Montgomery County · Lower Salford · MCPC #22-0229-003
SCK2 Group at Vernfield
841 Main Street, Lower Salford, PA · 10 homes, townhomes · 1.39 acres
About this project
The owner plans to build 10 homes in five buildings on the 1.39-acre lot at 841 Main Street in Lower Salford Township. The project adds a new parking lot, a sidewalk along Main Street, and a walkway linking the sidewalk to the parking and homes. The existing two-and-a-half-story house on the property will stay.
County planning commission: Supports, with comments
Issues raised: 50-foot driveway curb radius lengthens pedestrian crossing, parking in front of new buildings conflicts with VC district rules, stormwater concentrated flow to Main Street swale could cause icing
- Applicant
- SCK2 Group LLC
- Engineer / rep.
- S.T.A. Engineering, Inc.
- Zoning
- VC
- Cross street
- COVENANT LANE
- Utilities
- public water, public sewer
Filing history
- 2025-02-26 · MCPC #22-0229-003 · Land Dev Plan, Prelim Plan, Resubmission · 10 homes
- 2022-11-07 · MCPC #22-0229-002 · Land Dev Plan, Prelim Plan · 6 homes · 4,800 sq ft
- 2022-08-29 · MCPC #22-0229-001 · Land Dev Plan, Sketch Plan · 6 homes · 4,800 sq ft
County review letters
2025-02-26 · LSALF 22-0229-003r.pdf
The full picture AI research · Nov 1, 2026
SCK2 Group LLC proposes 10 townhomes in five buildings on a 1.39-acre lot at 841 Main Street in the Vernfield area of Lower Salford Township. The existing two-and-a-half-story house on the lot would stay.
The plan adds a new parking lot, a sidewalk along Main Street, and a walkway linking that sidewalk to the parking area and the homes.
No news coverage, developer project page or readable township minutes about this specific townhome plan were found. Township records may show an earlier plan for the same address with a different mix of uses, but that could not be confirmed. This summary therefore relies on the county filing alone.
What it could mean nearby
- Ten new households would add some traffic on Main Street. The records reviewed do not include a traffic study.
- The new sidewalk along Main Street would add pedestrian infrastructure at the site.
- Keeping the existing house preserves part of the property's current appearance.
Where it stands
The latest county filing is dated February 26, 2025. It suggests the plan is in township and county review. Next steps usually include review by the township planning commission and a vote by the township supervisors on land development approval. The current status could not be confirmed online.
- Feb 26, 2025 Latest county planning filing for the project
Want to weigh in? The Lower Salford Township planning commission and board of supervisors would normally review the plan at public meetings. Residents can comment there or contact the township office.
Who's behind it
SCK2 Group LLC
Planning terms explained
- Land development
- The township's formal review of a site plan showing new buildings, parking and other site improvements.
- Townhomes
- Attached homes that share side walls and are grouped into buildings.
- Planning commission
- A volunteer township board that reviews development plans and advises the elected supervisors.
We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
Scope estimate for contractors
Estimated construction value: $3.7M
- ~140 roofing squares
- ~10 HVAC systems
- ~10 kitchens / 20+ bathrooms
- ~20,000 sq ft of finished living space
- ~1.0 acres of site work (grading, stormwater, landscaping)
- New parking lot
- New sidewalk along Main Street frontage
- Walkway connecting sidewalk to parking and homes
- Driveway entrance and curb work
- Stormwater swale mitigation such as level spreader or vegetation
Contractor or supplier? Get projects like this in the counties you work, by email. Join contractor early access →