Montgomery County · Worcester · MCPC #25-0008-002
Methacton High School Redevelopment
1001 Kriebel Mill Rd, Worcester, PA · 100,000 sq ft non-residential, school · 62.83 acres
About this project
The Methacton School District is rebuilding the west wing of its high school at 1001 Kriebel Mill Road in Worcester, demolishing the existing structure and constructing a new approximately 86,000-square-foot building with classrooms, auditorium, natatorium, and performing arts rooms. The project also includes expanded parking areas, a renovated bus loop, and improved athletic fields.
County planning commission: Supports, with comments
Issues raised: new sidewalks needed on Kriebel Mill Road and in parent drop-off area, parking lot shade tree coverage insufficient, student capacity reduced by approximately 200 students despite potential future enrollment growth
- Engineer / rep.
- T and M Associates
- Zoning
- AGR
- Tax parcel
- 67-00-01393-00-7
- Cross street
- Germantown Pike
- Approvals needed
- variance
- Utilities
- public water, public sewer
- Demolition
- west wing of the existing high school building and one access driveway
Filing history
- 2026-06-01 · MCPC #25-0008-002 · Land Dev Plan, Prelim Plan · 100,000 sq ft
- 2025-01-14 · MCPC #25-0008-001 · Land Dev Plan, Sketch Plan · 312,000 sq ft
County review letters
2025-01-14 · WORCE 25-0008-001r.pdf
2026-06-01 · WORCE 25-0008-002r.pdf
The full picture AI research · Nov 1, 2026
The Methacton School District plans to rebuild part of Methacton High School at 1001 Kriebel Mill Road in Worcester. County records describe demolishing the west wing and building a new wing of roughly 86,000 square feet. The new wing would hold classrooms, an auditorium, a swimming pool area (natatorium) and performing arts rooms. The same filing covers more parking, a renovated bus loop and improved athletic fields on the 62.83-acre campus.
The school district's own project page describes a broader renovation. It lists a new classroom wing with a fabrication lab, a new auditorium, an 8-lane pool and wellness center, a new front entrance, and traffic and parking changes. It also lists upgrades to the existing building's heating, cooling, roofing and fire systems. The district estimates the cost at about $113 to $114 million, paid with 30-year bonds that will require a tax increase. The high school dates to 1961. No news coverage or township records specific to this filing were found.
What it could mean nearby
- Construction is planned in phases from mid-2027 to about summer 2030, so students, staff and neighbors may see construction activity and changed entrances and parking during that time.
- The district says traffic flow and parking improvements are part of the work, and the county filing mentions a renovated bus loop.
- Athletic field improvements and a new pool and wellness center may add campus facilities, though public access is not stated in the sources found.
- Funding through district bonds means a school tax increase, according to the district.
Where it stands
The school board approved moving to the construction documents (final design drawings) phase on August 25, 2026, and the county filing is dated June 2026. Bidding is expected in early 2027, and Worcester Township's land-development review is a likely step, but its status was not confirmed.
- May 2027 Construction projected to start, with completion around summer 2030
- Feb 2027 Bidding projected to begin
- Oct 28, 2026 Public hearing required for school construction projects (Act 34) tentatively scheduled; whether it took place was not confirmed
- Aug 25, 2026 School board approved advancing the project to the construction documents phase
- Jun 1, 2026 Latest county planning filing
- Feb 24, 2026 School board approved moving into the design development phase
Want to weigh in? The Methacton Board of School Directors decides on the project and takes public comment at its meetings, and Worcester Township's planning commission and supervisors are expected to review the site plans.
Who's behind it
Methacton School District · The public school district serving the Worcester area. It is the owner and sponsor of this project, and T and M Associates is the firm named on the county filing.
Around the web
- Methacton High School Renovation ProjectMethacton School DistrictThe district describes the project scope, cost of about $113 to $114 million, bond funding, the August 2026 approval and a construction timeline running to 2030.
- MHS Campus Planning Project JourneyMethacton School DistrictThe district outlines how it moved from a possible full rebuild to a renovation with new construction, and the planning steps in between.
Planning terms explained
- Act 34 hearing
- A public hearing that Pennsylvania requires before a school district proceeds with a major construction project, where residents can comment on scope, cost and need.
- Design development
- A design phase in which the building's layout, systems and materials are refined before final drawings.
- Construction documents
- The detailed final drawings and specifications that contractors use to bid on and build the project.
- Natatorium
- A building or room that houses an indoor swimming pool.
- Land development review
- The township's review of site plans for new buildings, parking and drainage before permits are issued.
Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
Scope estimate for contractors
Estimated construction value: $35.0M
- ~500 roofing squares (assumes 2 stories)
- ~250 tons of cooling (rule of thumb 400 sq ft/ton)
- ~17.6 acres of site work (grading, stormwater, landscaping)
- Natatorium
- Performing arts rooms
- Auditorium
- Parking lot expansion
- New bus loop
- Stormwater management system