A data center complex will replace the former GlaxoSmithKline pharmaceutical facility at 411 Swedeland Road. The developer will construct four 2-story data center buildings with offices, two central utility plants, and associated infrastructure totaling 1.7 million square feet on the 141.87-acre site.

County planning commission: Raises serious concerns

Issues raised: Does not comply with township's newly adopted data center ordinance, Special Exception required for data center use determination, Will Serve letters needed for public water and wastewater, Partial property in R-1 residential district with adjacent homes on Jones Road, Data centers not anticipated in Comprehensive Plan; additional standards needed, Five related data center proposals in area total 4.6+ million square feet

Applicant
Innovation 411 Fee Owner LLC
Engineer / rep.
Edward B. Walsh & Associates, Inc.
Zoning
LI and HI
Cross street
Renaissance Blvd & Jones Rd
Approvals needed
Special Exception for data center use, Will Serve letters for public water and wastewater
Utilities
public water, public sewer
Demolition
All existing structures on the site including the former GlaxoSmithKline complex (office, laboratory, manufacturing, research facilities), parking areas, closed quarries/landfills, helipad, and sports courts

Filing history

  • 2026-03-12 · MCPC #26-0063-001 · Land Dev Plan, Prelim Plan · 1,677,800 sq ft

View all filings on the county site →

The full picture AI research · Nov 1, 2026

A data center complex is proposed for the 141.87-acre former GlaxoSmithKline pharmaceutical campus at 411 Swedeland Road in Upper Merion. The plan has four 2-story data center buildings with offices and two central utility plants. In total it is about 1.7 million square feet.

The site is now a pharmaceutical and life-sciences campus. News coverage says GSK still operates there as a tenant. The site is one of five data center sites proposed by the developer MLP Ventures in the township.

The proposal drew strong resident opposition at public meetings. In August 2026 the township supervisors voted to deny extensions and preliminary plans for all five sites. The developer then sued the township. No occupant was identified in the sources found.

What it could mean nearby

Where it stands

The township supervisors denied the plans in August 2026, and the developer has sued over the review process and an extension. The case is in court, so the next step is likely a ruling or an appeal. Any approval would need further review.

Want to weigh in? Decisions now rest with the court because of the lawsuit; any renewed plan would return to the Upper Merion planning commission and Board of Supervisors, whose public meetings accept comment.

Who's behind it

MLP Ventures (county filing lists Innovation 411 Fee Owner LLC as owner) · News coverage identifies MLP Ventures as the developer that bought the site from GSK and also owns a life sciences company.

Around the web

Planning terms explained
Land development application
A formal request to the township to approve a site plan for building on a property.
Preliminary approval
An early approval step that must be followed by final approval before construction.
Planning commission
A township advisory board that reviews plans and recommends action to the elected supervisors.
Limited Industrial (LI) zoning
A zoning category that permits certain lighter industrial uses.
Central utility plant
A building housing the power and cooling equipment that serves the main buildings.

Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $1.2B

Contractor or supplier? Get projects like this in the counties you work, by email. Join contractor early access →