 400 sq ft/ton)